ITEM:

INFORMATIONAL ITEM/STAFF REPORT

 

26.

MONTHLY WATER SUPPLY AND CALIFORNIA AMERICAN WATER PRODUCTION REPORT

 

Meeting Date:

January 23, 2020

Budgeted: 

N/A

 

From:

David J. Stoldt,

Program/

N/A

 

General Manager

Line Item No.:

 

 

 

 

Prepared By:

Jonathan Lear

Cost Estimate:

N/A

 

General Counsel Review:  N/A

Committee Recommendation:  N/A

CEQA Compliance:  Exempt from environmental review per SWRCB Order Nos. 95-10 and 2016-0016, and the Seaside Basin Groundwater Basin adjudication decision, as amended and Section 15268 of the California Environmental Quality Act (CEQA) Guidelines, as a ministerial project; Exempt from Section 15307, Actions by Regulatory Agencies for Protection of Natural Resources.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Exhibit 26-A shows the water supply status for the Monterey Peninsula Water Resources System (MPWRS) as of January 1, 2020.  This system includes the surface water resources in the Carmel River Basin, the groundwater resources in the Carmel Valley Alluvial Aquifer and the Seaside Groundwater Basin.  Exhibit 26-A is for Water Year (WY) 2020 and focuses on four factors: rainfall, runoff, and storage.  The rainfall and Streamflow values are based on measurements in the upper Carmel River Basin at Sleepy Hollow Weir. 

 

Water Supply Status:  Rainfall through December 2019 totaled 8.62 inches and brings the cumulative rainfall total for WY 2020 to 10.23 inches, which is 151% of the long-term average through December.  Estimated unimpaired runoff through December totaled 13,072 acre-feet (AF) and brings the cumulative runoff total for WY 2020 to 14,284 AF, which is 205% of the long-term average through December.  Usable storage for the MRWPRS was 30,240 acre-feet, which is 104% of average through December, and equates to 80% percent of system capacity 

 

Production Compliance:  Under State Water Resources Control Board (SWRCB) Cease and Desist Order No. 2016-0016 (CDO), California American Water (Cal-Am) is allowed to produce no more than 8,310 AF of water from the Carmel River in WY 2020.  Through December, using the CDO accounting method, Cal-Am has produced 1,758 AF from the Carmel River (including ASR capped at 600 AF, Table 13, and Mal Paso.)  In addition, under the Seaside Basin Decision, Cal-Am is allowed to produce 1,820 AF of water from the Coastal Subareas and 0 AF from the Laguna Seca Subarea of the Seaside Basin in WY 2020.  Through December, Cal-Am has produced 789 AF from the Seaside Groundwater Basin.  Through December, 257 AF of Carmel River Basin groundwater have been diverted for Seaside Basin injection; 0 AF have been recovered for customer use, and 75 AF have been diverted under Table 13 water rights.  Cal-Am has produced 2,382 AF for customer use from all sources through December.  Exhibit 26-C shows production by source.  Some of the values in this report may be revised in the future as Cal-Am finalizes their production values and monitoring data.  The 12 month moving average of production for customer service is 9,764 AF, which is below the rationing trigger of 10,130 AF for WY 2020.

 

EXHIBITS

26-A    Water Supply Status: December 1, 2019

26-B    Monthly Cal-Am Diversions from Carmel River and Seaside Groundwater Basins:  WY 2020

26-C    Monthly Cal-Am production by source: WY 2020

 

U:\staff\Boardpacket\2020\20200123\InfoItems\26\Item-26.docx