ITEM: |
PUBLIC HEARING |
||||
|
|||||
17. |
CONSIDER DECLARING Monterey
County Zoning Ordinance Inapplicable to the Sleepy Hollow Steelhead Rearing
Facility Upgrade (CEQA: Does not constitute a “Project” per
California Environmental Quality Act (CEQA) Guidelines 15378 (b).) |
||||
|
|||||
Meeting
Date: |
July 16,
2018 |
Budgeted: |
N/A |
||
|
|||||
From: |
David A. Stoldt, |
Program/ |
2-3-1-F |
||
|
General Manager |
Acct. No.: |
24-04-785812 |
||
|
|||||
Staff
Contact: |
Larry Hampson |
Cost
Estimate: |
N/A |
||
|
|||||
General
Counsel Approval: Yes. |
|||||
Committee
Recommendation: N/A |
|||||
CEQA Compliance: Does not constitute a project per CEQA
guidelines 15378(b) as it is an organizational or
administrative activity that will not result in direct or indirect physical
changes in the environment. |
|||||
SUMMARY: The Board will consider whether to exempt
construction activities proposed to upgrade the Sleepy
Hollow Steelhead Rearing Facility (SHSRF) from complying with Monterey
County zoning ordinances under Government Code Section 53096, which provides
for such an exemption for facilities related to the storage and transmission of
water. Operation of the SHSRF is a
required mitigation for diversion of Carmel River flows for municipal use.
The District submitted an initial application for
permits to upgrade the SHSRF to the Monterey County Resource Management Agency
(RMA) in March 2017. RMA staff have
indicated that the earliest a hearing can be scheduled to consider the project is
July 26, 2018, after which there would be a one to three-month period to clear
permit conditions before construction could commence.
Construction of the facility upgrade must
begin in early August 2018 in order to complete certain construction activities
in the channel of the Carmel River prior to October 1, 2018, which is the
deadline that the Regional Water Quality Control Board has set to complete work
in the channel of the Carmel River. Issuance
of permits by Monterey County in late August or September (or later) would not
allow the District to complete construction of necessary facilities by the October
1 deadline.
In order to exempt the facility upgrade under
Government Code Section 53096, the Board must find that there is no feasible
alternative and must vote to do so by four-fifths of its members. For a seven-member Board, six votes would be necessary
to approve this action.
RECOMMENDATION: Staff
recommends that the Board adopt Resolution 2018-18 (Exhibit 17-A) declaring Monterey County Zoning
Ordinance inapplicable to the Sleepy Hollow Steelhead Rearing Facility Upgrade.
DISCUSSION: The Board
certified the Allocation Program Environmental Impact Report (EIR) in November
1990 and set limits on how much water the community may use from the Carmel
River. A Mitigation Program was adopted to mitigate
for impacts associated with the diversion and use of Carmel River flows to meet
municipal demand. The Mitigation Program
included the construction and operation of the Sleepy Hollow Steelhead Rearing
Facility (SHSRF), which is located along the Carmel River about one mile
downstream of the former San Clemente Dam site.
An 800-foot long channel that simulates natural river conditions is the
centerpiece of the facility and has been operated since 1996 to mitigate for
the impacts to steelhead due to Carmel River diversions by California American
Water and other diverters along the river that dry up the stream in the lower
nine miles of the river almost annually.
The facility is designed to rear steelhead rescued from reaches of the
river before it goes dry. Steelhead are reared
for several months at the SHSRF and are returned to the river when it reconnects
to the lagoon, usually in late fall or early winter.
With the removal of San Clemente Dam and an
increase in debris and sediment load at the facility’s water intake, an upgrade
is required to replace the intake and make the facility plumbing and filtration
capabilities more robust to withstand changing conditions in water quality and
quantity. In addition, the National
Marine Fisheries Service and the California Department of Fish and Wildlife are
requiring the District to operate the facility for longer periods in order to
hold fish in the facility until habitat conditions in the river are the best
possible for steelhead survival. Because
river flows can remain very low during drought periods, the facility may also need
to operate year-round, which it is not designed to do currently. In addition to required operation under the
Allocation Program EIR, the State Water Resources Control Board has also
required that the facility continue to operate as a condition of Order 95-10
and subsequent Cease-and-Desist Orders, which require Cal-Am to reduce unlawful
Carmel River diversions and find replacement supplies.
The Facility Upgrade Project includes: 1)
temporarily diverting flow in the Carmel River in order to remove the existing
intake and install a new intake with erosion protection that will be capable of
providing flow to the rearing facility under a variety of adverse conditions; and
2) installing new pumps, plumbing, filters, a building to house facilities, and
other upgrades to allow recirculation of a portion of rearing channel flow. The Project includes mitigation measures to
reduce potential impacts from the work to a less than significant level.
District staff submitted an initial application
to Monterey County in March 2017 for an Amended Use Permit to construct the
proposed facility upgrade (original construction of the facility was completed
under a 1996 Use Permit issued by the County).
There were long delays in processing the facility upgrade application through
Monterey County and there were delays in obtaining information and making
design changes in response to RMA and Monterey County Water Resources Agency comments
on the design. Eventually, in April
2018, the project application was considered complete; however, a hearing on
the application is not scheduled until July 26, 2018. After approval of an Amended Use Permit, the
County requires an applicant to obtain a grading permit and building
permit. In addition, several conditions
attached to the draft Amended Use Permit require further County review and
approval of several documents and plans before construction can begin. The additional review and approval process by
the County was estimated by the County planner to take 30 to 60 days if there
are no complications during review. With
this schedule, the soonest the project could start would be late August and
more likely late September or later if there are complications in meeting
permit conditions.
The facility upgrade has been designed to meet
the 2016 California Building Code adopted by the County as well as Monterey
County’s requirements for facilities built adjacent to the Carmel River. District staff and third-party inspection
services will carry out inspections and monitor construction activities to
ensure that the project is built according to the design and in compliance with
permits issued by the U.S. Army Corps of Engineers, the Regional Water Quality
Control Board, and the California Department of Fish and Wildlife.
Work in the channel of the Carmel River
requires dewatering of a portion of the bottom of the river. There is a limited time during the year when
this can occur – usually between July and October when Carmel River flows are
at their lowest. At other times of the
year, steelhead are migrating through the river and would be impacted by
in-channel work or river flows are too high to work in.
It is important to note that the California
Department of Fish and Wildlife and the National Marine Fisheries Service have
allowed the District to forego operation of the Sleepy Hollow Steelhead Rearing
Facility in 2018 to accommodate construction of the upgrade in 2018 in a single
phase. This was an unusual action by
these agencies, as the alternative to placing fish at SHSRF that are rescued
from drying reaches of the river SHSRF is to place them in river reaches with
perennial flow, which can result in overcrowding and higher loss of
steelhead.
If the facility is required to be operation
while an upgrade is carried out, completing the upgrade would require several
phases of construction. This would
increase costs and the complexity of completing construction and commissioning
the project. In addition, staff believe
that it may not be possible to run the SHSRF without completion of the
upgrade. This is due to the large volume
of sand that was introduced to the river at the SHSRF site after the removal of
San Clemente Dam. Occasional use of the
SHSRF pumps to provide water for routine maintenance in 2017 (a year that the
facility was not required to be operated due to year-round flow in the river) resulted
in large volumes of sand passing through the system intake in just a few hours. The intake and pumps are not designed for
this type of condition.
Staff estimate that construction in the
channel bottom could take eight weeks to complete. If construction of the facility upgrade is
approved by the MPWMD Board at the July 16, 2018 meeting, it is anticipated
that construction would start in early August and would be finished by the
October 1 deadline. A later start would
compromise the feasibility of completing work in the channel in 2018 and would
trigger phasing and additional costs for the project. Completion of the facility upgrade and
commissioning operations of the new facilities would likely be delayed into
2020, which would be an undesirable outcome for steelhead.
Staff have concluded that it is not feasible
to complete construction activities in the Carmel River channel in 2018, if the
project start must wait for the issuance of all Monterey County permits for
this project. It is District staff’s
understanding that RMA staff and MCWRA staff would not object to the District
taking an action under Government Code 53096.
MCWRA staff stated that the re-design of the facility has satisfied
their concern about a potential increase in the 100-year flood elevation. In addition, the project was re-designed to
meet more stringent seismic safety standards recommended in a building-specific
geotechnical investigation requested by the County RMA.
CEQA and Government Code Action Required
Under Government Code 53096, the governing board of a local agency may declare city or county zoning ordinance inapplicable to a proposed use of property for facilities related to storage or transmission of water. The Board certified the Allocation Program EIR in November 1990 that set a limit on how much water Cal-Am can divert to its system and at the same time adopted a Mitigation Program to mitigate for impacts associated with the diversion and use of Carmel River flow by Cal-Am and others. The Mitigation Program included construction and operation of the SHSRF. Thus, the SHSRF meets the test of being a facility related to transmission of water. The proposed facility upgrade was previously approved by the Board at their November 14, 2016 meeting under a Mitigated Negative Declaration. The Board subsequently amended the Project on January 25, 2017 and July 16, 2018 (see related item in this packet under Public Hearings) and the State Coastal Conservancy amended the Project on November 30, 2017.
It is staff’s opinion that it is not feasible to obtain Monterey County permits and complete the project in a timely manner. Completion of the upgrade is necessary to ensure that the facility can operate with changed conditions in the Carmel River due to the removal of San Clemente Dam. A delay in completing the facility upgrade would likely result in harm to steelhead present in drying reaches of the river due to the risk that those steelhead would not be allowed to be placed into perennial flow reaches and create an overcrowding condition.
IMPACT TO DISTRICT RESOURCES: There would be reduced costs to the District by not having to pay additional Monterey County fees associated with obtaining permits.
EXHIBIT
17-A Resolution 2018-18 Rendering
Monterey County Zoning Ordinance Inapplicable to the Sleepy Hollow Steelhead Rearing Facility
Upgrade
U:\staff\Boardpacket\2018\20180716\PublicHrng\17\Item-17.docx