ITEM:

CONSENT CALENDAR

 

14.

CONSIDER APPROVAL OF ADDITIONAL EXPENDITURE TO HDR ENGINEERING, INC. FOR THE LOS PADRES DAM FISH PASSAGE STUDY

 

Meeting Date:

June 17, 2019

Budgeted: 

Yes

 

From:

David J. Stoldt,

General Manager

Program/

Los Padres Dam Long Term Plan

 

 

Line Item No.:    

1-1-2-A

 

Prepared By:

Larry Hampson

Cost Estimate:

$10,000

 

General Counsel Review:  N/A

Committee Recommendation:  The Administrative Committee reviewed this item on June 10, 2019 and recommended approval.

CEQA Compliance:  Exempt,  CEQA Section 15262 (Feasibility and Planning Studies)

 

SUMMARY:  On April 18, 2016, the MPWMD Board approved entering into an agreement for services with HDR Engineering, Inc. (HDR) for a Not-to-Exceed amount of $310,000 to conduct a fish passage study at Los Padres Dam.  The cost of the study was reimbursed by Cal-Am as part of the 2015-2017 General Rate Case approved by the California Public Utilities Commission.  The original schedule for this project anticipated completion in December 2017.  Due to several circumstances occurring outside of the District’s and HDR’s control during Project implementation, HDR has requested additional schedule, scope, and budget to complete the project successfully. The need for this contract amendment has grown over the past several months due to turnover in the Technical Review Committee (TRC) formed to review the study and requests from the TRC for additional meetings.  HDR has also incurred unanticipated project management costs due to the extended length of the project as described in Exhibit 14-A.

 

Approximately $28,000 remains as a contingency from the April 18, 2016 Board authorization.   Staff needs an additional $10,000 authorized to complete the study.  This additional spending is included in the 2019-2020 Budget to be adopted by the Board on June 17, 2019.

 

RECOMMENDATION:  Staff is requesting the Board authorize additional spending in the amount of $10,000 to complete the Los Padres Dam fish passage study. 

 

DISCUSSION:  HDR has completed about 90% of the work outlined in the original scope of the fish passage study.  Because this study has gone on for much longer than anticipated, there has been a 100% turnover of staff assigned to the TRC from the California Department of Fish and Wildlife and the National Marine Fisheries Service (there has been no turnover in staff assigned to this project at Cal-Am and MPWMD).    Funds requested by HDR will cover expenses associated with additional meetings with the TRC, additional analysis requested at TRC meetings, and project management costs.  A final report is expected to be concluded by December 2019. 

 

EXHIBIT

14-A    Request for Contract Amendment (Cover Letter)

 

U:\staff\Boardpacket\2019\20190617\ConsentClndr\14\Item-14.docx