ITEM:

CONSENT CALENDAR

 

5.

Consider APPROVAL OF EXPENDITURE FOR PHONE SYSTEM AND SERVER NETWORK UPGRADE

 

Meeting Date:

June 18, 2018

Budgeted: 

Yes

 

From:

David J. Stoldt,

Program/

Fixed Assets

 

General Manager

Line Item No.:

Various

 

Prepared By:

Suresh Prasad

Cost Estimate: 

$60,000

 

General Counsel Review:  N/A

Committee Recommendation:  The Administrative Committee reviewed this item on June 11, 2018 and recommended approval.

CEQA Compliance:  This action does not constitute a project as defined by the California Environmental Quality Act Guidelines Section 15378.

 

SUMMARY: The District’s current PBX phone system is about 20 years old and is in dire need to get upgraded. Parts for the existing phone system are not readily available at times, which adds to the lead time for getting the system fixed. Additionally, running an old phone system incurs a higher recurring monthly fees since we are not able to utilize the latest technology available in the market.  Most organizations are using cloud based phone systems which eliminates having to purchase costly equipment upfront.  District’s proposal is also based on a cloud based phone system. 

 

In order to go through with a phone system upgrade, District’s current network cabling will also need to be upgraded. The existing network cabling are about 20 years old and will not be able to handle the new phone system which works across these cables sharing both voice and data on the same cable. Bundled together with the network cable upgrade, we will also be re-locating the server room from first floor to ground floor.  This move is required to help minimize noise and vibrations that are caused by the server equipment’s in the existing location.  The ground floor location has concrete flooring which provides better stability and support for the server equipment as well as better environment for cooling and humidity control.

 

District’s server room air conditioner was also budgeted to be replaced this fiscal year. Instead of replacing the unit in the existing room, staff will be getting a new unit installed at the new server location. The existing air conditioning unit is about 8 years old and is a residential unit which is not the type to be used for server rooms. It has had numerous service calls to get the unit repaired. Staff has also been experiencing irregular climate control with the existing unit due to the inefficiency of the existing unit.

 

District solicited cost estimate from phone vendor that has experience in the phone and data network areas, and is available locally for support.  We also wanted a vendor that has worked with public agencies, cities and special districts in the area.

 

The cost breakdown for the upgrade project are summarized in the following table:

 

One-Time

Current

Monthly

Proposed

Monthly

Phone Hardware & Setup

$14,877

 

 

Existing Phone Charges

 

$3,250

 

Proposed Phone Charges

 

 

$2,500

 

 

 

 

Network Cabling Upgrade

$14,820

 

 

Server Room Re-Location

$9,934

 

 

Server Room Air-Conditioner

$10,000

 

 

 

 

 

 

 

 

 

 

Projected Monthly Savings

 

 

$750

 

This project could have a potential savings of $750 or more per month in phone bills, which would pay for the new hardware & setup costs, and network cabling within 3 years. In addition, there are numerous other value added benefits for changing to the new system, such as unified communications, ability to answer desk phone calls using mobile phones while out of the office, ability to access voice mails through email. Also, District staff would not have to manage the phone lines or bills or schedule service calls with local carrier. It will be done through the phone vendor.

 

RECOMMENDATION:  Staff recommends that the Board authorize expenditure of funds to purchase and upgrade the phone system, network cabling, server room relocation, and server room air conditioner at a not-to-exceed price of $60,000.  The approval of this item is contingent upon the adoption of FY 2018-2019 budget by the Board. 

 

BACKGROUND:  The Fiscal Year 2018-2019 Budget includes $43,500 for the purchase and upgrade of the phone system, $25,000 for server room re-location, and $10,000 for server room air conditioner. The District’s current phone system and network cabling are about 20 years old and is need of replacement. In addition to upgrading the phone system and network cables, server room will also be re-located from first floor to ground floor for noise and vibration reduction as well as provide more stable flooring to house the server equipment’s.

 

EXHIBIT

5-A  Phone & Network Upgrade Proposal

 

 

U:\staff\Boardpacket\2018\20180618\ConsentClndr\05\Item-5.docx