ITEM: |
INFORMATIONAL
ITEM/STAFF REPORT |
||||
|
|||||
12. |
MONTHLY PROGRESS REPORT – SANTA MARGARITA WATER TREATMENT
FACILITY |
||||
|
|||||
Meeting Date: |
August 17, 2020 |
Budgeted: |
N/A |
||
|
|||||
From: |
David J. Stoldt |
Program/ |
N/A |
||
|
General Manager |
Line Item: |
|
||
|
|||||
Prepared By: |
Maureen Hamilton |
Cost Estimate: |
N/A |
||
|
|
|
|
||
General Counsel Review: N/A |
|||||
Committee
Recommendation: The Administrative Committee reviewed
this item on August 11, 2020. |
|||||
CEQA Compliance: This action does not constitute a project as
defined by the California Environmental Quality Act Guidelines Section 15378. |
|||||
SUMMARY: This progress report is provided for information only, no action is required.
Work conducted after the previous progress report:
· Most doors installed.
· Completed plaster and paint.
· Final grading prior to concrete and asphalt installation.
· Poured southern sidewalk.
· Installed on-site trench drains.
· Installing interior piping and pumps.
· Began work on HVAC, southern gate, curb and gutter.
· Ninety-nine submittals have been received; ninety-seven of those submittals have been closed.
Change orders for the following work were issued:
· Additional MCC Disconnect ($8,979.00)
· Relocation of Lighting Panel ($17,982.74)
· Deletion of Compressor (-$8,500.00)
· Chemical Room Heater Control Addition to 3 rooms ($20,000)
A no-cost change order extending substantial completion (date at which Cal Am can begin SCADA work) to August 26, 2020 was issued. The date will be further extended to accommodate a change to the MCC breaker requested by Cal Am.
EXPENDITURES:
Base Contract: $4,649,400.00
Change Orders: $ 108,246.94 (2.3%)[1]
Total: $4,757,646.94
Paid: $2,370,988.50
(50%)[2]
EXHIBIT
None
U:\staff\Boardpacket\2020\20200817\InfoItems\12\Item-12.docx