ITEM: |
CONSENT
CALENDAR |
||||
|
|||||
3. |
Consider Expenditure of Funds for the Manufacture and Supply of
Five Fiberglass Reinforced Tanks for the Sleepy Hollow Steelhead Rearing
Facility |
||||
|
|||||
|
|||||
Meeting Date: |
October
18, 2021 |
Budgeted: |
Yes |
||
|
|||||
From: |
David J. Stoldt, General Manager |
Program/ |
Protect
Environmental Quality
|
||
|
|
Line Item
No.: |
2-3-1-O |
||
|
|||||
Prepared By: |
Larry
Hampson |
Cost
Estimate: |
$
48,000 |
||
|
|||||
General
Counsel Review: N/A |
|||||
Committee
Recommendation: The Administrative
Committee reviewed this item on October 11, 2021, and recommended approval. |
|||||
CEQA Compliance: Exempt
under §15301 Existing Facilities. |
|||||
SUMMARY: Staff proposes to contract for the manufacture
and delivery of five fiberglass reinforced plastic (FRP) tanks to the Sleepy
Hollow Steelhead Rearing Facility (SHSRF) in Carmel Valley. The tanks would replace the original tanks,
which are used to quarantine incoming steelhead and are at the end of their
useful life. One bid for the procurement
project was received from Reiff Manufacturing for $43,477.12 (see Exhibit 3-A).
The engineer’s estimate for the project was $55,000.
RECOMMENDATION: The Administrative Committee recommends that
the Board authorize the General Manager to enter into a contract with Reiff
Manufacturing for procurement and delivery of five FRP tanks in an amount
not-to-exceed $43,477.12 and approve a contingency of approximately $4,523 for
unforeseen circumstances.
DISCUSSION: The SHSRF rearing facility was initially
constructed in 1996. In 2018, the
District undertook a major upgrade of several of the components necessary to
successfully rear steelhead rescued from the Carmel River. However, the five 8-foot diameter fiberglass
quarantine tanks used to control disease in fish rescued from the river were
not replaced with the 2018 upgrade. The
tanks and their support systems are in various states of disrepair with cracks
and failing foundation supports. The existing
tanks are also not insulated, which leads to stress-inducing water
temperatures. New tanks would be
insulated and include covers to minimize heat gain during warm periods.
Due to potentially long lead times for
manufacture and delivery of tanks and the relatively short window for
construction work between operational periods, staff opted to advertise for
manufacture and delivery of new tanks as a separate project. Bid
advertisements were placed three times with the Monterey County Weekly; the
project was placed on ebidboard.com (a comprehensive cross-agency database of
California public works construction projects and documents); and staff reached
out via email to several FRP tank manufacturers including Aquatic Enterprises
in San Jose, DT Fiberglass in Sacramento, Integrated Aqua Systems in San Diego,
and Reiff Manufacturing in Walla Walla, Washington.
Reiff Manufacturing was the sole bidder
for the procurement project. The bid (Exhibit
3-A) and Bid Bond (Exhibit 3-B) responded to all District requirements
(note that sales tax of $3,127.12 was not listed as a separate item but was
included in the bid). Reiff provided
three FRP tanks for the 2018 SHSRF upgrade and has 30 years of experience with
manufacturing FRP tanks.
CEQA:
The
California Environmental Quality Act Section 15301 exempts maintenance of
mechanical equipment for existing facilities, including those under section i)
“ Maintenance of fish screens, fish
ladders, wildlife habitat areas, artificial wildlife waterway devices,
streamflows, springs and waterholes, and stream channels (clearing of debris)
to protect fish and wildlife resources; ”
The quarantine tanks are an integral part
of the rearing facility.
IMPACTS ON STAFF AND RESOURCES: Funds for this work are budgeted under Sleepy
Hollow Operations Budget Program line item 2-3-1-O Design/Construct Rearing
Channel and Quarantine Tank Improvements.
The work would be performed under the direction of the District Engineer. An approximate 10% contingency is requested
for unforeseen conditions such as supply chain problems and for tank delivery
during periods when the access road into Sleepy Hollow may be deteriorated.
EXHIBITS
3-A Reiff
Manufacturing bid
3-B Bid Bond