ITEM: |
INFORMATIONAL
ITEM/STAFF REPORT |
||||
|
|||||
19. |
MONTHLY INFORMATIONAL PROGRESS REPORT – SANTA MARGARITA WATER
TREATMENT FACILITY. |
||||
|
|||||
Meeting Date: |
September 21, 2020 |
Budgeted: |
N/A |
||
|
|||||
From: |
David J. Stoldt |
Program/ |
N/A |
||
|
General Manager |
Line Item: |
|
||
|
|||||
Prepared By: |
Maureen Hamilton |
Cost Estimate: |
N/A |
||
|
|||||
General Counsel Review: N/A |
|||||
Committee
Recommendation: The Administrative
Committee reviewed this item on September 15, 2020. |
|||||
CEQA Compliance: This action does not constitute a project as
defined by the California Environmental Quality Act Guidelines Section 15378. |
|||||
SUMMARY: This progress report is provided for information only, no action is required.
Work conducted after the previous progress report:
· Doors and hardware completed
· Unloading pad installed
· Exterior chemical unloading panels installed
· Installing interior piping and pumps
· Constructed remaining columns to support gates
· Asphalt delivery road and parking installed
No new change orders were issued since the previous progress report.
The Contractor submitted 4 notices of delay due to chemical room electrical strut material backorder, lead time for Motor Control Center main disconnect component added in Change Order 4, 2.5” PVC coated rigid steel electrical fitting backorder, and another Covid 19 infection.
All parties are working to mitigate the delays so that handover to Cal Am happens the end of this month. A startup planning meeting is scheduled for Thursday September 10, 2020.
EXPENDITURES:
Base Contract: $4,649,400.00
Change Orders: $ 108,246.94 (2.3%)[1]
Total: $4,757,646.94
Paid: $2,370,988.50 (50%)[2]
EXHIBIT
None
U:\staff\Boardpacket\2020\20200921\InformationalItems\19\Item-19.docx