ITEM:

INFORMATIONAL ITEMS/STAFF REPORT

 

24.

MONTHLY WATER SUPPLY AND CALIFORNIA AMERICAN WATER PRODUCTION REPORT

 

Meeting Date:

May 17, 2021

Budgeted: 

N/A

 

From:

David J. Stoldt,

Program/

N/A

 

General Manager

Line Item No.:

 

 

 

 

Prepared By:

Jonathan Lear

Cost Estimate:

N/A

 

General Counsel Review:  N/A

Committee Recommendation:  N/A

CEQA Compliance:  Exempt from environmental review per SWRCB Order Nos. 95-10 and 2016-0016, and the Seaside Basin Groundwater Basin adjudication decision, as amended and Section 15268 of the California Environmental Quality Act (CEQA) Guidelines, as a ministerial project; Exempt from Section 15307, Actions by Regulatory Agencies for Protection of Natural Resources.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Exhibit 24-A shows the water supply status for the Monterey Peninsula Water Resources System (MPWRS) as of May 1, 2021.  This system includes the surface water resources in the Carmel River Basin, the groundwater resources in the Carmel Valley Alluvial Aquifer and the Seaside Groundwater Basin.  Exhibit 24-A is for Water Year (WY) 2021 and focuses on four factors: rainfall, runoff, and storage.  The rainfall and Streamflow values are based on measurements in the upper Carmel River Basin at Sleepy Hollow Weir. 

 

Water Supply Status:  Rainfall through April 2021 totaled 0.04 inches and brings the cumulative rainfall total for WY 2021 to 10.85 inches, which is 53% of the long-term average through April.  Estimated unimpaired runoff through April totaled 2,398 acre-feet (AF) and brings the cumulative runoff total for WY 2021 to 15,042 AF, which is 24% of the long-term average through April.  Usable storage for the MRWPRS was 28,390 acre-feet, which is 90% of average through April, and equates to 86% percent of system capacity. 

 

Production Compliance:  Under State Water Resources Control Board (SWRCB) Cease and Desist Order No. 2016-0016 (CDO), California American Water (Cal-Am) is allowed to produce no more than 7,310 AF of water from the Carmel River in WY 2021.  Through April, using the CDO accounting method, Cal-Am has produced 2,652 AF from the Carmel River (including ASR capped at 600 AF, Table 13, and Mal Paso.)  In addition, under the Seaside Basin Decision, Cal-Am is allowed to produce 1,474 AF of water from the Coastal Subareas and 0 AF from the Laguna Seca Subarea of the Seaside Basin in WY 2021.  Through April, Cal-Am has produced 977 AF from the Seaside Groundwater Basin.  Through March, 66 AF of Carmel River Basin groundwater have been diverted for Seaside Basin injection; 0 AF have been recovered for customer use, 17 AF have been diverted under Table 13 water rights, and 1,476 AF of Pure Water Monterey recovered.  Cal-Am has produced 5,098 AF for customer use from all sources through April.  Exhibit 24-B shows production by source.  Some of the values in this report may be revised in  the future as Cal-Am finalizes their production values and monitoring data.  

 

EXHIBITS

24-A    Water Supply Status: May 1, 2021

24-B    Monthly Cal-Am production by source: WY 2021

U:\staff\Boardpacket\2021\20210517\Information Items\24\Item-24.docx