ITEM:

INFORMATIONAL ITEMS/STAFF REPORT

 

27.

MONTHLY WATER SUPPLY AND CALIFORNIA AMERICAN WATER PRODUCTION REPORT

 

Meeting Date:

July 16, 2018

Budgeted: 

N/A

 

From:

David J. Stoldt,

Program/

N/A

 

General Manager

Line Item No.:

 

 

 

 

Prepared By:

Jonathan Lear

Cost Estimate:

N/A

 

General Counsel Review:  N/A

Committee Recommendation:  N/A

CEQA Compliance:  Exempt from environmental review per SWRCB Order Nos. 95-10 and 2016-0016, and the Seaside Basin Groundwater Basin adjudication decision, as amended and Section 15268 of the California Environmental Quality Act (CEQA) Guidelines, as a ministerial project; Exempt from Section 15307, Actions by Regulatory Agencies for Protection of Natural Resources.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Exhibit 27-A shows the water supply status for the Monterey Peninsula Water Resources System (MPWRS) as of July 1, 2018.  This system includes the surface water resources in the Carmel River Basin, the groundwater resources in the Carmel Valley Alluvial Aquifer and the Seaside Groundwater Basin.  Exhibit 27-A is for Water Year (WY) 2018 and focuses on four factors: rainfall, runoff, and storage.  The rainfall and Streamflow values are based on measurements in the upper Carmel River Basin at Sleepy Hollow Weir. 

 

Water Supply Status:  Rainfall through June 2018 totaled 0.0 inches and brings the cumulative rainfall total for WY 2018 to 13.52 inches, which is 65% of the long-term average through June.  Estimated unimpaired runoff during June totaled 1,136 acre-feet (AF) and brings the cumulative runoff total for WY 2018 to 31,376 AF, which is 47% of the long-term average through June.  Usable storage for the MRWPRS was 29,580 acre-feet, which is 96% of average through June, and equates to 79% percent of system capacity 

 

Production Compliance:  Under State Water Resources Control Board (SWRCB) Cease and Desist Order No. 2016-0016 (CDO), California American Water (Cal-Am) is allowed to produce no more than 8,310 AF of water from the Carmel River in WY 2018.  Through June, using the CDO accounting method, Cal-Am has produced 5,956 AF from the Carmel River (including ASR capped at 600 AF, Table 13, and Mal Paso.)  In addition, under the Seaside Basin Decision, Cal-Am is allowed to produce 1,820 AF of water from the Coastal Subareas and 0 AF from the Laguna Seca Subarea of the Seaside Basin in WY 2018.  Through June, Cal-Am has produced 1,965 AF from the Seaside Groundwater Basin.  Through May, 532 AF of Carmel River Basin groundwater have been diverted for Seaside Basin injection; 0 AF have been recovered for customer use, and 153 AF have been diverted under Table 13 water rights.  Cal-Am has produced 7,071 AF for customer use from all sources through June.  Exhibit 27-C shows production by source.  Some of the values in this report may be revised in the future as Cal-Am finalizes their production values and monitoring data.  The 12 month moving average of production for customer service is 9,935 AF, which is below the rationing trigger of 10,130 AF for WY 2018.

 

EXHIBITS

27-A    Water Supply Status: July 1, 2018

27-B    Monthly Cal-Am Diversions from Carmel River and Seaside Groundwater Basins:  WY 2018

27-C    Monthly Cal-Am production by source: WY 2018

 