ITEM: |
PUBLIC
HEARING |
||||
|
|||||
12. |
CONSIDER ADOPTION OF
MID-YEAR FISCAL YEAR 2019-2020 BUDGET ADJUSTMENT |
||||
|
|||||
Meeting
Date: |
March 16, 2020 |
Budgeted: |
N/A |
||
|
|||||
From: |
David J.
Stoldt, |
Program/ |
N/A |
||
|
General
Manager |
Line Item No.: |
|||
|
|||||
Prepared
By: |
Suresh
Prasad |
Cost Estimate: |
N/A |
||
|
|||||
General Counsel Review: N/A |
|||||
Committee Recommendation: N/A |
|||||
CEQA Compliance: This action does not constitute a project
as defined by the California Environmental Quality Act Guidelines Section
15378. |
|||||
SUMMARY: Annually, the District considers its financial position after the end of the first 7-8 months of the fiscal year (FY). District staff has reviewed income and spending patterns from July 1, 2019 through the end of February 29, 2020 and determined that adjustments to the FY 2019-2020 Budget is required. The FY 2019-2020 Budget was adopted on June 17, 2019. Included in the budget adjustment process was a review of staffing levels, supplies, outside services, project expenditures, current work assignments and other factors affecting the current budget. The table below summarizes the proposed changes to the budget:
Monterey Peninsula Water Management District |
|||
2019-2020 |
|||
Mid-Year Budget Adjustment-Summary |
|||
Revenue |
Adopted |
Change |
Amended |
Property Tax |
$2,050,000 |
$0 |
$2,050,000 |
Permit Fees - WDD |
175,000 |
0 |
175,000 |
Permit Fees - WDS |
56,000 |
0 |
56,000 |
Capacity Fee |
400,000 |
100,000 |
500,000 |
User Fees |
5,000,000 |
0 |
5,000,000 |
Water Supply Charge |
3,400,000 |
0 |
3,400,000 |
Interest |
180,000 |
50,000 |
230,000 |
Other |
15,000 |
0 |
15,000 |
Subtotal District Revenues |
11,276,000 |
150,000 |
11,426,000 |
Reimbursements - CAW |
1,229,700 |
270,000 |
1,499,700 |
Reimbursements - Watermaster |
35,000 |
0 |
35,000 |
Reimbursements - Reclamation |
20,000 |
0 |
20,000 |
Reimbursements - Other |
126,300 |
0 |
126,300 |
Reimbursements - Recording
Fees |
6,000 |
0 |
6,000 |
Reimbursements - Legal Fees |
16,000 |
0 |
16,000 |
Grants |
468,000 |
0 |
468,000 |
Subtotal Reimbursements |
$1,901,000 |
$270,000 |
$2,171,000 |
|
|
|
|
Carry Forward/Use of
Reserves |
4,862,350 |
3,328,900 |
8,191,250 |
Total Revenues |
$18,039,350 |
$3,748,900 |
$21,788,250 |
Expenditures |
Adopted |
Change |
Amended |
Personnel |
$4,054,100 |
($55,000) |
$3,999,100 |
Supplies & Services |
1,369,700 |
55,000 |
1,424,700 |
Project Expenditures |
10,550,000 |
4,007,700 |
14,557,700 |
Fixed Assets |
213,900 |
0 |
213,900 |
Debt Service |
230,000 |
0 |
230,000 |
Capital Equip. Reserve |
49,500 |
0 |
49,500 |
General Fund Balance |
302,150 |
(258,800) |
43,350 |
Pension Reserve |
100,000 |
0 |
100,000 |
OPEB Reserve |
100,000 |
0 |
100,000 |
Reclamation Project |
1,000,000 |
0 |
1,000,000 |
Contingency |
70,000 |
0 |
70,000 |
Total |
$18,039,350 |
$3,748,900 |
$21,788,250 |
As the table above indicates, project expenditures increased by
$4,007,700. Most of the expenditure increases were previously authorized by the
Board after the original budget adoption and are now incorporated into the
mid-year budget. Detailed information
regarding all other proposed changes, as well as their effect on reserves, is
detailed in the background section of this report.
RECOMMENDATION: Following a presentation by District staff and a public hearing, staff recommends adoption of the proposed mid-year budget adjustment for FY 2019-2020.
BACKGROUND: The Board of Directors adopted the original FY 2019-2020 budget on June 17, 2019. The paragraphs below summarize the original budget, proposed mid-year adjustments to the budget and projected reserves accounts.
Revenues
The 2019-2020 adopted budget anticipated revenue sources in the amount of $18,039,350. Through February 29, 2020, actual revenue collections totaled $8,607,809 or about 48% of the budgeted amount. Revenues for the first half of this FY year are in line with previous year figures. District staff has analyzed the revenue activity for the first 8 months of the FY, as well as activities scheduled for the remainder of the FY, and recommends various adjustments to the revenue portion of the budget as shown in Exhibit 12-A and discussed below:
The cumulative effect of these revenue adjustments is an increase of $420,000 in projected revenues for FY 2019-2020.
Expenditures
The original budget envisioned expenditures of $18,039,350 in the fiscal year ending June 30, 2020. Through February 29, 2020, actual expenditures totaled $6,799,879, or approximately 38% of the budgeted amount. The spending pattern at mid-way point of the fiscal year is not unusual because most of the project expenditures for the first half of each fiscal year are low. District staff has analyzed the expenditure activity for the first 8 months of the fiscal year, as well as activities scheduled for the remainder of the fiscal year, and recommends various adjustments to the expenditure portion of the budget as discussed below:
The cumulative effect of the adjustments to the expenditure side of the budget is a net increase of $4,007,700. Additional use of reserve in the amount of $3,328,900 is need to balance the mid-year budget.
Reserves
The District’s reserve balance is projected to be as follows:
Monterey
Peninsula Water Management District |
|||||
Analysis of
Reserves |
|||||
2019-2020 |
|||||
Projected |
Actual |
||||
Balance |
Balance |
FY 2019-2020 |
Est. Balance |
||
Reserves |
6/30/2019 |
6/30/2019 |
Budget |
|
06/30/2020 |
Litigation/Insurance Reserve |
250,000 |
250,000 |
0 |
$250,000 |
|
Capital Equipment Reserve |
532,000 |
532,000 |
21,000 |
$553,000 |
|
Flood/Drought Reserve |
328,944 |
328,944 |
0 |
$328,944 |
|
Debt Reserve |
221,656 |
222,098 |
0 |
$222,098 |
|
Pension Reserve |
100,000 |
100,000 |
100,000 |
$200,000 |
|
OPEB Reserve |
100,000 |
100,000 |
100,000 |
$200,000 |
|
General Operating Reserve |
12,397,965 |
15,482,297 |
(8,119,400) |
$7,362,897 |
|
Totals |
$13,930,565 |
$17,015,339 |
($7,898,400) |
|
$9,116,939 |
The above adjustments will result in an estimated reserve balance of 9,116,939 at June 30, 2020 as shown on Exhibit 12-F. This amount meets the minimum 5% of the operating budget established by the Board during the 2005-06 budget process. The original adopted budget had a projected reserve balance of $14,077,665 for the FY.
12-A Revenues
12-B Personnel Costs
12-C Supplies & Services Costs
12-D Capital Assets
12-E Project Expenditures
12-F Reserves Analysis
U:\staff\Boardpacket\2020\20200316\PublicHearings\12\Item-12.docx