ITEM: |
CONSENT
CALENDAR |
||||
|
|||||
8. |
CONSIDER Expenditure of Funds to Maintain the access
ROAD to the Sleepy Hollow Steelhead Rearing Facility |
||||
|
|||||
Meeting
Date: |
April
19, 2021 |
Budgeted: |
Yes |
||
|
|||||
From: |
David J. Stoldt, General Manager |
Program/ |
Protect
Environmental Quality
|
||
|
|
Line Item
No.: |
2-3-1 C Road Maintenance |
||
|
|||||
Prepared
By: |
Thomas
Christensen |
Cost
Estimate: |
$10,000 |
||
|
|||||
General
Counsel Review: N/A |
|||||
Committee
Recommendation: The Administrative
Committee reviewed this item on April 12, 2021 and recommended approval. |
|||||
CEQA Compliance: Categorical Exemption, Section 15301,
Existing Facilities. |
|||||
SUMMARY: Staff proposes to hire a contractor (Cordrey Construction) to carry
out road maintenance along the access to the Sleepy Hollow Steelhead Rearing
Facility. The cost of repairs is
estimated to be up to $10,000. This
amount is already in the adopted current year budget. Work should be carried
out prior to the initiation of 2021 operations at the facility and should take less
than one week. Due to the 2020 Carmel
fire and subsequent intense rains in late January, an exceptional amount of
rock and debris washed down onto the access road and there are several large
potholes along the road.
RECOMMENDATION: The
Administrative Committee recommends that the Board consider hiring the proposed
contractor and approve the funds for road maintenance.
DISCUSSION: The Sleepy Hollow Steelhead Rearing Facility is
accessed from Carmel Valley Road over an approximately one-mile single lane
dirt road on Cal-Am property east of Carmel Valley Village. Cal-Am and the District have a shared
interest in maintaining the road. In
September 2020, Cal-Am carried out over $400,000 of slope stabilization work after
MPWMD notified Cal-Am that the road was unsafe.
In January 2021, the road was blocked by debris in several locations as
a result of intense rainfall on steep slopes burned during the 2020 Carmel
fire.
Cal-Am equipment cleared most, but not
all, of the debris from the access road and made it passable for high-clearance
vehicles. Portions of the road still
need some clean-up for safe passage and a section that turns to deep mud after
rain requires placement of base rock.
Staff’s priority is to repair the worst sections of the road first. If any funds are left after completion of the
priority items, they would be used to start repairing potholes along the road.
District staff received a quote from Scardina
Builders (Exhibit 8-A) and requested a
quote from Cordrey Construction. Both
firms are licensed contractors and both are located in Carmel Valley. An estimate had not been received from
Cordrey Construction by the deadline for staff notes.
IMPACTS ON STAFF AND RESOURCES: Funds for maintenance work were included in
the FY 2020-2021 budget Program line item 2-3-1 C. Road Maintenance.
EXHIBIT
8-A March 23, 2021 Cost Estimate from Scardina
Builders, Inc.
U:\staff\Boardpacket\2021\20210419\ConsentCalendar\08\Item-8.docx