ITEM: |
CONSENT CALENDAR |
||||
|
|||||
4. |
Consider AUGMENTING Expenditures for
Permitting of a New Carmel River Fish Counting Weir (Exempt under CEQA Guidelines Section 15306 and
15378) |
||||
|
|||||
Meeting Date: |
August
19, 2019 |
Budgeted: |
Yes |
||
|
|||||
From: |
Dave Stoldt, General Manager |
Program/ |
Protect Environmental Quality |
||
|
|
Line Item No.: |
Program
– Aquatic Resources Fisheries |
||
|
|
|
|||
Prepared By: |
Kevan Urquhart |
Cost Estimate: |
$
10,000 |
||
|
|||||
General Counsel Approval:
N/A |
|||||
Committee Recommendation:
The Administrative Committee reviewed this item on August 12, 2019 and
recommended approval. |
|||||
CEQA
Compliance: The primary project is
Categorically Exempt under the California Environmental Quality Act
Guidelines section 15306, and the remaining actions do not constitute a
project as defined by the California Environmental Quality Act Guidelines
section 15378. |
|||||
SUMMARY:
The District needs to complete the permitting
process required to install a new fish counting weir that will enumerate the
full annual run size of Carmel River steelhead.
This process was initiated in fall 2018.
The last permit to be applied for is a California Department of Fish
& Wildlife (CDFW), 5-Year Lake & Streambed Alteration Agreement (LSAA) permit that staff will prepare
in August. We also need to augment and
extend the existing agreement between Denise Duffy & Associates (DD&A)
and the District to assist in completing the process of acquiring other State
and local permits or waivers.
RECOMMENDATION: Staff recommends the
Board of Directors: (1) approve an expenditure of $3,288.75 for the CDFW LSAA five–year permit fee that increased in
2019; (2) authorize the General Manager to augment and extend an existing agreement
with DD&A for a not-to-exceed additional amount of $5,000.00 for assistance
with remaining permit acquisition; and (3) include a $1,711.25 contingency for
a total expenditure of $10,000.00.
BACKGROUND:
The District had budgeted for a new fish-counting weir to be built
in the winter of 2018-2019 at River Mile ~0.5. It will be placed between the banks of the
Carmel River on property owned by the Carmel Area Wastewater District and the
City of Carmel-by-the-Sea. It will be
removed and reinstalled annually for up to a six month monitoring season from
December – May. The design is a
resistance board weir, attached with sand anchors to the substrate, where the
center panels are hinged, allowing them to lay down and flatten out under high
flows, so that debris can pass over the structure. The weir includes a trap for adult steelhead
on one bank. Regulatory agency
permitting requirements being applied to this project, but almost nowhere else
in California to other identical projects, have delayed its installation an
increased permit preparation costs and application fees.
The
District originally maintained a DIDSON hydro-acoustic sound camera upstream of
this location on loan from the CDFW for this purpose, but the use of that
device in the lower river has been rendered ineffective by the large number of
striped bass that now regularly move up and down the river, which cannot be distinguished
from steelhead with existing hydro-acoustic technology.
Preliminary consultations with CDFW and National Marine Fisheries Service staff operating these types of weirs from Santa Cruz County to the Oregon border, and in the Sacramento Valley, had suggested that other Counties, the United States Army Corps of Engineers (USACoE) and the State Coastal Commission (SCC) did not previously exert permit jurisdiction over these kinds of seasonal temporary installations elsewhere, and we might simply have to notify the parties and request a waiver. CDFW’s Central Region has indicated they will require a LSAA not required in other Regions, which also required the District to conduct CEQA compliance through issuing Notice of Exemption last fall. The Monterey County Water Resources Agency requires formal consultation on any structures placed in the Carmel River flood plain, but decided it did not need to exert jurisdiction or undergo permitting for this project. The USACoE decided to exert jurisdiction and require Federal Endangered Species Act (ESA) Section 7 consultation with the U.S. Fish and Wildlife Service (USFWS) and the National Marine Fisheries Service (NMFS), because the area is deemed under tidal influence for at least part of the year. The USACoE staff have completed their review and site visit, but the federal interagency Section 7 consultations remain to be completed, and may incur more consulting support for any responses.
The Board approved an initial $15,000 for this effort in August 20, 2018, which has been exhausted, so that the budget has to be augmented to continue the process.
ACTION #1:
The Board should approve an expenditure of $3,288.75 to acquire a CDFW LSAA for the next five years of weir
operations.
ACTION #2: The Board should authorize the General
Manager to amend and extend an agreement with DD&A for a not-to-exceed augmentation
of $5,000 to the existing contract for assistance with permit acquisition. DD&A will be responsible for completing
the USACoE permit application process, including ESA
Section 7 consultations with the USFWS or NMFS, and assisting with the CDFW
LSAA permit application, if necessary. MPWMD would acquire a CDFW LSAA permit
for the project; and supervise installation by a specialized biological
consulting firm to be selected as a result of a bid process in September 2019.
ACTION #3: The Board should authorize a $1,711.25
contingency for a total expenditure of $10,000.
IMPACT
TO STAFF/RESOURCES: Thirty percent of the funds for the permits
and to retain the services of DD&A in the FY 2019-2020 Fisheries Program
Budget under account 24-04-785851 “2-3-4 Monitoring of Adult Steelhead Counts: A.
Resistance Board Weir Construction (Permitting)”, and the remaining 70% will come
from the same account under “2-3-4 Monitoring of Adult Steelhead Counts: B.
Resistance Board Weir. Staff time will
also be needed for the CDFW LSAA application, and to oversee the project.
None
U:\staff\Boardpacket\2019\20190819\ConsentCalendar\04\Item-4.docx