ITEM: |
CONSENT CALENDAR |
||||
|
|||||
3. |
CONSIDER EXPENDITURE FOR FY 2016-17 AQUIFER STORAGE AND RECOVERY
PLANNING AND OPERATIONS |
||||
|
|||||
Meeting Date: |
July 18, 2016 |
Budgeted: |
Yes |
||
|
|||||
From: |
David J. Stoldt, |
Program/ |
1-2-1 A & B |
||
|
General Manager |
Line Item No.: |
|
||
|
|||||
Prepared By: |
Joe Oliver & Jon Lear |
Cost Estimate: |
Operations $184,748 (reimbursable) Engineering $300,729 (not reimbursable) |
||
|
|||||
General Counsel Review: N/A |
|||||
Committee Recommendation: The Administrative Committee reviewed this
item on July 11, 2016 and recommended approval. |
|||||
CEQA Compliance: N/A |
|||||
SUMMARY:
Ongoing work associated with the Monterey Peninsula Aquifer Storage and
Recovery (ASR) Project is planned for Fiscal Year (FY) 2016-17. To facilitate this planned work, the Monterey
Peninsula Water Management District (MPWMD or District) has requested proposals
from the firm that has been providing assistance on the ASR project, Pueblo
Water Resources (Pueblo). The first
proposal is for Operations Support (Exhibit
3-A); the second proposal is for Engineering
Support (Exhibit 3-B).
These are separate proposals as the costs associated with Operations
Support are subject to reimbursement under MPWMD’s management and operations
agreement with California American Water (CAW) for the ASR project, while costs
associated with Engineering Support relate to planned facility improvements at
the MPWMD ASR site and are not subject to reimbursement under this
agreement. The Pueblo proposals describe
the tasks necessary to accomplish this work in greater detail; key elements of
each proposal are briefly described below.
Operations
Support -- Operations
support to MPWMD staff is proposed for preparation of required operations
reporting, provision of technical assistance during the upcoming Water Year
2017 ASR season, implementation of scheduled well rehabilitation at the ASR-3
well, and completion of baseline injection testing at the ASR-4 well.
Engineering
Support -- Engineering
support to MPWMD staff is proposed for site expansion design/engineering, ASR
well soundproof enclosure and turbidimeter designs, and backup well
design/specifications. The District has
been working to acquire the necessary approvals for a modest expansion of the
Phase 1 Aquifer Storage and Recovery (ASR) site on General Jim Moore Boulevard
in Seaside (a.k.a. Santa Margarita ASR site, Water Project 1). This site expansion is needed in order to
accommodate the space for underground utility pipelines to the on-site facility
building, to allow an increase in the size of the backflush basin, and to facilitate
re-orientation of the driveway pattern at the reconfigured site for delivery
vehicle access. The proposed site expansion
from the existing 1.09 acres to 1.91 acres is shown in Exhibit 3-C.
RECOMMENDATION:
District staff recommends authorization to amend the existing contract
with PWR for technical services for: (A)
Operations Support as described in Exhibit
3-A, for a not-to-exceed amount of $184,748,
and (B) Engineering Support as described in Exhibit 3-B for a not-to-exceed
amount of $300,729. If approved, staff
will process contract amendments for these amounts in order to continue work on
the ASR project without delay. The
requested funding authorization includes a 10% contingency which would only be
utilized based on written request and authorization by the District.
IMPACT
ON STAFF/RESOURCES: Planning, design, construction and operation
of the Phase 1 (Santa Margarita) and Phase 2 (Seaside Middle School) ASR
project facilities are ongoing significant staff commitments, as reflected in
the District’s Strategic Plan. Funds for
this work are included in the MPWMD FY 2016-17 budget under
Line Items 1-2-1 A. 1 to 2, and B. 1 to 2 (adopted June 20, 2016). District staff will continue to coordinate
with CAW on all work elements applicable for direct reimbursement.
BACKGROUND:
When the Phase 1 ASR site was originally conceived in the 2001-2006
period, it was intended as a stand-alone project facility. Since then, the project designs have been
modified in order to accommodate the added capacity needs of other existing and
proposed ASR sites in the Seaside Basin.
Specifically, expanded water treatment and well backflushing facilities
are planned for the capacity needs of these other ASR sites, and this has
necessitated an expansion of the site footprint. To enable full functioning of the site, the
existing facility building must be connected to new underground raw and
finished (i.e., treated) water delivery pipelines which currently have their
terminal connection points outside the existing easement area adjacent to
General Jim Moore Boulevard. Accordingly,
over the last several years the District has been working with the Fort Ord
Reuse Authority (FORA), which is the responsible agency for unexploded ordnance
cleanup and property transfer of former Fort Ord lands, and the City of
Seaside, which is slated to ultimately receive properties in this area of
former Fort Ord, to acquire the additional strip of land needed to accommodate
the pipeline placement and expanded backflush basin area. Assuming the expansion area will soon be authorized,
the District plans to complete the design and construction of this
infrastructure.
The proposed work described in
this item represents a continuation of past efforts on the Phase 1 and 2 ASR
facilities, with technical assistance from Pueblo. Given the current knowledge base and
capabilities of the Pueblo staff, District staff believes that it is most
prudent and efficient to extend the existing contract with Pueblo, to avoid
delays and potential for duplicative work on the project. Pueblo is prepared and able to initiate this
work in accordance with the current requested schedule, and has successfully
accommodated other past short-notice schedule changes on both the Phase 1 and 2
ASR project work elements. By retaining Pueblo
for this work, there is greater assurance that the District’s and CAW’s ASR project
plans will be well coordinated and cost effective.
3-A Monterey Peninsula ASR Project, Proposal
for FY 2016-17 Operational Support Services
3-B Monterey Peninsula ASR Project, Proposal
for FY 2016-17 Engineering Services
3-C Proposed Expansion, Santa Margarita Well
Site plan map
U:\staff\Boardpacket\2016\20160718\ConsentClndr\03\Item-3.docx