ITEM:

ACTION ITEM

 

15.

CONSIDER extension of time for district grant for removal of concrete ford on finch creek located on hastings reserve

 

Meeting Date:

November 15, 2021

Budgeted: 

Yes

 

From:

David J. Stoldt,

Program/

ERD/Fisheries

 

General Manager

Line Item No.:

2-3-9

 

Prepared By:

David J. Stoldt

Cost Estimate:

N/A

 

General Counsel Approval:  N/A

Committee Recommendation:  N/A

CEQA Compliance:  This action does not constitute a project as defined by the California Environmental Quality Act Guidelines Section 15378.

 

SUMMARY: At its March 16, 2020 meeting the District Board approved $100,000 of grant funding for removal of the wet stream crossing (ford) at UC Berkeley’s (UCB) Hastings Natural History Reservation on Finch Creek which had been identified as the 6th worst steelhead barrier in the District’s 2014 Steelhead Barrier Assessment Report, which was funded through a District IRWM grant. Removal of this barrier would allow unrestricted passage to an additional 3.5 miles of quality stream habitat in wet years.  Finch Creek, in upper Carmel Valley, is the primary tributary to Cachagua Creek, and is potentially one of the most productive, highest habitat value creeks downstream of Los Padres Dam. In normal and above water years, much of Finch Creek remains wetted, allowing steelhead to survive the summer and contribute to the overall success of the Carmel River watershed’s steelhead population.

 

UCB has been working with Waterways Consulting and the Resource Conservation District of Monterey County. They have completed 65% plans, the geotechnical investigation and are hard at work applying for CDFW, Army Corp, and CA Water Board permits for the construction phase of the project. They have received preliminary approval from the State Coastal Conservancy, pending board support, to fund the construction costs (~$800k), with the hope to be under construction in summer 2022. 

 

The District agreed to let UCB use any of the grant funds remaining after the design phase toward construction. At this stage there is $9,964.32 in unobligated funds. However, the grant is set to end on December 31, 2021, and UCB has requested an extension to use these remaining funds (see Exhibit 15-A). UCB has asked to extend the grant for 2 more years, until December 31, 2023. UCB is hopeful that this project will be completed next year, but it's possible that delays due to permitting approvals, weather or supplies may push construction out until summer 2023.  

 

RECOMMENDATION:  Authorize the extension of the District’s grant to UCB until December 31, 2023. 

 

EXHIBIT

15-A    Letter from UCB dated October 20, 2021

 

 

 

U:\staff\Boardpacket\2021\20211115\Action Items\15\Item-15.docx