ITEM: |
ACTION ITEM |
||||
|
|||||
8. |
Consider Approving and Authorizing the District
to Enter into an Amended and Restated Water Purchasing Agreement for the Pure
Water Monterey Project Expansion |
||||
|
|||||
Meeting Date: |
August 16, 2021 |
Budgeted: |
|
||
|
|||||
From: |
David J. Stoldt, General Manager |
Program/ |
|
||
|
|
Line Item No.: |
|
||
|
|||||
Prepared By: |
David J. Stoldt |
Cost Estimate: |
|
||
|
|||||
General Counsel Approval: N/A |
|||||
Committee Recommendation: None |
|||||
CEQA
Compliance: This action does not
constitute a project as defined by the California Environmental Quality Act
Guidelines Section 15378. |
|||||
SUMMARY: On May
11, 2021 District staff, representatives of California American Water Company
(Cal-Am), and Monterey One Water (M1W) staff met to discuss opening discussions
on construction of the Pure Water Monterey (PWM) expansion project and what
terms and conditions, or amendments to the existing water purchase agreement
(WPA), might be necessary. In all the
parties had nine meetings and exchanged terms and suggested language fourteen
times. Attorneys for all the parties
participated in the meetings.
It was decided that, using the existing WPA as a starting point, an
Amended and Restated Water Purchase Agreement would be the best approach to contract
for water deliveries from the combined base and expanded PWM project. There were several areas of
discussion/negotiation: (a) recitals, (b) project construction timeline, (c)
water delivery guarantees, (d) financial penalties in event of default, (e) the
public agency’s actions in event of cost recovery for stranded desalination
expenditures, if any, and (f) the public agency’s support of alternative water
supply sources in the event of repeated failure to meet PWM delivery
guarantees.
District staff believes the draft Amended and Restated WPA attached
hereto as Exhibit 8-A
meets the objectives of all three parties.
The California Public Utilities Commission (CPUC) will need to approve
the WPA before the parties can sign it.
It is not yet clear what process will be utilized to secure CPUC
approval, but it is expected that the CPUC will do so. Agreement by all three parties that each
intends to sign the WPA when approved will serve as a basis for expenditure of
pre-construction monies for design, bid documents, additional environmental
work, and permitting. It is likely the
District will be asked to participate in such pre-construction funding based
upon the WPA.
RECOMMENDATION: The
Board should consider approval of the attached draft Amended and Restated Water
Purchase Agreement and authorize the General Manager to sign it once CPUC
approval is obtained.
EXHIBIT
8-A Proposed (Draft) Amended and Restated Water Purchase Agreement Dated August 11, 2021
U:\staff\Boardpacket\2021\20210816\Action
Items\08\Item-8.docx