ITEM: |
INFORMATIONAL
ITEM/STAFF REPORT |
||||
|
|||||
19. |
MONTHLY PROGRESS REPORT – SANTA MARGARITA WATER TREATMENT
FACILITY |
||||
|
|||||
Meeting Date: |
January 23, 2020 |
Budgeted: |
N/A |
||
|
|||||
From: |
David J. Stoldt |
Program/ |
N/A |
||
|
General Manager |
Line Item: |
|
||
|
|||||
Prepared By: |
Maureen Hamilton |
Cost Estimate: |
N/A |
||
|
|||||
General Counsel Review: N/A |
|||||
Committee
Recommendation: N/A |
|||||
CEQA Compliance: This action does not constitute a project as
defined by the California Environmental Quality Act Guidelines Section 15378. |
|||||
SUMMARY: This status report is provided for information only, no action is required.
Completed work:
· Excavation and construction of the building footings was completed.
· Construction of the cellar walls was completed.
· In advance of scheduled cellar floor concrete pour; the base course, moisture barrier, and rebar installation were installed.
· Forty-two submittals have been received; twenty of those submittals have been reviewed and closed.
· No change orders have been initiated.
· The construction schedule shows the facility will be ready for Cal Am to conduct its SCADA installation and implementation beginning July 23, 2020. The critical path item is the Motor Control Center. An executive construction schedule should be available in February.
EXPENDITURES:
|
Contract |
Contingency (10%) |
Board Authorization |
$4,797,500 |
$479,750 |
Change Orders |
|
$0 (0%) |