ITEM: |
ACTION ITEM |
||||
|
|||||
16. |
CONSIDER EXPENDITURE OF FUNDS FOR THE MAINTENANCE AND
REPAIR OF THE REARING CHANNEL LINER AT THE SLEEPY HOLLOW STEELHEAD REARING
FACILITY |
||||
|
|||||
Meeting Date: |
February 25, 2021 |
Budgeted: |
No |
||
|
|||||
From: |
David J. Stoldt, General Manager |
Program/ |
Protect Environmental Quality |
||
|
|
Line Item No.: |
2-3-1 A General operations and maintenance |
||
|
|||||
Prepared By: |
Beverly Chaney and Larry Hampson |
Cost Estimate: |
$13,363 |
||
|
|||||
General Counsel Review: N/A |
|||||
Committee
Recommendation: The Administrative Committee reviewed this item on
February 10, 2021 and recommended approval. |
|||||
CEQA
Compliance: Categorical Exemption, Section 15301, Existing
Facilities. |
|||||
SUMMARY: Staff proposes to hire Scardina
Builders, Inc. to repair a portion of the liner used in the rearing channel at
the Sleepy Hollow Steelhead Rearing Facility. The cost of repair is
estimated to be $12,363 (see Exhibit 16-A).
District staff would like to include a $1,000 contingency for this project.
Work must be completed prior to the initiation of 2021 operations and should
take approximately one week. Because the needed repair work was
discovered after the adoption of the FY 2020-2021 budget in June 2020, the
General operations and maintenance line item should be increased with the
mid-year budget adjustment.
RECOMMENDATION: The Administrative Committee
recommends that the Board of Directors approve the following actions:
A) Authorize repairs at a Not-to-Exceed cost of $13,363; and
B) Authorize a mid-year budget adjustment of $13,363 in line item
2-3-1 A. General operations and maintenance for the Sleepy Hollow Steelhead
Rearing Facility.
DISCUSSION: The Sleepy Hollow Steelhead Rearing
Facility was recently upgraded to allow for expanded use of the facility and
was operated for several months in 2020. However, no repairs were
made to the original 800 feet of liner in the rearing channel during the
upgrade project. In the past when there was evidence of minor leaks in
the liner, staff have carried out repairs. Operations during 2020
showed that the liner, which was installed in 1996 and is made of Hypalon, has
deteriorated to the point that there are water leaks out of the channel through
the bottom and sides at several locations. The location proposed for
repairs is one of the largest leaks along the channel and could cause loss of
support material for the liner and concrete walls. The liner has
been repaired previously but must now be replaced in this section and the new
section joined to the adjacent upstream section. It is important to note, that
the current liner is sitting on sand, and part of this repair is to put in a
concrete floor to support the liner at this location. After testing out the new
repair, with the addition of the concrete floor, the remainder of the rearing
channel pools will be evaluated. This will allow staff to determine if the
other pools should have this type of repair in the future. If repair of the
other pools is necessary, staff will request additional quotes for the work and
place a line item in the 2021-22 budget. Staff has worked with Scardina
Builders, Inc., on several other maintenance projects at the facility.
IMPACTS ON STAFF AND
RESOURCES: Funds for
repairs will be included in the FY 2020-2021 mid-year budget adjustment under
Program line item 2-3-1 A. General operations and maintenance.
EXHIBIT
16-A January 15, 2021 Cost Estimate
from Scardina Builders, Inc.
U:\staff\Boardpacket\2021\20210225\Action
Items\16\Item-16.docx