ITEM:

CONSENT CALENDAR

 

4.

CONSIDER INCREASE OF FUNDS FOR CONSULTANT SERVICES FOR SLEEPY HOLLOW STEELHEAD REARING FACILITY MONITORING AND CONTROL SYSTEMS

 

Meeting Date:

April 18, 2022

Budgeted: 

Yes

 

From:

David J. Stoldt,

General Manager

Program/

Protect Environmental

Quality

 

 

Line Item No.: 

2-3-1-N

 

Prepared By:                  

Thomas Christensen

Cost Estimate: 

$ 8,060

 

General Counsel Review:  N/A

Committee Recommendation:  The Administrative Committee reviewed this item on April 11, 2022 and recommended approval.

CEQA Compliance:  Exempt under §15262.

 

SUMMARY:  This item is to authorize an increase of $8,060 for the agreement with Telemetrix (TMX) to provide up to 100 hours of consultant service to assist staff with operations and troubleshooting, maintain a web service to provide remote access to on site controls, provide telecommunications, provide 24-hour alarm monitoring, and to provide operational monitoring data at the Sleepy Hollow Steelhead Rearing Facility (Facility) in Carmel Valley.

 

RECOMMENDATION:  The Administrative Committee recommends that the Board authorize the General Manager to amend an agreement with Telemetrix, Inc. for consultant services in an amount not-to-exceed $8,060.  If this item is approved, the not-to-exceed amount would be $26,000.

 

DISCUSSION:  At their July 19, 2021 meeting, the Board authorized entering into an agreement with Telemetrix (TMX) to provide technical support for a one-year period for the Programmable Logic Controller (PLC) that monitors and controls most functions of the Facility.  At the time TMX made a proposal for services, the District requirement for consultant liability insurance for this Facility was set at a minimum of $2 million.  Subsequently, based on District Counsel recommendation, the District determined that due to the value of improvements at the Facility, the proposed work would require a $5 million policy.  The annual cost to the consultant for obtaining the policy was just over $9,000, which significantly reduced the budget for providing technical support and web services.

 

IMPACTS ON STAFF AND RESOURCES:  The mid-year budget adjustment adopted on February 24, 2022 includes $26,000 in funds for this work under Sleepy Hollow Operations Budget Program line item 2-3-1-N Operations Consultant with Web Support.  The work would be performed under the direction of District staff involved with Sleepy Hollow Facility operations. 

 

EXHIBIT

None

 

U:\staff\Boardpacket\2022\20220418\Consent Calendar\04\Item-4.docx