ITEM: |
ACTION
ITEM |
||||
|
|||||
33. |
CONSIDER AUTHORIZATION OF
FUNDS TO MONTEREY ONE WATER FOR THE PURE WATER MONTEREY PROJECT |
||||
|
|||||
Meeting
Date: |
June 18, 2018 |
Budgeted: |
No |
||
|
|||||
From: |
David J.
Stoldt |
Program/ |
|
||
|
General
Manager |
Line Item No.: |
N/A |
||
|
|||||
Prepared
By: |
Suresh
Prasad |
Cost Estimate: |
$2,000,000 |
||
|
|||||
General Counsel Approval: N/A |
|||||
Committee Recommendation: The Administrative Committee reviewed this item on June 11, 2018 and recommended approval. |
|||||
CEQA Compliance: This action does not constitute a project as
defined by the California Environmental Quality Act Guidelines Section 15378. |
|||||
SUMMARY: In
May 2013, the District entered into a Cost-Sharing Agreement with the Monterey
Regional Water Pollution Control Agency (now Monterey One Water) to fund the
Groundwater Replenishment (now Pure Water Monterey) Project planning and
development costs. In July 2016, the
District entered into Amendment 1 to the Cost Sharing Agreement. In September
2017, District entered into Amendment 2 to the Agreement.
Monterey One Water (M1W) will exhaust all of its 4% contingency set aside
for the project and estimates it will need of an additional $8 million towards
the contingency part of the project. This additional $8 million will set the
total contingency level at around 10% of the total project cost.
Monterey One Water is in the process of increasing the amount of the
State Revolving Fund loan by an additional $12 million. $6 million of the loan
proceeds will go towards the contingency line item, while the other $6 million
will go towards the reimbursement of pre-construction costs incurred by both M1W
and MPWMD. Based on the reimbursement
sharing formula stated in Amendment No. 2 of the Agreement, M1W will get
$1,321,609 and MPWMD will get $4,678,391 of the $6 million proceeds.
In order to keep the water cost down, M1W has asked the District to potentially
contribute an additional $2 million from its share of the $4.7 million reimbursement
proceeds to help increase the contingency line item of the project, if needed. The
District will ensure that the following contingencies are met:
·
Additional
$2 million will come from the proceeds of second reimbursement from the SRF
loan. If the reimbursement does not happen, the District will not be obligated
to fund the $2 million.
·
The
District’s $2 million proceeds will be disbursed to Monterey One Water towards
the end of the project which would determine if proceeds are needed to either
meet project expenses or reduce the cost of the water by reducing the loan
amount.
RECOMMENDATION: Staff
requests that the Board approve authorization of $2 million from reimbursement
of preconstruction costs to be reserved as contingency for Monterey One Water
to be used towards the Pure Water Monterey Project.
FISCAL IMPACT: Funding an additional $2 million towards the
PWM project will come from the proceeds received from SRF loan toward
reimbursement of planning and development costs.