ITEM: |
CONSENT CALENDAR |
||||
|
|||||
6. |
CONSIDER ADOPTION
OF AMENDMENT 2 TO COST SHARING AGREEMENT WITH MONTEREY ONE WATER FOR THE PURE
WATER MONTEREY PROJECT |
||||
|
|||||
Meeting Date: |
November 13, 2017 |
Budgeted: |
N/A |
||
|
|||||
From: |
David J. Stoldt |
Program/ |
N/A |
||
|
General Manager |
Line Item No.: |
|
||
|
|||||
Prepared By: |
David J. Stoldt |
Cost Estimate: |
N/A |
||
|
|||||
General Counsel Approval: N/A |
|||||
Committee Recommendation: Water Supply Planning Committee approved Amendment 2 to the Cost Sharing Agreement at its October 17th meeting with a 3-0 vote. |
|||||
CEQA
Compliance: Action does not constitute
a project as defined by the California Environmental Quality Act Guidelines
section 15378. |
|||||
SUMMARY:
In May 2013, the
Monterey Peninsula Water Management District (District) entered into a Cost
Sharing Agreement (Agreement) with Monterey One Water (M1W), at the time
Monterey Regional Water Pollution Control Agency) to fund the Groundwater
Replenishment (GWR) Project planning and development costs, also referred to as
pre-construction costs.
In April
of 2017, M1W’s State Revolving Fund Loan was approved to support the payment of
GWR/Pure Water Monterey (PWM) project costs, providing the opportunity to
reimburse pre-construction costs from the State Revolving Fund loan.
To
formalize this action, as well as incorporate additional terms to support the
continued relationship between the parties, a Second Amendment to the Cost
Sharing Agreement is needed.
M1W’s
Board approved this Amendment 2 to the Cost Sharing Agreement at its October
30, 2017 meeting.
Proposed Revised
Amendment 2: After having met to discuss the matter, the
parties propose the attached revised Amendment 2 to the Cost Sharing Agreement
(Exhibit 6-A.) This form was approved by the District’s
Water Supply Planning Committee on October 17, 2017.
Key
provisions are listed below:
Planning
and Development Costs Definition
Amends
the existing planning and development costs definition.
Add
Reimbursement of Planning and Development Costs
Adds
a new section to address the planning and development costs reimbursed through
the State Revolving Fund (SRF) Loan. This section provides for a 50%-50% initial
reimbursement share for each agency and addresses how subsequent reimbursements
would be shared between the two agencies, targeting a goal of bringing both
parties back in line with proportional reimbursement after subsequent
reimbursements.
Add
Unreimbursed Construction Period Costs
Adds
a new section to address project-related costs that are not allowed to be paid
through the SRF loan between March 1, 2017 to June 30, 2019. The State is disallowing certain costs that
are not associated with the project design and construction. Such costs include
public outreach, regulatory proceedings, groundwater modeling, geochemical
monitoring, and regulatory proceedings. This section would provide a mechanism
of continued cost sharing on unreimbursed costs.
Add
Financing of GWR Unreimbursed Construction Period Costs
Adds
a section to state that the District shall pay seventy-five percent (75%) of
the Unreimbursed Construction Period costs and M1W shall pay twenty-five
percent (25%) of such costs.
Add
Debt Service Reserve Fund
Adds
a section to address funding the debt service reserve fund. Unlike earlier
proposals, there is no shared funding agreement at this time and M1W retains
the right to address alternative approaches for the funding of the reserve at
the in-service date in the future.
Amending
Term
Amends
the existing term of the Agreement to remain in effect until June 30,
2019. An extension could occur at the
agreement of the parties.
RECOMMENDATION:
The General
Manager recommends the Board approve Amendment 2 to the Cost Sharing
Agreement with M1W for the Pure Water Monterey Project.
BACKGROUND:
Under the Cost
Sharing Agreement adopted in May 2013, beginning with Fiscal Year 2013-14, M1W
agreed to fund 25% of all costs listed in Section II (A)(1,2) of the Agreement,
while the District agreed to pay for 75% of the specified costs. In July 2016,
the parties entered into Amendment 1 to the Cost Sharing Agreement to increase
the number of fully-funded M1W positions covered and support the costs associated
with the line of credit.
After
approval of M1W’s State Revolving Fund Loan in April of this year, project
costs through February 28, 2017 concluded the pre-construction costs covered by
the Cost Sharing Agreement. All eligible costs incurred after that period were
paid by M1W and subject to reimbursement by the State.
Staff of
M1W and the District agreed to apply for $8.2 million in initial reimbursements
from the State Revolving Fund loan, in concept with the reimbursement shared
equally between the organizations. The Agency’s $4.1 million share of the
reimbursements was earmarked to replenish and increase reserve balances.
At the
September 8, 2017 M1W BPC meeting, there were still on-going discussions
between both parties. Staff was initially considering a recommendation for an
equal distribution of the $8.2 million initial reimbursement, an equivalent
contribution to establish the PWM debt service fund, and that any future
distributions be based on the proportional share of costs or a true-up to that
level. As stated above, at the BPC meeting, M1W staff was directed to pursue
reimbursement of M1W funds, and to suggest that the District give consideration
to waiving reimbursement of their costs.
At the
District’s Administrative Committee September 11, 2017 meeting, the Committee
approved the proposed form of amendment, as well as an alternate version, where
the District would not participate in funding the debt service reserve fund and
the initial reimbursement proportions would be different.
The
District’s full board approved either of both versions on consent at its
September 18, 2017 meeting.
At M1W’s
September 25, 2017 full board meeting, the reimbursement proposals were
discussed and staff was directed to develop a series of talking points to be
conveyed to the District by the M1W board Chair, in support of the District
giving consideration to waiving reimbursement of their costs.
Both parties’ board Chairs and general managers met on October 4,
2017, at which time the District strongly expressed that it does not agree to
waive its reimbursement. The District
also provided its own talking points in response to M1W.
As a result of the discussion between the parties on October 4th,
the board Chairs and general managers agree that the revised proposal attached
as Exhibit 6-A
hereto represents a compromise which (i) is fair to both parties, (ii) provides
for potential future reimbursement of pre-construction costs in a manner that bring
both parties closer to proportional reimbursement, and (iii) leave the door
open for a future contribution by the District to help reduce the wholesale
cost of product water.
EXHIBITS
6-A Proposed Amendment 2 to
MRWPCA-MPWMD Groundwater Replenishment Project Cost Sharing Agreement
U:\staff\Boardpacket\2017\20171113\ConsentClndr\06\Item-6.docx