ITEM: |
GENERAL MANAGER’S REPORT |
||||
|
|||||
9. |
UPDATE ON DEVELOPMENT OF
WATER SUPPLY PROJECTS |
||||
|
|||||
Meeting Date: |
October 18, 2021
|
Budgeted: |
N/A |
||
|
|||||
From: |
David J. Stoldt, |
Program/ |
|
||
|
General Manager |
Line Item No.: |
|
||
|
|||||
Prepared By: |
David J. Stoldt |
Cost Estimate: |
|
||
|
|||||
General Counsel Review: N/A |
|||||
Committee Recommendation: N/A |
|||||
CEQA Compliance: This action does not constitute a project as
defined by the California Environmental Quality Act Guidelines Section 15378. |
|||||
DISCUSSION:
ASR: All major construction complete.
Landscape plan expected by end of 2021 calendar year.
Desalination Project (MPWSP): Nothing to report.
Pure Water Monterey Project:
Total PWM water recharged to date:
Approximately 4,500 AF (~ 1.47 billion
gallons delivered).
Source Waters:
Blanco Drain and Reclamation Ditch are
operational. Salinas Stormwater Phase 1A
& 1B facilities are available for use.
Advanced Water Purification Facility: AWPF is fully operational. In early October, the Waste Management
District (WMD) will advertise for construction bids the AWPF-to-Waste Management
District cogeneration power tie-in electrical work. Bids opening December 7th with
award in January-February 2022. WMD cogen power should be in use at the AWPF by
Spring 2023.
Water Conveyance Pipeline &
Blackhorse Reservoir:
The pipeline & reservoir are conveying purified water full-time to
the injection facilities.
Injection Wells Facilities Phase 3: All injection wells in service; nominal
injection rate holding steady at 300 AF per month.
PWM permitting activities:
State Division of Drinking Water and the RWQCB continue to focus on the latest
IW Tracer Study and groundwater modeling results. A site visit by the
regulators, M1W, and MPWMD was conducted October 13, 2021. As part of the ongoing permitting activities,
a follow-up extrinsic tracer study is being initiated in October. M1W hopes to increase RWQCB waste discharge
permit from 3,700 AF to 4,300 AF per calendar year by May/June 2022.
Injection Wells Phase 3: Latest schedule shows delay impacts due to
the Deep Injection Wells (DIW’s) backflush pumps, for example, DIW-3 first
injection is now early February 2022. The procurement delays of the DIW
backflush pumps being supplied by National Pump Company are the result of their
global and national-level material supply chain impacts and labor shortages.
National Pump Company is expediting their Tier 2 and Tier 3 suppliers for
improved delivery dates and are themselves working extended shifts and
weekends. The Contractor will likely request a force majeure (or Act
of God) schedule extension as a result of the DIW backflush pumps being
delivered late. M1W and the on-site construction manager have requested a
Time Impact Analysis from the Contractor and will address the time extension
change order after review. A revised
schedule is attached as Exhibit 9-A.
Expanded Pure Water Monterey
MPWMD and Cal-Am are still in
discussion about how to best move the Water Purchase Agreement (WPA) forward
through the CPUC.
MPWMD has proposed a 1-page
Memorandum of Understanding (MOU) that would indicate the three Parties intent
to sign the WPA when approved by the CPUC.
Such an MOU would allow the public agencies to spend pre-construction
monies. MPWMD should expect to approve
an amendment to the project cost sharing agreement with M1W.
M1W and MPWMD staff are working
directly with City of Seaside staff to obtain permission for the exploratory
DIW borings needed in the October 2021 timeframe to develop the Injection Wells
Phase 4 design at the new eastern well field. The Seaside permit to conduct the
related geotechnical survey has been secured.
The upcoming exploratory borings at the
eastern well field are required to complete the hydrogeologic design of the new
DIW’s. To secure firm water injection capacity and ensure reliable project
yield, a sixth DIW is now recommended, i.e., in addition to the planned DIW-5.
The design team will add DIW-6 to the ongoing Expanded PWM Project final design
and M1W staff will work with the environmental consultant to prepare the
related environmental documentation which will be subject to M1W Board
approval.
Expanded PWM permitting and design
activities for both the AWPF expansion and Injection Wells Facilities Phase 4
are ongoing with construction scheduled to start in early September 2022, and
substantial completion of new facilities by the end of 2023.
M1W and MPWMD staff have also been
meeting with City of Seaside staff to initiate the final property easement
acquisition process for all the PWM injection well field facilities.
EXHIBIT
9-A Executive Level Project Schedule
U:\staff\Boardpacket\2021\20211018\GM
Reports\09\Item-9.docx