ITEM: |
CONSENT
CALENDAR |
||||
|
|||||
3. |
CONSIDER AUTHORIZATION
OF ADDITIONAL CONTINGENCY FUNDS FOR CONSTRUCTION AND RELATED SERVICES FOR THE
SLEEPY HOLLOW STEELHEAD REARING FACILITY RAW WATER INTAKE AND WATER SUPPLY
SYSTEM UPGRADE PROJECT |
||||
|
|||||
Meeting
Date: |
November
18, 2019 |
Budgeted: |
No;
funds to be identified from changes to FY2019-2020 Budget |
||
|
|||||
From: |
David J. Stoldt, General Manager |
Program/ |
Protect
Environmental Quality
|
||
|
|
Line Item
No.: |
2-3-1 & other Mitigation Program activities |
||
|
|||||
Prepared
By: |
Larry
Hampson |
Cost
Estimate: |
$134,500 |
||
|
|||||
General
Counsel Review: N/A |
|||||
Committee
Recommendation: The Administrative
Committee reviewed this item on November 13, 2019 and recommended approval by
a 3-0 vote. |
|||||
CEQA Compliance: The
Board certified the Final Initial Study/Mitigated Negative Declaration,
approved this project, and adopted the Mitigation and Monitoring and
Reporting Plan on November 14, 2016. |
|||||
SUMMARY: As of November 1, 2019, staff estimates that
approximately $51,000 remains of the previous Board authorizations to complete
the Sleepy Hollow Facility Upgrade (the Project). An additional amount of up to $134,500 will
be required to complete approximately $185,500 of additional change orders
identified during facility start-up (see the following tables). Staff has identified funds for the additional
work, which would come from Sleepy Hollow operations funds and Carmel River
program activities in the Mitigation Program that will not be expended in FY
2019-20 (approximately $143,000). Adjustments
to individual budgeted line items would be made at the mid-year budget
adjustment.
The Board has previously authorized up to
$257,165 in contingency funds for the project. Staff recommends that an additional $134,600
in contingency funds be authorized for the project.
RECOMMENDATION: The Board of Directors should approve the
following action:
Authorize the General Manager to approve additional
change orders to construction and service contracts or for new service
contracts for the Project in an amount up to $134,500 in total. With this action, authorized contingency
funds for the Project would rise from $257,165 to $391,165.
DISCUSSION: The Sleepy Hollow Steelhead Rearing Facility
upgrade (the Project) includes a new intake structure in the Carmel River, new
pumps, a dual filtration system, modifications to the cooling tower, disease
control (ultraviolet radiation of circulating water), a recirculating
aquaculture system (RAS), a degassing system, an oxygenator, a power upgrade, advanced
alarm systems, and an integrated control system. Current costs and proposed additional funding
is as shown in the table below. In 2018,
the District obtained a grant of $1.8 million for the Project from the State
Coastal Conservancy, which is administering funds from a Settlement Agreement
between Cal-Am and the National Marine Fisheries Service that funds Carmel
River steelhead improvement projects.
Sleepy Hollow
Facility Upgrade Budget and Estimated Costs as of November 2019
Item |
Authorized
Funding |
Estimated
Variance (+) |
Estimated
Variance (-) |
Total |
Construction |
$1,802,835 |
$32,025 |
($34,140 |
$1,800,720 |
Survey Control |
$10,000 |
|
($10,000) |
$0 |
Inspection/testing |
$5,000 |
|
|
$5,000 |
Record Drawings & Engineering
Assistance |
$25,000 |
|
|
$25,000 |
Contingency |
$257,165 |
|
($38,800 |
$218,365 |
Sub-Total Expenditures |
$2,100,000 |
$32,025 |
($82,940) |
$2,049,085 |
Expected Additional Change Orders |
|
185,500 |
|
$185,500 |
Sub-Total |
|
|
|
$2,234,585 |
Additional Funds Required (Total Project
Cost – Current Authorization) |
|
|
|
$134,585 |
Most of the construction in the original
contract for the facility upgrade and subsequent change orders authorized with previously
approved Board funding were complete as of the first week of November 2019,
although several “punchlist” items remain.
Contingency funds have been used for services and materials for road
repairs, additional facility upgrades, additional equipment, installation of a
sign, construction testing, and a power upgrade by PG&E. The largest additional expenditure to date has
been road repairs, due to damage from heavy construction equipment as well as
almost daily contractor access and staff access.
During facility startup and inspections,
several additional change orders were identified as shown in the table below. If the Board approves additional funding, the
total of authorized contingency funds would be $391,165, which represents about
17.5% of the estimated total project cost.
Proposed Additional Change Orders
IMPACTS ON STAFF AND RESOURCES: Funds for additional contingency expenses,
should they occur, would be funded from Sleepy Hollow Operations (Budget
Program line item 2-3-1) and other Carmel River Riparian Mitigation Program
items (2-1-1 through 2-1-5) that were budgeted, but will not be expended in FY
2019-20. If this item is approved, funds
for the additional contingency amount would be identified in the mid-year FY2019-20
budget adjustment.
Several District staff are involved in the
upgrade assisting with project management, inspections, permit compliance, fish
rescue, revegetation, monitoring and facility commissioning. The work is being performed under the direction of the District
Engineer.
EXHIBITS
None