CONSIDER ADOPTION OF MID-YEAR FISCAL YEAR 2020-2021 BUDGET ADJUSTMENT

 

Meeting Date:

March 15, 2021

Budgeted: 

N/A

 

From:

David J. Stoldt,

Program/

N/A

 

General Manager

Line Item No.:

 

Prepared By:

Suresh Prasad

Cost Estimate:

N/A

 

General Counsel Review:  N/A

Committee Recommendation:  N/A

CEQA Compliance:  This action does not constitute a project as defined by the California Environmental Quality Act Guidelines Section 15378.

 

SUMMARY:  Annually, the District considers its financial position after the end of the first 7-8 months of the fiscal year (FY).  District staff has reviewed income and spending patterns from July 1, 2020 through the end of January 31, 2021 and determined that adjustments to the FY 2020-2021 Budget is required.  The FY 2020-2021 Budget was adopted on June 15, 2020.  Included in the budget adjustment process was a review of staffing levels, supplies, outside services, project expenditures, current work assignments and other factors affecting the current budget.  The table below summarizes the proposed changes to the budget:

 

Monterey Peninsula Water Management District

2020-2021

Mid-Year Budget Adjustment-Summary

Revenue

Adopted

Change

Amended

Property Tax

$2,050,000

$0

$2,050,000

Permit Fees - WDD

150,000

0

150,000

Permit Fees - WDS

48,000

0

48,000

Capacity Fee

400,000

0

400,000

User Fees

4,250,000

750,000

5,000,000

Water Supply Charge

3,300,000

0

3,300,000

PWM Water Sales

0

4,800,000

4,800,000

Interest

200,000

0

200,000

Other

15,000

0

15,000

Subtotal District Revenues

10,413,000

5,550,000

15,963,000

Reimbursements - CAW

1,754,700

0

1,754,700

Reimbursements - Reclamation Tank

500,000

0

500,000

Reimbursements - Watermaster

35,000

0

35,000

Reimbursements - Reclamation

20,000

0

20,000

Reimbursements - Other

126,300

0

126,300

Reimbursements - Recording Fees

6,000

0

6,000

Reimbursements - Legal Fees

16,000

0

16,000

Grants

2,495,400

0

2,495,400

Subtotal Reimbursements

$4,953,400

$0

$4,953,400

Carry Forward/Use of Reserves

7,058,100

0

7,058,100

From Capital Equipment Reserve

57,900

9,000

66,900

From Fund Balance

1,939,400

(1,412,700)

526,700

Total Revenues

$24,421,800

$4,146,300

$28,568,100

Expenditures

Adopted

Change

Amended

Personnel

$4,038,700

($40,000)

$3,998,700

Supplies & Services

1,499,600

(34,300)

1,465,300

Project Expenditures

16,639,100

4,211,600

20,850,700

Fixed Assets

220,000

9,000

229,000

Debt Service

230,000

0

230,000

Capital Equip. Reserve

324,400

0

324,400

General Fund Balance

500,000

0

500,000

Pension Reserve

100,000

0

100,000

OPEB Reserve

100,000

0

100,000

Mechanics Bank Reserve

500,000

0

500,000

Election Expense

200,000

0

200,000

Contingency

70,000

0

70,000

       Total

$24,421,800

$4,146,300

$28,568,100

 

 

As the table above indicates, most of the change is attributed to increase in User Fee revenue and Pure Water Monterey (PWM) Water Sales revenue. The off-set on the expenditure side is increase in project expenditures related to PWM water purchase. Additionally, a reduction in use of reserves which was adopted with the original budget.  Detailed information regarding all other proposed changes, as well as their effect on reserves, is detailed in the background section of this report.

 

RECOMMENDATION:  Following a presentation by District staff and a public hearing, staff recommends adoption of the proposed mid-year budget adjustment for FY 2020-2021.

 

BACKGROUND:  The Board of Directors adopted the original FY 2020-2021 budget on June 15, 2020.  The paragraphs below summarize the original budget, proposed mid-year adjustments to the budget and projected reserves accounts.

 

Revenues

 

The 2020-2021 adopted budget anticipated revenue sources in the amount of $24,421,800.    Through January 31, 2021, actual revenue collections totaled $9,359,530 or about 38% of the budgeted amount.  District staff has analyzed the revenue activity for the first seven months of the FY, as well as activities scheduled for the remainder of the FY, and recommends various adjustments to the revenue portion of the budget as shown in Exhibit 10-A and discussed below:

 

 

The cumulative effect of these revenue adjustments is an increase of $4,146,300 in projected revenues for FY 2020-2021.

 

Expenditures

 

The original budget envisioned expenditures of $24,421,800 in the fiscal year ending June 30, 2021.  Through January 31, 2021, actual expenditures totaled $9,587,583, or approximately 39% of the budgeted amount.  The spending pattern at mid-way point of the fiscal year is not unusual because most of the project expenditures for the first half of each fiscal year are low.  District staff has analyzed the expenditure activity for the first seven months of the fiscal year, as well as activities scheduled for the remainder of the fiscal year, and recommends various adjustments to the expenditure portion of the budget as discussed below:

 

 

 

 

 

The cumulative effect of the adjustments to the expenditure side of the budget is a net increase of $4,146,300. Use of reserve in the amount of $526,700 is need to balance the mid-year budget.  Original budget had anticipated use of reserve in the amount of $1,939,400.

 

 

Reserves

 

The District’s reserve balance is projected to be as follows:

 

Monterey Peninsula Water Management District

Analysis of Reserves

2020-2021

Projected

Actual

Balance

Balance

FY 2020-2021

Est. Balance

Reserves

6/30/2020

6/30/2020

Budget

 

06/30/2021

Litigation/Insurance Reserve

250,000

250,000

0

$250,000

Capital Equipment Reserve

553,000

581,500

257,500

$839,000

Flood/Drought Reserve

328,944

328,944

0

$328,944

Debt Reserve

222,098

222,524

0

$222,524

Pension Reserve

200,000

200,000

100,000

$300,000

OPEB Reserve

200,000

200,000

100,000

$300,000

Mechanics Bank Reserve

0

0

500,000

$500,000

General Operating Reserve

9,677,197

16,308,941

(7,084,800)

$9,224,141

                                Totals

$11,431,239

$18,091,909

($6,127,300)

 

$11,964,609

 

 

The above adjustments will result in an estimated reserve balance of 11,964,609 at June 30, 2021 as shown on Exhibit 10-F.  This amount meets the minimum 5% of the operating budget established by the Board during the 2005-06 budget process.  The original adopted budget had a projected reserve balance of $10,958,339 for the FY.

 

EXHIBITS

10-A    Revenues

10-B    Personnel Costs

10-C    Supplies & Services Costs

10-D    Capital Assets

10-E    Project Expenditures

10-F    Reserves Analysis

 

 

 

U:\staff\Boardpacket\2021\20210315\Action Items\10\Item-10.docx