ITEM: |
GENERAL
MANAGER’S REPORT |
||||
|
|||||
12. |
UPDATE ON DEVELOPMENT OF
WATER SUPPLY PROJECTS |
||||
|
|||||
Meeting
Date: |
February 17, 2016 |
Budgeted: |
N/A |
||
|
|||||
From: |
David J.
Stoldt, |
Program/ |
|
||
|
General
Manager |
Line Item No.: |
|||
|
|||||
Prepared
By: |
David J.
Stoldt |
Cost Estimate: |
N/A |
||
|
|||||
General Counsel Review: N/A |
|||||
Committee Recommendation: N/A |
|||||
CEQA Compliance: N/A |
|||||
Monterey Peninsula Water Supply Project Application
Project sizing:
Demand |
Supply |
13,290 AF 5-year customer demand 500 AF for economic recovery 325 AF for Pebble Beach buildout 1,181 AF
for legal lots of record 15,296 AF total demand |
3,376 AF legally from Carmel
River (2017) 1.474 AF legally from Seaside
Basin (2021) (700) AF Cal-Am intends to leave
in the Seaside Basin for recharge for 25 years 94 AF available from Sand City
long term 1,300 AF assumed available from
ASR 3,500 AF assumed from Pure Water
Monterey 6,252 AF
from small Desal 15,296 AF total supply |
CPUC Schedule:
DATE |
PHASE 1 (Desalination
Plant) |
PHASE 2 (Pure Water
Monterey) |
December 15, 2015 |
Supplemental testimony with
updated MPWSP costs |
|
January 22, 2016 |
Supplemental testimony on demand
and supply, brine discharge, and return water |
Testimony, including the WPA and
applicant’s showing on the WPA |
January to May 2016 [a] |
Phase 1 settlement discussions |
Phase 2 settlement discussions |
March 22, 2016 |
Concurrent rebuttal testimony |
Concurrent rebuttal testimony |
April 14-15, 2016 (To be rescheduled) |
Evidentiary hearings on Phase 1
updates |
Evidentiary hearings for Phase 2 |
May 2016 |
|
Opening Brief on Phase 2 |
May 2016 (2 weeks following) |
|
Reply Brief on Phase 2 |
Same date as Reply Brief |
|
Motion for separate Phase 2
decision |
July 2016 |
|
If two decisions: Target for
Phase 2 Proposed Decision |
August 2016 |
|
If two decisions: Target for
Commission action on Phase 2 decision |
TBD (April?) |
CPUC’s issuance of combined Draft
EIR/EIS |
|
45 days after issuance of
DEIR/DEIS |
Close of comment period on
DEIR/DEIS |
|
15 days after close of DEIR/DEIS
comments |
Opening Legal and Policy Briefs |
|
30 days after close of DEIR/DEIS
comments |
Reply Legal and Policy Brief |
|
TBD |
If two decisions: Phase 1 PD |
|
TBD |
If two decisions: Commission on
Phase 1 PD |
|
Desalination Facility
Cost: California American Water
now has pricing for all of the major project components. While the pipeline and
conveyance facility bids were higher than expected, overall the costs for a 9.6
MGD desalination plant are still within the total project budget and within the
range of the cost estimate California American Water provided to the California
Public Utilities Commission in November 2013.
New cost data was filed with the CPUC on December 15th.
Garney Pacific, Mountain Cascade, and
Monterey Peninsula Engineering were awarded the pipeline contracts, valued at
approximately $95 million for 22 miles of pipeline. Boart
Longyear was awarded the contract for the slant
wells, valued in therange of $19 to $25 million,
depending on 7 to 9 wells.
Budget:
Subsurface
Intake System and Supply Return Facilities: $79M (23% spent to date)
Desalination
Plant: $115M (12% spent to date)
Pipeline
Facilities: $128M (11% spent to date)
Test Well: The test slant well
California American Water drilled for the Monterey Peninsula Water Supply
Project last year reached its 100th day of operation milestone in late December
and is showing salinity levels of 92 percent.
The goal is 96% to 97%.
Slant wells
are a type of subsurface intake, which are considered environmentally preferable
to open ocean intakes by the California Coastal Commission, State Water
Resources Control Board, and Monterey Bay National Marine Sanctuary have each
stated a preference for subsurface intakes.
Return
Water:
Under the County Water Resources Agency Act, all Salinas Valley Basin
groundwater must remain in the basin. In
early January, lawyers for the Salinas Valley Water Coalition, Monterey County
Farm Bureau, LandWatch Monterey County, and the
Monterey Peninsula Regional Water Authority agreed on a draft term sheet with
Cal-Am and the Castroville Community Services District that would dedicate a
portion of the water produced by the proposed Monterey Peninsula Water Supply
Project desalination facility to serve the water-challenged community of Castroville,
satisfying the return flow requirement.
Schedule:
Next
Governance Committee Meeting Feb 18, 2016
Draft
Environmental Impact Report April 2016
CPUC
Decision Nov/Dec
2016
Coastal
Commission Permit Q1/Q2
2017
Project
Operation May
2019
Pure Water Monterey
Pure Water
Monterey will deliver over 3,500 acre-feet of highly purified drinking water
annually that will be injected directly into the Seaside Basin for delivery by Cal-Am
to the residents and businesses of the Monterey Peninsula. Using scientifically
verified technology, the source water will undergo a four-step advanced water
purification process, creating a safe and sustainable supply of purified water.
This
environmentally preferred project will not only reduce discharge into the
Monterey Bay National Marine Sanctuary, but will have lower levels of carbon
emissions and energy consumption. With a certified and unchallenged Final
Environmental Impact report, the project is anticipated to deliver water by the
end of 2017.
Budget:
Source Water
Diversion and Conveyance: $10.0 million
Advanced
Water Treatment Facilities: $31.6 million
Product
Water Pipeline: $21.9 million
Product
Water Injection Facilities: $8.7 million
Expended to
Date: $15.8 million (through end of FY2015-16)
Schedule:
Draft
Environmental Impact Report Complete
CPUC
Decision July/Aug
2016
Initial
Operation Q4
2017
Full
Operation Q1
2018
Aquifer Storage and Recovery
With heavy
winter rains increasing flows on the Carmel River, the District’s Aquifer
Storage and Recovery Project (ASR) is once again able to capture excess water
and inject it into the Seaside Groundwater Basin for storage and later use.
This year,
through February 5th the project has been capturing approximately 3.6 million
gallons of water per day, enough daily volume to serve 40 homes for an entire
year. To date in 2016, ASR has diverted
and injected over 80 million gallons or over 245 acre-feet of water.
This
winter’s rains have swollen the Carmel River and connected it back to the Ocean
for the first time since June, allowing the District to begin seasonal
diversions. The injection season lasts
from December through May.
ASR is a
joint partnership between the District, which owns the first two ASR wells, and
California American Water Company who diverts, treats, and delivers the Carmel
River water to wells located along General Jim Moore Boulevard in Seaside.
Since testing began in 1998, the ASR program has injected a total of 5,233
acre-feet into the Seaside Basin.
Cease and Desist Order
The
Company, the District, and the Authority estimate that the community will not
be able to make the current cease-and-desist order deadline of December 31,
2016. As a result, the parties worked together to develop a proposal to extend
the deadline to provide the time needed for the project to work its way through
the regulatory approval process. The
parties on November 20th filed a joint petition to modify the State Water
Resources Control Board’s 2009 cease-and-desist order The
proposal would extend the deadline until December 31, 2020, with modest
reductions in pumping from the river required in the interim. During the
extension period, the company would be required to meet annual milestones
related to the development of the project.
The proposal would impose additional reduction penalties of 1,000
acre-feet each if any of the milestones are not met.
The State
Board has not announced a hearing date for consideration of the proposal. Action is expected by summer.
Local Water Projects
Projects
grant funded by the District include:
$200,000
City of Pacific Grove – Local Water Project to provide non-potable supplies to
golf course and cemetery ($100,000 spent to date); District approved Ordinance establishing
Pacific Grove water entitlement at January Board meeting. Pacific Grove will get 66 acre-feet of usable
water to its allocation, 13 acre-feet permanently retired to benefit the Carmel
River, and 9 acre-feet reserved by the District for allocation elsewhere.
$80,000
Pebble Beach Company - Test well at Del
Monte Golf Course to remove from Cal-Am potable supply system. Well completed and results look promising.
$85,000
City of Monterey - Examine the feasibility of Peninsula-wide water recovery and
reclamation system and possibilities for sources, including finding uses of
storm and non-storm water flows. Just getting started.
$106,900
City of Seaside - Modifications and
improvements to Laguna Grande well for non-potable uses to offset existing
potable uses. Just
getting started.
$30,000
Monterey Regional Airport – Remediation well retrofit for non-potable water
supply ($14,000 spent to date)
$75,000 Monterey
County Fairgrounds – Use well water to flush toilets (currently under review
following toilet retrofit.)
Malpaso Water (Eastwood/Odello)
In August 2015, the District passed Ordinance No. 165 which establishes a
Water Entitlement for the Malpaso Water Company LLC (Malpaso) of 80 Acre-Feet Annually (AFA) to
be used for new and intensified water uses by properties located within the
California American Water service area that are within the Carmel River
watershed or the City of Carmel-by-the-Sea.
A Water
Entitlement is a discrete quantity of water designated by a District ordinance
to a specified Water Entitlement Holder for new or Intensified Water Use. Water Entitlement Holders established by
previous MPWMD ordinances include the Pebble Beach Company and the other fiscal
sponsors of the CAWD/PBCSD Wastewater Reclamation Project, the City of Sand
City, DBO LLC, and Cypress Pacific Investors LLC.
For the Malpaso Water Company Water Entitlement, the Water
Entitlement Holder assigns water to its subscribers via Assignment Documents
that the subscribers then use to obtain Water Use Permits from the District.
The Water Use Permit can then be used to permit new or intensified water use up
to the amount specified. Malpaso has begun processing Assignment Documents at $2,400
per fixture unit or approximately $240,000 per acre-foot. However, as of February 8, 2016 the District
has not received any requests for Water Use Permits based on a Malpaso entitlement.
Alternative Desal
(DeepWater Desal)
Had
kick-off meeting for EIR/EIS on November 19th. Working with Dudek environmental engineers, the same firm that did the
Carlsbad Poseidon desalination project EIR.
Lead agencies are the State Lands Commission and the National Marine
Sanctuary (NOAA). Most of the studies
feeding into the EIR will be completed by March. Q4
2016 completion of the final study.
Signed contract with Black and Veatch to act as Owners Engineer
for the project. They are preparing to start
the site plan, sub-station plan and possibly additional R/O design.
EMC
environmental is working on wetlands delineation and studies required for the
biological assessment. Tenera is doing the same
for any additional oceanographic studies.
Brierley
Associates is finishing up the constructability study and starting the 15%
design for the pump station.
Project
sponsors are meeting with potential offtakers such as
Cal Water Service (Salinas) and Soquel Creek WD. Pajaro
Sunny Mesa was considering memorandum of intent to work with the project
sponsors at its January meeting.
They hired
another full time employee at the end of last year, an engineer who worked at
Soquel Creek WD and headed up the joint desal project
there.
Pebble Beach Reclamation Project
Last year’s
Usage: 1,062 AF
Last 5 Year
Average: 948 AF
20-Year
Average: 979 AF
As of
February 4, 2016 the Forest Lake Reservoir was almost at full capacity the
earliest in the year since 2011.
U:\staff\Boardpacket\2016\20160217\GMreport\12\Item
12.docx