ITEM: |
INFORMATIONAL
ITEM/STAFF REPORT |
||||
|
|||||
5. |
MONTHLY PROGRESS REPORT – SANTA MARGARITA WATER TREATMENT
FACILITY |
||||
|
|||||
Meeting Date: |
November 10, 2020 |
Budgeted: |
N/A |
||
|
|||||
From: |
David J. Stoldt |
Program/ |
N/A |
||
|
General Manager |
Line Item: |
|
||
|
|||||
Prepared By: |
Maureen Hamilton |
Cost Estimate: |
N/A |
||
|
|||||
General Counsel Review: N/A |
|||||
Committee
Recommendation: N/A |
|||||
CEQA Compliance: This action does not constitute a project as
defined by the California Environmental Quality Act Guidelines Section 15378. |
|||||
SUMMARY: This progress report is provided for information only; no action is required.
Work conducted after the previous progress report:
· Interior works plumbed to exterior header
· Electrical system commissioned
· Control system commissioned
· Operator training
· Chemicals delivered
· Started the facility calibrating both ASR1 and ASR3 wells on sodium hypochlorite (disinfectant) and zinc orthophosphate (corrosion inhibitor).
No change orders were authorized during this time period. Additional change orders are being negotiated.
EXPENDITURES:
Base Contract: $4,649,400.00
Change Orders: $ 140,225.78 (3.0%)[1]
Total: $4,789,625.72
Paid: $4,031,129.16 (84%)[2]