CONSIDER APPROVAL OF FUNDS TO REPLACE HVAC UNIT AT THE MPWMD HARRIS
COURT ADMINISTRATION BUILDING |
||||
|
|||||
Meeting
Date: |
April 18, 2016 |
Budgeted: |
Yes |
||
|
|||||
From: |
David J.
Stoldt, |
Program/ |
Fixed Assets |
||
|
General
Manager |
Line Item No.: |
918000 Building Improvements |
||
|
|||||
Prepared
By: |
Suresh
Prasad |
Cost
Estimate: |
$12,000 |
||
|
|||||
General Counsel Review: Yes |
|||||
Committee Recommendation: The Administrative Committee reviewed this item on April 11, 2016 and recommended approval. |
|||||
CEQA Compliance: N/A |
|||||
SUMMARY: The District’s FY 2015-2016 Budget
includes a project for replacement of the Heating, Ventilation and Air
Conditioning (HVAC) unit at the main MPWMD Harris Court Administration
Building. The new unit will replace a non-functional
HVAC unit that has been in service for over 15 years.
Originally we were told that replacement cost of the HVAC unit will be around $15,000 plus additional fees. Based on the preliminary verbal quote, staff included $20,000 in the FY 2015-2016 budget to replace the HVAC unit. Airtec Service, our HVAC service provider, has provided a quote of $9,222 including crane rental and labor for installation of the new HVAC unit. The new unit includes a modulating economizer which is an energy saver component and adjusts based on the temperature outside by not turning the cooling compressor which saves electricity. Staff recommends using Airtec Service since they are our HVAC service provider and is familiar with our facilities and equipment.
RECOMMENDATION: District
staff recommends authorizing the General Manager to replace the HVAC unit at
the MPWMD Harris Court Administration Building for an amount not to exceed $12,000,
which includes crane and labor plus additional costs.
BACKGROUND: District
acquired the MPWMD Harris Court Administration Building in 1999. The existing HVAC units have been in service
for over 15 years. One of the HVAC units
has failed and is need of replacement.
Based on preliminary estimates, staff included replacement cost in the
FY 2015-2016 budget. A formal quote to
replace the failed unit was obtained from Airtec
Service, District’s HVAC service provider.
3-A Airtec Service Quote