ITEM:

CONSENT CALENDAR

 

7.

CONSIDER Expenditure of Funds to Maintain the access to the Sleepy Hollow Steelhead Rearing Facility

 

Meeting Date:

January 27, 2022

Budgeted: 

Yes

 

From:

David J. Stoldt,

General Manager

Program/

Protect Environmental

Quality

 

 

Line Item No.: 

2-3-1 C Road

Maintenance

 

Prepared By:                  

Larry Hampson

Cost Estimate: 

$9,950

 

General Counsel Review:  N/A

Committee Recommendation:  The Administrative Committee reviewed this item on January 19, 2022 and recommended approval.

CEQA Compliance:  Categorical Exemption, Section 15301, Existing Facilities.

 

SUMMARY:  Staff proposes to hire Valley Grading & Paving, Inc. to carry out road maintenance along the access to the Sleepy Hollow Steelhead Rearing Facility (Facility).  The cost of repairs is estimated to be up to $9,950.  Work would be carried out during Fiscal Year 2021-22.  Due to the remaining effect of the 2020 Carmel fire and subsequent rains, rock and debris washes down onto the access road and runoff continues to degrade the road.  The contractor would be on call to remove debris that blocks the road and to repair areas that are made impassable to District vehicles using the road to access the Facility.

 

RECOMMENDATION:  The Administrative Committee recommends that the Board approve the funds for road maintenance and direct the General Manager to enter into a contract with Valley Grading and Paving, Inc., for a not-to-exceed amount of $9,950.

 

DISCUSSION:  The Sleepy Hollow Steelhead Rearing Facility is accessed from Carmel Valley Road over an approximately one-mile single lane dirt road on Cal-Am property east of Carmel Valley Village.  Although Cal-Am installed approximately $1 million in slope protection in September 2020 along the most unstable portion of the road, the lingering effects of the 2020 Carmel fire in combination with wet conditions continue to result in periodic rock and debris fall along the road that impedes District vehicles.

 

The District and Cal-Am share responsibility under a 1994 lease agreement for road maintenance.  MPWMD requires access to the site on a daily basis when steelhead are being raised and on a frequent basis at other times of the year.  During FY 2021-22, MPWMD staff anticipate a need for nearly daily trips to the facility for operation and maintenance tasks.  However, Cal-Am’s road maintenance contractor is not always available to respond to requests for maintenance in a timely manner.   Having an agreement in place for a local contractor that can respond  within three days of a request by staff for service would reduce the risk to the facility from a prolonged delay in access.

District staff requested quotes from local grading and paving contractors located near Carmel Valley, including Scardina Builders, Inc., Coastal Paving and Excavating, Inc., Cordrey Construction, Inc., David Casarez Excavating, Inc., and Valley Grading and Paving, Inc.  Staff received one quote from Valley Grading & Paving (Exhibit 7-A).  Work under an agreement would be for time and materials to remove road blockages and make any necessary repairs to make the access road passable.

 

IMPACTS ON STAFF AND RESOURCES:  Funds for maintenance work were included in the FY 2021-2022 budget Program line item 2-3-1 C. Road Maintenance.

 

EXHIBIT

7-A      Valley Grading and Paving, Inc. Rate Sheet

 

 

U:\staff\Boardpacket\2022\20220127\Consent Calendar\07\Item-7.docx