ITEM: |
INFORMATIONAL
ITEM/STAFF REPORT |
||||
|
|||||
24. |
MONTHLY WATER SUPPLY AND
CALIFORNIA AMERICAN WATER PRODUCTION REPORT |
||||
|
|||||
Meeting Date: |
February 19, 2020 |
Budgeted: |
N/A |
||
|
|||||
From: |
David J. Stoldt, |
Program/ |
N/A |
||
|
General Manager |
Line Item No.: |
|
||
|
|
|
|||
Prepared By: |
Jonathan Lear |
Cost Estimate: |
N/A |
||
|
|||||
General Counsel Review: N/A |
|||||
Committee Recommendation: N/A |
|||||
CEQA
Compliance: Exempt from environmental
review per SWRCB Order Nos. 95-10 and 2016-0016, and the Seaside Basin
Groundwater Basin adjudication decision, as amended and Section 15268 of the
California Environmental Quality Act (CEQA) Guidelines, as a ministerial
project; Exempt from Section 15307, Actions by Regulatory Agencies for
Protection of Natural Resources. |
|||||
Exhibit 24-A shows the water
supply status for the Monterey Peninsula Water Resources System (MPWRS) as of February 1, 2020. This system includes the surface water
resources in the
Water Supply Status: Rainfall
through February 2020 totaled 0.0 inches
and brings the
cumulative rainfall total for WY 2020 to 11.48
inches, which is 74% of the
long-term average through February. Estimated unimpaired runoff through February totaled 3,153 acre-feet
(AF) and brings the cumulative runoff total for WY 2020 to 23,235 AF, which is 65% of
the long-term average through February. Usable storage for the MRWPRS was 30,420 acre-feet, which is 98% of average through February, and equates to 81% percent of system capacity
Production Compliance: Under State Water Resources Control Board (SWRCB) Cease and Desist Order No. 2016-0016 (CDO), California American Water (Cal-Am) is allowed to produce no more than 8,310 AF of water from the Carmel River in WY 2020. Through February, using the CDO accounting method, Cal-Am has produced 3,106 AF from the Carmel River (including ASR capped at 600 AF, Table 13, and Mal Paso.) In addition, under the Seaside Basin Decision, Cal-Am is allowed to produce 1,820 AF of water from the Coastal Subareas and 0 AF from the Laguna Seca Subarea of the Seaside Basin in WY 2020. Through February, Cal-Am has produced 1,013 AF from the Seaside Groundwater Basin. Through February, 418 AF of Carmel River Basin groundwater have been diverted for Seaside Basin injection; 0 AF have been recovered for customer use, and 88 AF have been diverted under Table 13 water rights. Cal-Am has produced 3,739 AF for customer use from all sources through February. Exhibit 24-C shows production by source. Some of the values in this report may be revised in the future as Cal-Am finalizes their production values and monitoring data. The 12 month moving average of production for customer service is 9,830 AF, which is below the rationing trigger of 10,130 AF for WY 2020.
EXHIBITS
24-A Water Supply Status: February
1, 2020
24-B Monthly Cal-Am Diversions from Carmel River and Seaside Groundwater Basins: WY 2020
24-C Monthly Cal-Am production by source: WY 2020
U:\staff\Boardpacket\2020\20200316\InfoItems\24\Item-24.docx