UPDATE ON INTEGRATED REGIONAL WATER MANAGEMENT GRANT STATUS

 

Meeting Date:

April 19, 2021

Budgeted: 

N/A

 

From:

David J. Stoldt, 

Program/

N/A

 

General Manager

Line Item No.: 

N/A

 

Prepared By:

David J. Stoldt

Cost Estimate:

N/A

 

General Counsel Approval:  N/A

Committee Recommendation:  N/A

CEQA Compliance:  This action does not constitute a project as defined by the California Environmental Quality Action Guidelines Section 15378.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

SUMMARY:  On April 4, 2021 the District received the executed Integrated Regional Water Management (IRWM) Implementation Round 1 Grant agreement (Agreement) for the Monterey Peninsula region in the amount of $2,238,904.

 

Next steps will be to issue subgrant agreements to the local project sponsors and start getting various required documents submitted to DWR.

 

The District, as “Grantee”, has many duties including (a) administration of the Agreement with California Department of Water Resources, (b) invoicing, with documentation, on behalf of the Local Project Sponsors, (c) progress reporting.

 

There are three projects – all non-District—that are being supported by this Implementation Round 1 grant, as described in Exhibit 15-A attached.

 

EXHIBIT

15-A    Implementation Round 1 Local Projects Receiving Grant Funding

 

 