ITEM: |
INFORMATIONAL
ITEM/STAFF REPORT |
||||
|
|||||
16. |
MONTHLY WATER SUPPLY AND |
||||
|
|||||
Meeting Date: |
August 16, 2021 |
Budgeted: |
N/A |
||
|
|||||
From: |
David J. Stoldt, |
Program/ |
N/A |
||
|
General Manager |
Line Item No.: |
|
||
|
|
|
|||
Prepared By: |
Jonathan Lear |
Cost Estimate: |
N/A |
||
|
|||||
General Counsel Review: N/A |
|||||
Committee Recommendation: N/A |
|||||
CEQA
Compliance: Exempt from environmental
review per SWRCB Order Nos. 95-10 and 2016-0016, and the Seaside Basin Groundwater
Basin adjudication decision, as amended and Section 15268 of the California
Environmental Quality Act (CEQA) Guidelines, as a ministerial project; Exempt
from Section 15307, Actions by Regulatory Agencies for Protection of Natural
Resources. |
|||||
Exhibit 16-A shows the water
supply status for the Monterey Peninsula Water Resources System (MPWRS) as of August 1, 2021. This system includes the surface water
resources in the
Water Supply Status: Rainfall
through July 2021 totaled 0.00 inches and brings
the cumulative rainfall total for WY 2021 to 10.85 inches, which is 52%
of the long-term average through July. Estimated unimpaired runoff through June totaled 58 acre-feet (AF) and
brings the cumulative runoff total for WY 2021 to 16,193 AF, which is 24% of the long-term average through June.
Usable storage for the MRWPRS was 26,530
acre-feet, which is 91% of
average through June, and equates to
80% percent of system capacity.
Production Compliance: Under State Water Resources Control Board (SWRCB) Cease and Desist Order No. 2016-0016 (CDO), California American Water (Cal-Am) is allowed to produce no more than 7,310 AF of water from the Carmel River in WY 2021. Through June, using the CDO accounting method, Cal-Am has produced 3,947 AF from the Carmel River (including ASR capped at 600 AF, Table 13, and Mal Paso.) In addition, under the Seaside Basin Decision, Cal-Am is allowed to produce 1,474 AF of water from the Coastal Subareas and 0 AF from the Laguna Seca Subarea of the Seaside Basin in WY 2021. Through July, Cal-Am has produced 1,346 AF from the Seaside Groundwater Basin. Through July, 66 AF of Carmel River Basin groundwater have been diverted for Seaside Basin injection; 0 AF have been recovered for customer use, 17 AF have been diverted under Table 13 water rights, and 2,472 AF of Pure Water Monterey recovered. Cal-Am has produced 7,791 AF for customer use from all sources through July. Exhibit 16-B shows production by source. Some of the values in this report may be revised in the future as Cal-Am finalizes their production values and monitoring data.
EXHIBITS
16-A Water Supply Status: August
1, 2021
16-B Monthly Cal-Am production by source: WY 2021
U:\staff\Boardpacket\2021\20210816\Informational
Items\16\Item-16.docx