ITEM: |
CONSENT
CALENDAR |
||||
|
|||||
9. |
CONSIDER CONTRACTING WITH MARTIN FEENEY TO INSTALL A
PERMANENT DOWN HOLE SAMPLING PUMP IN PARALTA TEST TO COMPLY WITH REGIONAL
WATER QUALITY CONTROL BOARD GENERAL PERMIT 2012-0010 |
||||
|
|||||
Meeting Date: |
July 18, 2022 |
Budgeted: |
Yes |
||
|
|||||
From: |
David J. Stoldt |
Program/ |
Project Operations |
||
|
General Manager |
Line Item: |
1-2-1-B.7 |
||
|
|||||
Prepared By: |
Jonathan Lear |
Cost Estimate: |
$30,000 |
||
|
|||||
General
Counsel Review: N/A |
|||||
Committee
Recommendation: The Finance and Administration Committee reviewed
this item on July 11, 2022 and recommended approval. |
|||||
CEQA
Compliance: This action does not constitute a project as
defined by the California Environmental Quality Act Guidelines section 15378. |
|||||
SUMMARY: In February 2022, the District was
informed that the Carmel River Aquifer Storage and Recovery (ASR) Program was
successfully enrolled into the General Permit for the injection of Drinking
Water. With the enrolment into the new
permit, there were some changes made to the Monitoring and Reporting plan by
the Regional Water Quality Control Board (RWQCB). The new Monitoring and Reporting program
requires monitoring of what the new permit refers to as Aquifer Monitoring
Wells, which are wells that are offsite from the sites containing injection
wells. According to the regulations, one
of the Aquifer Monitoring Wells should be under the influence of water injected
by the Project and one of the Aquifer Monitoring Wells should be outside of the
influence of the project and monitor the background Aquifer water quality. Paralta Test Well was identified by the RWQCB
as the Aquifer Monitoring Well under influence of injected water. Paralta Test is located approximately 30 feet
north-east of Paralta Production in the Paralta Cal-Am well yard.
Currently there is not a
dedicated pump installed in Paralta Test, so collection of the quarterly water
quality sample is not possible. District
staff has worked with Cal-Am and RWQCB Staff to identify a sampling method that
is compliant with the new permit.
Because Paralta Test is located so close to the Paralta Production well,
Cal-Am staff has requested that all construction required to retrofit Paralta
Test with a down hold pump be completed sub-grade so that the area in the pump
yard can still be used to stage equipment when Paralta Production requires
repair work or rehabilitation. The
District currently has a contract with Martin Feeney and uses his services when
well reconfiguration/repair work is required on wells within the ASR monitoring
network. Mr. Feeney worked with a number
of well drillers to come up with a plan to install a pump sub-grade that would
satisfy both the RWQCB and Cal-Am. The
scope and estimate are included as Exhibit 9-A. This work is included in the Adopted FY
2022-2023 budget and with a 5% contingency, the work should not exceed
$30,000. This work is related to ASR
compliance and is covered under the Amended and Restated ASR Agreement, so all
cost related to this project will be reimbursed to the District through this
Agreement.
RECOMMENDATION: The Finance and Administration
Committee recommends that the Board of Directors authorize the
District Staff to enter into and contract amendment with Martin Feeney to
complete the installation of a down hold sampling pump in Paralta Test Well in
an amount not to exceed $30,000.
BACKGROUND: Over 2020 and 2021,
District Staff worked with the MPWMD Board and the RWQCOB staff to move the
Carmel River ASR Program from the previous permit regime to the RWQCB preferred
permit regime. In February 2022,
District Staff received notification that the application to enroll the Carmel
River ASR Program into the General Permit 2012-0010 for the injection of
drinking water was accepted by the RWQCB in the January 2022 Board Meeting. A letter received February 7, 2022 outlines
the requirements of the new Monitoring and Reporting program and is included as
Exhibit 9-B.
EXHIBITS:
9-A Bid submitted to the
District for Martin Feeney to equip Paralta Test with a dedicated down hole
sampling pump
9-B Letter received from the RWQCB outlining the new
Monitoring and Reporting requirement related to the District’s Carmel River ASR
Project operation
U:\staff\Boardpacket\2022\20220718\Consent
Calendar\09\Item-9.docx