SPECIAL JOINT MEETING |
||||
|
||||
DISCUSSION ITEM |
||||
|
||||
2. |
LONG-TERM WATER
SUPPLY FOR THE PENINSULA – WHERE DO WE STAND AND WHERE ARE WE GOING? |
|||
|
||||
Meeting Date: |
October 17, 2017 |
Budgeted: |
N/A |
|
|
||||
From: |
David J. Stoldt |
Program/ |
|
|
|
General Manager |
Line Item No.: |
N/A |
|
|
||||
Prepared By: |
David J. Stoldt |
Cost Estimate: |
N/A |
|
|
||||
General Counsel Approval: N/A |
||||
Committee Recommendation: N/A |
||||
CEQA
Compliance: Not a project as defined
by the California Environmental Quality Act Guidelines Section 15378. |
||||
SUMMARY:
The application to the California Public Utilities Commission (CPUC) for
the Monterey Peninsula Water Supply Project (MPWSP) was filed by California
American Water (Cal-Am) in April 2012.
During that extended time period through today, several events have occurred:
(i) The environmental impact report for the MPWSP was delayed several times and
is now expected in March 2018; (ii) The Cease and Desist Order (CDO) issued by
the State Water Resources Control Board (SWRCB) was extended to December 31, 2021
with the implementation of new annual milestones and penalties; (iii) The Pure
Water Monterey project and Monterey Pipeline were approved by the CPUC; (iv) Consumer
demand for water use has trended downward, and the CPUC has asked for
additional testimony on demand levels and the supplies required to meet them;
among other things. As a result, the
Authority and the District should engage discussion on the following:
a)
Summary of recent MPWSP testimony at the CPUC (Demands,
supply need, interim supplies; Where do future general plan needs come in?)
b) CPUC
Schedule and SWRCB milestones/penalties under the CDO; How will it really work?
c)
Water allocation process going forward – History,
method, timing
d)
How can our agencies best support each other in
advancing our missions, and meeting the needs of our community? (Includes review of mission statements of
each agency)
Each of these is addressed below.
a)
Summary
of Recent CPUC Testimony
DEMAND AND SUPPLY: In an August 28, 2017 ruling titled “Assigned
Commissioner and Administrative Law Judge’s Ruling Setting Issues and Schedule
for Further Evidentiary Hearings and Requiring Submission of Supporting
Documents” the CPUC requested additional testimony on 9 areas. Primary among the topics, was sizing the
water supply project – the first two issues:
1. Demand:
updated estimates and analysis of demand including but not limited to:
a.
use by existing customers
b.
status with respect to legal lots of record
c.
status with respect to Pebble Beach
d.
status with respect to economic recovery of
hospitality industry
2.
Supply: updated estimates and analysis of supply
including but not limited to:
a.
Plans for expansion of the Pure Water Monterey (PWM)
project, if any
b.
Can expansion of the PWM project provide water to
applicant in excess of 3,500 acre-feet per year, in what amounts, and at what
cost
c.
Is water available for purchase by applicant from
Marina Coast Water District, in what amounts, and at what cost
The other issues upon which the CPUC requested input
are:
3.
Updated cost estimates for the MPWSP.
4.
Updated information on project financing
5.
Feasibility and costs of MPWSP being downsized or construction
in modular increments
6.
Role of solar and renewables.
7.
Access to land at the CEMEX site if CEMEX ends
operation
8.
Are modifications needed, if any, to any pending
Settlement Agreement?
9.
In determining whether or not to grant the CPCN, what
consideration should the Commission give to community values, recreational and
park areas, and historical and aesthetic values
Testimony of the parties is summarized in Exhibit
2-A attached hereto. Since the 2012
application was filed, the overall water supply needs of the Peninsula, and
required supply, have been sized as follows:
Demand |
Supply |
13,290 AF average
customer demand 500 AF for economic recovery 325 AF for Pebble Beach buildout 1,181 AF for legal lots of record ------------- 15,296 AF total
demand |
3,376
AF legally from Carmel River (2017) 1,474
AF legally from Seaside Basin (2021) (700)
AF Cal-Am intends to leave in the Seaside
Basin for recharge for 25 years 94
AF available from Sand City long term 1,300
AF assumed available from ASR 3,500
AF from Pure Water Monterey 6,252
AF from Desalination Plant ------------ 15,296 AF total supply |
The testimony reflects differing views on the
applicability of the 4 components of demand, and therefore, the needed supply
project to serve replacement water.
DEMAND FOR GENERAL PLAN BUILD-OUT: None of the demand projections in the
testimony include water for build-out of the 6 cities, unincorporated county,
or airport general plans, with the exception of the testimony of the Coalition
of Peninsula Businesses, which supports a 9.6 MGD desalination facility,
despite already existing approval and construction of Pure Water Monterey. By design, the proposed MPWSP is only
supposed to replace the unlawful diversions and meet already approved, legally
required uses of water, not general plan growth. Hence, the issue of when to plan for
additional water is worthy of discussion.
In 2006,
the District prepared an estimate of future water needs based on information
obtained from the service area jurisdictions.
Each jurisdiction provided estimates of the number of residential units
and nonresidential square footage that would be developed under buildout of the
currently adopted general plan, as well as anticipated residential remodels. The
MPWMD estimated that 4,545 AFY would be needed to meet future water demands.
Since the 2006 estimate was prepared, the future
water needs of four jurisdictions have been revised, reducing the total:
·
Monterey County adopted a new general plan in 2010
that revised their water demand estimates;
·
The City of Pacific Grove testified on the MPWSP in
2013, revising its estimate of water needed to accommodate general plan
buildout;
·
The City of Seaside commented on the April 2015
MPWSP Draft EIR, updating its future water needs, and noting that full buildout
of the West Broadway Urban Village Specific Plan would require a net increase
of 80 afy of water.
·
Sand City built the 300-afy Sand City Coastal
Desalination Plant. In consideration for the delivery of 300 afy of potable
water from this plant to the CalAm system, MPWMD Ordinance 132 establishes a
water entitlement of 206 afy from the CalAm system for Sand City, separate from
the city’s current water allocation, and indicates that the remaining 94 afy
will be permanently added to CalAm’s system. The estimated future demand for
Sand City is therefore revised to reflect that 206 afy of the city’s future
demand will be offset by supply from the city’s desalination plant, which is
why it is not included in the supplies assumed for the MPWSP in most demand
analyses, even though most of it is likely to remain available to Cal-Am for
the next 10 to 15 years.
With these revisions, future demand would total
3,526 afy. The table on the next page shows the District’s 2006 future
demand estimates, with and without the four revisions. In addition, Pacific
Grove may reduce its future demand estimate by 66 afy because of the Pacific
Grove Local Water Project. However, the city has not submitted a formal
revision to its demand numbers since the 2013 revision noted above.
FUTURE WATER DEMAND -
SERVICE AREA JURISDICTIONS
(acre-feet per year)
Jurisdiction |
Future Supply Needs (2006
Estimate)a |
Future
Supply Needs (Revised Estimate) |
City of Carmel |
288 |
288b |
City of Del Rey Oaks |
48 |
48 |
City of Monterey |
705 |
705 |
City of Pacific Grove |
1,264 |
500c,d |
City of Sand City |
386 |
180e |
City of Seaside |
582 |
662f |
Monterey County
(Unincorporated) |
1,135 |
1,005 |
Monterey Peninsula
Airport District |
138 |
138 |
Total |
4,545 |
3,526 |
Note: All
footnotes have been deleted for this staff note; Interested parties should
contact the General Manager for additional information if desired.
At some point, the jurisdictions and the District
should coordinate an update of future water needs related to general plans, as
well as better understand the interaction of future needs with legal lots of
record and Pebble Beach entitlement. How
and when to update future general plan buildout might be a topic subject to
discussion at the Special Joint Meeting.
SUPPLY – EXPANSION OF PURE WATER MONTEREY: With respect to the issue of Pure Water
Monterey expansion, in its testimony Monterey One Water developed 3 scenarios
of plant expansion that are deemed possible.
They are summarized in the table below:
Summary of PWM Project
Expansion Scenarios
|
Scenario A |
Scenario
B |
Scenario
C |
AWPF rated capacity (approved PWM Project = 4 mgd) |
5
mgd |
6.5
mgd |
10
mgd |
Approved
PWM project yield to CalAm |
3,500 AFY |
3,500
AFY |
3,500
AFY |
Incremental yield above approved PWM Project for CalAm |
650
AFY |
2,250
AFY |
3,570
AFY |
Estimated
total yield for CalAm |
4,150 AFY |
5,750
AFY |
7,070
AFY |
Incremental capital cost above the approved PWM Project |
$6.9
million |
$51.6
million |
$132.9
million |
Annual operations and maintenance costs (Approved plus
Expansion Scenario) |
$5.0
million |
$6.2
million |
$8.4
million |
Cost
of water ($/AF) (1) |
$1,897 |
$1,858 |
$2,335 |
Estimated construction completion date (see Note 2) |
4th Quarter of 2019 |
4th Quarter of 2020 |
4th Quarter of 2022 |
Note 1: Loan term of 10 years for Scenario A; and a 40 year
term for Scenarios B and C. Assumes a 3% interest rate on revenue bonds,
interest only internal loan to support the debt reserve requirement for the
State Revolving Fund Loan, and supplemented replacement and renewal costs. Note 2. The completion dates are based on concept-level
critical path analysis that are affected by timing of MRWPCA receiving
funding, financing, local partner agency |
b)
CPUC
Schedule and SWRCB milestones
The current CPUC schedule for the proceeding is
attached as Exhibit 2-C and the SWRCB
milestones for performance under the CDO are included as Exhibit 2-D.
Key
questions related to schedule include the following:
·
What
is the CPUC’s schedule for approval?
·
Will
approval happen soon enough to meet the next CDO milestone?
·
What
if there is a CEQA lawsuit over the Final Environmental Impact Report (FEIR),
will CPUC approval be delayed? Will
we miss a milestone?
·
If
there is a CEQA lawsuit, do we have a contingent back-up plan?
·
If
we miss a milestone, what happens?
·
Doesn’t
Pure Water Monterey help us against a missed milestone?
Each
of these are addressed below:
WHAT
IS THE CPUC’S SCHEDULE FOR APPROVAL? Exhibit 2-C
shows the CPUC schedule. The FEIR is
scheduled to be released March 16, 2018.
There are 10 days to then file opening briefs on the FEIR, followed by 7
days to file closing briefs, or April 2nd. On such a schedule, the best that could occur
is a proposed decision from the CPUC in mid- to late-April. To allow 30-day public review, that means the
certification of the FEIR would not likely occur until the second business
meeting of the CPUC, late May. As
discussed below, it is likely that the Certificate of Public Convenience and
Necessity (CPCN) or project approval would be issued by the CPUC at the same
time.
WILL
APPROVAL HAPPEN SOON ENOUGH TO MEET THE NEXT CDO MILESTONE? Yes, likely.
As shown in Exhibit 2-D, the next CDO milestone is the issuance of
the CPCN on or before September 30, 2018.
If the CPCN is issued at the CPUC’s second May business meeting, this
milestone is met. It also means there
are 4 months available for delays at the CPUC.
However, any delay at this point must be met with reaction from the
Parties and entreaties to the SWRCB to weigh in with the CPUC.
WHAT
IF THERE IS A CEQA LAWSUIT OVER THE FINAL ENVIRONMENTAL IMPACT REPORT (FEIR),
WILL CPUC APPROVAL BE DELAYED? It is unlikely that a CEQA lawsuit can be
filed before CPUC approval and the issuance of a CPCN. There are 3 actions the CPUC must take before
a party can file a CEQA lawsuit: (i) a Notice of Determination (NOD) is filed
upon project approval, which triggers a 30-day period for legal challenges;
(ii) the project approval in the CPUC’s case is done through the issuance of
the CPCN; and (iii) the CPCN can only be issued upon certification of the
FEIR. Hence, it is likely that the CPUC
will both certify the FEIR and issue the CPCN at the same business meeting,
although they could separate the two.
The NOD is usually filed by staff a few days after the project approval
step. Hence, it appears that the CPCN
would not be delayed beyond the CDO milestone due to a CEQA lawsuit. (Note: some agencies have issued an NOD upon
certification of an FEIR, however the body of law shows that that project approval
is required.)
WHAT
IF THERE IS A CEQA LAWSUIT OVER THE FINAL ENVIRONMENTAL IMPACT REPORT (FEIR),
WILL WE MISS A MILESTONE? As shown
above, it is unlikely to miss the CDO’s September 30, 2018 milestone due to a
CEQA lawsuit. However, the subsequent
2019 CDO milestone would be at risk. The
2019 milestone is start of construction of the desalination plant, excavation
of brine and backwash storage basins, and 25% completion of the transmission
pipeline. Any litigant would first
attempt to get the court to issue an injunction against proceeding with the
project. An injunction would require
showing irreparable harm and a set of facts that could be construed as the
basis for potentially prevailing in court.
An injunction would halt the project.
Even
without an injunction, if the case is allowed to proceed, then there is always
the specter that a plaintiff might prevail.
Thus, it becomes a Cal-Am corporate decision whether to proceed with the
project in the face of litigation.
One
nuance here is the venue – the California Supreme Court. The Supreme Court could send it down to a
lower court or hear the case itself. It
is unknown at this time path would be taken.
Either way, landing in the courts will likely require 2 years or more to
resolve.
IF
THERE IS A CEQA LAWSUIT, DO WE HAVE A CONTINGENT BACK-UP PLAN? This is part of the reason for the CPUC
request for information about expansion of Pure Water Monterey. In its testimony, the Planning and
Conservation League has suggested that the CPUC consider a contingent CPCN for
Pure Water Monterey expansion. The
concept would be: If the desal plant becomes uncertain, delayed, or deferred,
then expansion of Pure Water Monterey would be allowed to proceed. (Note:
Other intervenors in the CPUC proceeding have suggested an expansion of
Pure Water Monterey should be done in lieu of the desalination facility.) There has also been the offer by Marina Coast
Water District of interim water supplies for a 6- to 10-year period. Then, once lawsuits clear, a down-sized
desalination facility would be permitted to proceed.
Relative
to the CDO risks: Carmel River pumping
the past three years of record (2014-16) averaged 7,209 AF. Pure Water Monterey can replace 3,500 AF and
Cal-Am has a legal right to 3,376 AF – leaving 340 AF of unmet need. The expansion and interim water can more than
offset that amount. Hence, even if the
desalination plant gets tied up in court, there is a path to satisfying the CDO
milestones. However, in this case, the
SWRCB would need to invoke footnote 17 of the CDO: “If at any point prior to completion of the facilities listed in these
Milestones the CPUC authorizes Cal-Am to acquire more than 1,000 afa of water
from an alternative source, then the following shall occur. Cal-Am shall submit
to the Executive Director within 60 days a revised set of milestones taking
this water supply source into account. If the proponents of the alternative
project are unable to reach concurrence with Cal-Am on revised milestones to
propose, the proponents may also submit revised milestones within that time
period. The Executive Director shall determine whether to bring forward a
recommendation to the State Water Board regarding amendment of the milestones.”
IF
WE MISS A MILESTONE, WHAT HAPPENS? The
first effort will be, months in advance of the milestone, to report to the
SWRCB indicating that a milestone is likely to be missed for reasons beyond
Applicants’ control (“Applicant” includes Cal-Am, the Authority, and the
District), and request the State Water Board to make a determination during its
regular meeting that the cause for delay is beyond Applicants’ control. If the
State Water Board determines that the cause is beyond Applicants' control, it
may suspend any corresponding reductions under the CDO until such time as the
Applicants can reasonably control progress towards the milestone. The report must be submitted at least 120
days prior to the milestone and a hearing at a regular board meeting may be
scheduled with the State Board no sooner than 60 days after submission of the
report
If
such relief of the milestone is not granted by the SWRCB, then 1,000 AF is
subtracted from the Effective Diversion Limit (EDL) for withdrawals from the
Carmel River. Currently, that limit is
8,310 AFY, so the new limit would be 7,310 AFY.
If the milestone is eventually met during the ensuing year, a portion of
the EDL will be restored. If a
subsequent milestone is missed, another 1,000 AF is subtracted from the
then-current EDL, and so on.
The
2016 Monterey Peninsula Conservation and Rationing Plan (Plan) has specific
triggers and actions related to pumping relative to regulatory limits. Typically, the last 12-months of pumping is
compared to the then current EDL to see if there is a violation. Certainly, if the EDL is reduced at the
beginning of a water year, even without a violation based on the prior
12-months, we will immediately determine if action is warranted. The Plan invokes a series of steps, first a
call for increased voluntary conservation, then conservation (penalty) rates,
and then finally rationing. These steps
are summarized in Exhibit 2-E, as they relate to regulatory triggers. Because the Plan evaluates Carmel River
withdrawals in conjunction with Seaside Basin and Sand City desal production,
our approach will need to be modified to assess Carmel River pumping relative
to the EDL.
Based
on the regulatory triggers, the timeline is as
follows:
·
If
12-month Cal-Am production is greater than the EDL, but less than 105% of the
EDL, then Stage 2 is entered and there is a call for additional voluntary
conservation with increased enforcement of water waste. If the 12-month production goes below the EDL
for 2 consecutive months the Stage is lifted, if 6 months pass without lifting,
then Stage 3 is implemented.
·
If
Stage 2 didn’t work, or 12-month production exceeds 105% of the EDL, Stage 3 is
entered. Level 1 of Stage 3 is a period
of a 25% surcharge on all rates, except Tier 1 residential customers, for a
minimum of 3 months. If over the last 2
of the 3 months the target is still exceeded, the surcharge is raised to 40%. If the 12-month production goes below the EDL
for 2 consecutive months the Stage is lifted, if 8 months in Stage 3 pass
without lifting, then Stage 4 is implemented.
·
If
Stage 3 didn’t work, then Stage 4 – Rationing – is entered. Stage 4 first prohibits non-essential water
use, with a focus on landscaping, for non-residential and residential uses. Then the residential sector is rationed. If measurable results are not achieved within
6 months, then non-residential uses will be rationed; however, exemptions are
provided to “best management practice” (BMP) compliant customers and businesses
that require water in their normal course of business (laundromats, nurseries,
among others). The reader is directed to
pages 5 and 7-10 of Exhibit 2-E for a description of the rationing program.
This is an orderly progression that does not
lead straight to rationing. Even in the
case where Stage 3 is entered directly, 8 months would pass with rate
surcharges before implementing rationing.
Another 6 months would pass before non-BMP compliant businesses would be
rationed.
However, if the SWRCB believes Cal-Am is not
making adequate progress to achieve the revised EDL, they could potentially
circumvent the Plan with a direct regulatory order to accelerate to a higher
level of penalty rates or rationing, as shown in Exhibit 2-E under “Regulatory Trigger –
Regulatory Order” under Stages 2 and 3, or “Regulatory Trigger” under Stage 4.
c)
Water Allocation Process Going
Forward
Water
for new uses is only available from three sources: Jurisdictional Allocations, Entitlements, and
Credits.
Credits
are created either from permanent abandonment of a Cal-Am use (“Water Use
Credit”) or a non-permanent removal of a use on a site which may be later
re-used on that site (“On-Site Credit)
Entitlements
are the result of a specific water-saving or water creating project that the
entitlement holder can then sell or apply to specific benefitted properties. Examples include Pebble Beach as a result of
its Reclamation Project or Malpaso Water Company LLC resulting from the
Eastwood Trust water right on the Odello East property.
Jurisdictional
Allocations are amounts of water allotted to each jurisdiction as a result of several
sources: (i) allocations made pursuant to the District’s 1990 Allocation EIR,
(ii) 1993 allocations of new capacity from the Paralta Well, (iii) from time to
time some jurisdictions developed their own water-saving projects resulting in
a public water credit, and (iv) the additional water in the MPWSP beyond
existing use. Exhibit 2-F provides a history of
the District’s water allocation program.
The table below shows the current state of jurisdictional allocations.
Jurisdictional Water
Allocations
Jurisdiction |
Original Allocation (all sources) |
Remaining Allocation |
Airport
District |
8.1 AF |
5.2 AF |
Carmel-By-The-Sea |
21.4 AF |
2.7 AF |
Del
Rey Oaks |
8.54 AF |
0 AF |
Monterey |
165.1 AF |
2.6 AF |
County |
108.6 AF |
13.0 AF |
Pacific
Grove |
43.1 AF |
0.2 AF |
Sand
City |
77.4 AF |
23.4 AF |
Seaside |
102.6 AF |
43.4 AF |
No
new water from the MPWSP will be available for allocation to the cities and the
county until the final water supply project comes on line that allows the CDO
to be lifted. Once the CDO is lifted,
the District will make a determination of how much water supply is available
for new uses over and above existing uses.
From that amount, a portion will be allocated to the jurisdictions. It is that future allocation process that
should be discussed at the Special Joint Meeting. The allocation process will require an EIR and
will invariably take time for all affected parties to participate. The process should start 18 months to 2 years
from completion of the last increment of water supply.
d)
How can our agencies best support
each other in advancing our missions and meeting the needs of our community?
Attached
as Exhibit 2-F
are the mission and powers of the Authority and District. Not all powers have been actively pursued by
the Authority or District, and each entity has prioritized its activities
periodically to meet the desired strategic outcomes of each respective board.
EXHIBITS
2-A Summary of Testimony
Related to MPWSP Demands and Supplies
2-B Table of
Historical Water Demand in Cal-Am Main Service Are
2-C CPUC
Schedule for MPWSP
2-D State
Water Board CDO
Milestones for MPWSP Progress
2-E Summary of Provisions
of the 2016 Monterey Peninsula Conservation and Rationing Plan
2-F History
of District’s Water Allocation Program
2-G Mission and Powers of the Authority and District
U:\staff\Boardpacket\2017\20171016JointMtng\02\Item-2.docx