MONTHLY WATER SUPPLY AND CALIFORNIA AMERICAN WATER PRODUCTION
REPORT |
||||
|
|||||
Meeting Date: |
February 22, 2018 |
Budgeted: |
N/A |
||
|
|||||
From: |
David J. Stoldt, |
Program/ |
N/A |
||
|
General Manager |
Line Item No.: |
|||
|
|
|
|||
Prepared By: |
Jonathan Lear |
Cost Estimate: |
N/A |
||
|
|||||
General Counsel Review: N/A |
|||||
Committee Recommendation: N/A |
|||||
CEQA
Compliance: Exempt from environmental
review per SWRCB Order Nos. 95-10 and 2016-0016, and the Seaside Basin
Groundwater Basin adjudication decision, as amended and Section 15268 of the
California Environmental Quality Act (CEQA) Guidelines, as a ministerial
project; Exempt from Section 15307, Actions by Regulatory Agencies for Protection
of Natural Resources. |
|||||
Exhibit 19-A shows the water
supply status for the Monterey Peninsula Water Resources System (MPWRS) as of February 1, 2018. This system includes the surface water
resources in the
Water Supply Status: Rainfall through January 2018 totaled 3.95 inches and brings the cumulative rainfall total for WY 2018 to 4.97 inches, which is 45% of the long-term average through January. Estimated unimpaired runoff during January totaled 2,640 acre-feet (AF) and brings the cumulative runoff total for WY 2018 to 5,235 AF, which is 27% of the long-term average through January. Usable storage for the MRWPRS was 28,800 acre-feet, which is 96% of average through January, and equates to 77% percent of system capacity
Production Compliance: Under State Water Resources Control Board (SWRCB) Cease and Desist Order No. 2016-0016 (CDO), California American Water (Cal-Am) is allowed to produce no more than 8,310 AF of water from the Carmel River in WY 2018. Through January, using the CDO accounting method, Cal-Am has produced 1,752 AF from the Carmel River (including ASR capped at 600 AF, Table 13, and Mal Paso.) In addition, under the Seaside Basin Decision, Cal-Am is allowed to produce 1,820 AF of water from the Coastal Subareas and 0 AF from the Laguna Seca Subarea of the Seaside Basin in WY 2018. Through January, Cal-Am has produced 1,332 AF from the Seaside Groundwater Basin. Through January, 0 AF of Carmel River Basin groundwater have been diverted for Seaside Basin injection; 0 AF have been recovered for customer use, and 0 AF have been diverted under Table 13 water rights. Cal-Am has produced 3,167 AF for customer use from all sources through January. Exhibit 19-C shows production by source. Some of the values in this report may be revised in the future as Cal-Am finalizes their production values and monitoring data. The 12 month moving average of production for customer service is 9,923 AF, which is below the rationing trigger of 10,130 AF for WY 2018.
EXHIBITS
19-A Water Supply Status: February 1, 2018
19-B Monthly Cal-Am Diversions from Carmel River and Seaside Groundwater Basins: WY 2018
19-C Monthly Cal-Am production by source: WY 2018