CEQA Compliance:  Exempt from environmental review per SWRCB Order Nos. 95-10 and 2016-0016, and the Seaside Basin Groundwater Basin adjudication decision, as amended and Section 15268 of the California Environmental Quality Act (CEQA) Guidelines, as a ministerial project; Exempt from Section 15307, Actions by Regulatory Agencies for Protection of Natural Resources.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Exhibit 16-A shows the water supply status for the Monterey Peninsula Water Resources System (MPWRS) as of August 1, 2021.  This system includes the surface water resources in the Carmel River Basin, the groundwater resources in the Carmel Valley Alluvial Aquifer and the Seaside Groundwater Basin.  Exhibit 16-A is for Water Year (WY) 2021 and focuses on four factors: rainfall, runoff, and storage.  The rainfall and Streamflow values are based on measurements in the upper Carmel River Basin at Sleepy Hollow Weir. 

 

Water Supply Status:  Rainfall through July 2021 totaled 0.00 inches and brings the cumulative rainfall total for WY 2021 to 10.85 inches, which is 52% of the long-term average through July.  Estimated unimpaired runoff through June totaled 58 acre-feet (AF) and brings the cumulative runoff total for WY 2021 to 16,193 AF, which is 24% of the long-term average through June.  Usable storage for the MRWPRS was 26,530 acre-feet, which is 91% of average through June, and equates to 80% percent of system capacity. 

 

Production Compliance:  Under State Water Resources Control Board (SWRCB) Cease and Desist Order No. 2016-0016 (CDO), California American Water (Cal-Am) is allowed to produce no more than 7,310 AF of water from the Carmel River in WY 2021.  Through June, using the CDO accounting method, Cal-Am has produced 3,947 AF from the Carmel River (including ASR capped at 600 AF, Table 13, and Mal Paso.)  In addition, under the Seaside Basin Decision, Cal-Am is allowed to produce 1,474 AF of water from the Coastal Subareas and 0 AF from the Laguna Seca Subarea of the Seaside Basin in WY 2021.  Through July, Cal-Am has produced 1,346 AF from the Seaside Groundwater Basin.  Through July, 66 AF of Carmel River Basin groundwater have been diverted for Seaside Basin injection; 0 AF have been recovered for customer use, 17 AF have been diverted under Table 13 water rights, and 2,472 AF of Pure Water Monterey recovered.  Cal-Am has produced 7,791 AF for customer use from all sources through July.  Exhibit 16-B shows production by source.  Some of the values in this report may be revised in the future as Cal-Am finalizes their production values and monitoring data.  

 

EXHIBITS

16-A    Water Supply Status: August 1, 2021

16-B    Monthly Cal-Am production by source: WY 2021

 

 