ITEM: |
DISCUSSION ITEM |
||||
|
|||||
20. |
DISCUSSION OF PURE
WATER MONTEREY PROJECT CALIFORNIA PUBLIC UTILITIES COMMISSION SETTLEMENT
AGREEMENT CRITERIA |
||||
|
|||||
Meeting Date: |
November 16, 2015 |
Budgeted: |
N/A |
||
|
|||||
From: |
David J. Stoldt |
Program/ |
|
||
|
General Manager |
Line Item
No.: |
|||
|
|||||
Prepared By: |
David J. Stoldt |
Cost Estimate: |
|
||
|
|||||
General Counsel Approval: N/A |
|||||
Committee Recommendation: N/A |
|||||
CEQA
Compliance: N/A |
|||||
SUMMARY: In
July 2013, the District participated with the various parties to A.12-04-019 at
the Public Utilities Commission – the Cal-Am application – in developing a
settlement and agreement for the proposed Monterey Peninsula Water Supply
Project (MPWSP.) The MPWMD Board of
Directors provided direction in closed session whether to approve and sign the
settlement agreement(s). The District
and other settling parties signed the agreements July 31, 2013.
At its January 30, 2013 and February 12, 2013 meetings the District Board
indicated that it would consider support for the Cal-Am application if certain
conditions were met. One of those
conditions the Board proposed was a strong statement endorsing the Pure Water
Monterey groundwater replenishment project (GWR). This was addressed in the General Settlement
Agreement, Section 4, and included 9 findings or criteria for the acceptance of
GWR as part of the MPWSP. In the
Settlement, the Parties agreed “the Commission should make the GWR Decision
based upon the findings set forth below and/or information supplied pursuant to
the advice letter process in Section 4.3(f). If all of the findings are made or
addressed through the advice letter process, then California American Water
shall be ordered to enter into a WPA and build the smaller desalination plant.”
The purpose of this report is to update the board on where the Pure Water
Monterey project currently stands relative to the 9 acceptance criteria in the
July 2013 proposed Settlement Agreement.
RECOMMENDATION: The General
Manager recommends the Board receive the update and discuss. The Board is urged to consider the current
status report in relation to Action Item 22.
DISCUSSION: The 9
criteria and current status are as follows:
Criterion 1: MRWPCA
has approved the GWR Project pursuant to a certified Final EIR; and no CEQA
suit has been filed within 30 days of a Notice of Determination
("NOD"), or if a CEQA suit is filed, no stay of the GWR Project has
been granted.
Status:
Satisfied complete.
Criterion 2: The
status of required permits is consistent with the published project schedule,
and for any required permits not yet obtained, the weight of the evidence in
the record does not show that any of the required permits for the GWR Project are
unlikely to be obtained in a timeframe consistent the published project schedule.
Status: The
GWR Project will need to receive a wide variety of permits and approvals from
an equally wide variety of agencies in order to proceed to construction and operation. A separate criterion (#4) specifically
addresses the permit/approvals required from the California Department of
Public Health and Regional Water Quality Control Board; therefore, it is
assumed this criterion addresses all other permits. Permits are listed in the EIR. Contracts have been provided to various
consultants to work on those permits this fiscal year. There are more permits required if the
Coastal Alignment of the product water pipeline is used. MRWPCA will prepare a detailed permitting
plan that covers all of the components of the GWR Project. The permitting plan will identify each
required permit or approval, the permitting entity, the steps to complete the
permit, the party responsible for obtaining the permit, and the estimated schedule
and cost for the permitting effort. At
this time, there is no reason to believe that this criterion will not be met.
Criterion 3: There
is sufficient legal certainty as to agreements or other determinations in place
to secure delivery of source water(s) necessary to produce between 3,000 to
3,500 acre feet per year of GWR product water for the recommended project.
Status: The
MRWPCA-MCWRA Amended and Restated Water Recycling Agreement was
approved by both agencies and the County Board of Supervisors in the past 30
days. An Agreement between MRWPCA and
the City of Salinas has also been approved.
Hence, this criterion has been met.
Criterion 4: The weight of the evidence in the record
does not show that the California Department of Health or the Regional Water
Quality Control Board will decline to accept or approve the GWR extraction or
GWR treatment and injection processes, respectively.
Status: The
Division of Drinking Water (DDW), formerly part of CDPH but now part of SWRCB,
provided a letter dated June 5, 2014 indicating that there were no issues they
had to decline approval of GWR. DDW has
been involved in the Independent Advisory Panel meetings and other update
meetings along with their colleagues at the Regional Water Quality Control
Board (RWQCB.) The RWQCB has emailed the
SWRCB in support of the project due to their desire to see the diversion of
Blanco Drain water away from the Salinas River.
Hence, this criterion appears to have been met, but additional evidence
will be produced as needed.
Criterion 5: The
GWR Project is on schedule, as verified by a report issued by an engineer
licensed in California, to be operable, on or before the later of (a) the
then-effective date of the Cease and Desist Order of the SWRCB or such other
date as the SWRCB states in writing is acceptable, or (b) the date the MPWSP
desalination project is scheduled to become operable. The Parties acknowledge that
the actual date of operation for the GWR Project and the desalination project
could vary from the operation date projected in the schedules, and therefore
agree to a range of up to an additional four months from the projected date of
operation, before the GWR Project schedule would no longer be considered on an
acceptable schedule.
Status: The
project is on schedule to be operable long before the desalination project and
the projected revised CDO effective date.
However, an engineer’s report to that effect will be included in the GWR
testimony at the CPUC.
Criterion 6: Preliminary
design for the GWR Project is at least at the 10% level, represented by a basis
of design report (so that an accurate project cost estimate can be generated)
or is at a level similar to or more advanced than the level of design for the
desalination project portion of the MPWSP.
Status: The MPWSP desalination
facility design is between the 60% and 90% level. GWR has been designed at or beyond the 10%
level of design and one component, connection between the Ag Wash water and the
Salinas Pump Station has been constructed.
The connection from the Salinas storm water and the Salinas Pump Station
or the Salinas Industrial Ponds will be designed to 100%. Criterion met. No additional work required.
Criterion 7: A GWR
Project funding plan, sufficient in detail to be accepted as an application for
a State Revolving Fund loan, is in place.
Status: This
is complete with one exception, an Approval Order on a change petition to the
SWRCB for the discharge of Salinas Industrial Pond water to the MRWPCA Regional
Treatment Plant, which is expected by the end of November.
Criterion 8: California
American Water, MPWMD, and MRWPCA have agreed on a WPA whose terms are just and
reasonable.
Status: A
substantially complete version has been exchanged between the parties and looks
like the form of agreement will be agreed to by the end of November. This is covered further under Agenda Item 21.
Criterion 9: The revenue requirement for the combination
of the GWR Project and the smaller desalination project, including the
projected debt equivalence for the GWR Project, if any, determined pursuant to
Section 4.4, is just and reasonable when compared to the revenue requirement
for a larger desalination project alone.
The parties agree that a revenue requirement premium for the combination
of the GWR Project and a smaller MPWSP desalination project may be determined
just and reasonable, if the combined GWR/smaller desalination project affords
significant net benefits including, but are not limited to, the following: (i) a material
schedule advantage in that the GWR Project is anticipated to be operable sooner
than the desalination plant; (ii) water supply resilience and reliability
(benefit of the portfolio approach); and (iii) other positive externalities of
the GWR Project, including, but not limited to reduced atmospheric carbon
emissions, reduced brine discharge, and the implementation and encouragement of
State policies regarding water recycling through early adoption of a water
reuse project.
Status: An
initial cost comparison analysis prepared by the District, but based on cost
estimates made by Cal-Am and filed with the CPUC and estimates prepared by
MRWPCA, has been shared with Cal-Am November 12th, the Water
Authority Technical Advisory Committee November 16th, and will be
presented to the District Board at its November 16th meeting. The results of that analysis shows positive
impact to ratepayers for the “Project Variant” of GWR-plus-6.4MGD Desal for both life-cycle savings and net present value of
life-cycle savings, as shown below:
9.6 MGD Desal Minus Project Variant |
|
Total Lifecycle Savings |
$1,779,000 |
NPV of Savings |
$8,762,000 |
However, the CPUC on October 12th held a prehearing conference
on revisions to the Phase 2 proceedings on GWR.
At that time, it was made clear that the economic cost comparison
analysis shall be redone for purposes of testimony based on updated Cal-Am
costs expected in December and then-current best available GWR cost
estimates. As a result, this analysis
shall be revisited with the Board.
However, certain actions are requested to be taken now (Agenda Item 22)
based on information known at the present.
Further, the District’s consultant, HDR, is undertaking a study or
“triple bottom line” analysis to demonstrate the potential benefits
environmentally and/or socially, of the externalities. The HDR study is expected to be complete by
the end of the year and inform expert testimony in the CPUC Phase 2 proceedings
on GWR.
EXHIBIT
None
U:\staff\Boardpacket\2015\20151116\DiscussionItems\20\Item20.docx