CEQA Compliance:  Exempt from environmental review per SWRCB Order Nos. 95-10 and 2016-0016, and the Seaside Basin Groundwater Basin adjudication decision, as amended and Section 15268 of the California Environmental Quality Act (CEQA) Guidelines, as a ministerial project; Exempt from Section 15307, Actions by Regulatory Agencies for Protection of Natural Resources.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Exhibit 30-A shows the water supply status for the Monterey Peninsula Water Resources System (MPWRS) as of July 1, 2019.  This system includes the surface water resources in the Carmel River Basin, the groundwater resources in the Carmel Valley Alluvial Aquifer and the Seaside Groundwater Basin.  Exhibit 30-A is for Water Year (WY) 2019 and focuses on four factors: rainfall, runoff, and storage.  The rainfall and Streamflow values are based on measurements in the upper Carmel River Basin at Sleepy Hollow Weir. 

 

Water Supply Status:  Rainfall through June 2019 totaled 0 inches and brings the cumulative rainfall total for WY 2019 to 30.93 inches, which is 147% of the long-term average through June.  Estimated unimpaired runoff through June totaled 3,102 acre-feet (AF) and brings the cumulative runoff total for WY 2019 to 142,850 AF, which is 215% of the long-term average through June.  Usable storage for the MRWPRS was 31,220 acre-feet, which is 101% of average through June, and equates to 83% percent of system capacity 

 

Production Compliance:  Under State Water Resources Control Board (SWRCB) Cease and Desist Order No. 2016-0016 (CDO), California American Water (Cal-Am) is allowed to produce no more than 8,310 AF of water from the Carmel River in WY 2019.  Through June, using the CDO accounting method, Cal-Am has produced 5,539 AF from the Carmel River (including ASR capped at 600 AF, Table 13, and Mal Paso.)  In addition, under the Seaside Basin Decision, Cal-Am is allowed to produce 1,820 AF of water from the Coastal Subareas and 0 AF from the Laguna Seca Subarea of the Seaside Basin in WY 2019.  Through June, Cal-Am has produced 1,775 AF from the Seaside Groundwater Basin.  Through May, 1,335 AF of Carmel River Basin groundwater have been diverted for Seaside Basin injection; 0 AF have been recovered for customer use, and 471 AF have been diverted under Table 13 water rights.  Cal-Am has produced 6,822 AF for customer use from all sources through June.  Exhibit 30-C shows production by source.  Some of the values in this report may be revised in the future as Cal-Am finalizes their production values and monitoring data.  The 12 month moving average of production for customer service is 9,719 AF, which is below the rationing trigger of 10,130 AF for WY 2019.

 

EXHIBITS

30-A Water Supply Status: July 1, 2019

30-B Monthly Cal-Am Diversions from Carmel River and Seaside Groundwater Basins:  WY 2019

30-C Monthly Cal-Am production by source: WY 2019