ITEM: |
CONSENT CALENDAR |
||||
|
|||||
4. |
Consider Approval of Funds and a Contract for the Sleepy Hollow
Steelhead Rearing Facility rearing channel rehabilitation Project |
||||
|
|||||
Meeting Date: |
November
14, 2022 |
Budgeted: |
Yes-partial |
||
|
|||||
From: |
David J. Stoldt, General Manager |
Program/ |
Protect
Environmental Quality
|
||
|
|
Line Item
No.: |
2-3-1-L |
||
|
|||||
Prepared By: |
Larry
Hampson |
Cost
Estimate: |
$739,500 |
||
|
|||||
General
Counsel Review: N/A |
|||||
Committee
Recommendation: The Finance and Administration
Committee reviewed this item on November 7, 2022, and recommended approval. |
|||||
CEQA Compliance: Exempt under §15301 Existing Facilities. |
|||||
SUMMARY: Staff proposes to contract for maintenance
work for the rearing channel at the District’s Sleepy Hollow Steelhead Rearing
Facility (Facility). Bids for the
project were received on October 28, 2022, from three General Contractors as
shown in the attached Exhibit 4-A. Bids were responsive to all requirements in
the Notice Inviting Bids. The low bidder
was Tyman Construction at $642,998. The
next highest bidders were Monterey Peninsula Engineering at $934,500 and Granite
Rock Company at $1,169,800. The engineer’s estimate for the project was $650,000
to $750,000.
The FY 2022-23 budget adopted
on June 20, 2022, included $750,000 for rehabilitation projects at Sleepy
Hollow. This line item includes funds previously authorized by the Board to
close out the contract for installation of quarantine tanks ($12,000) and to
carry out planning and engineering ($33,000). Staff requests the Board
authorize $739,500 for the rearing channel work, which would require a mid-year
budget adjustment of an additional $34,500 in the Sleepy Hollow Rearing Channel
line item for a total line item budget of $784,500..
RECOMMENDATION: The Finance and Administration Committee recommends
that the Board authorize the General Manager to enter into a contract with Tyman
Construction for the Sleepy Hollow Steelhead Rearing Facility Rearing Channel
Rehabilitation Project in an amount not-to-exceed $643,000. Due to the unknowns
associated with this work, staff is requesting approval of a contingency amount
of $96,500 (15% of the contract amount) for unforeseen circumstances and
engineering consultant services for a total project cost of $739,500.
DISCUSSION: The Facility was initially constructed in 1996
and was intended to be operated on a temporary basis to mitigate for impacts to
Carmel River steelhead from water diversions until a replacement water supply
was constructed. It has been modified on several occasions to address issues with
operations and to add components necessary to successfully rear steelhead
rescued from the Carmel River.
The Hypalon liner along 800 feet of the
channel has reached the end of its design life and leaks in several places,
despite being frequently patched (where possible). This threatens the integrity
of the rearing channel walls and liner that could collapse from sinkholes
developing under the channel. In
addition, the drain line was not designed for staged removal of steelhead It is
undersized and difficult to operate when removing steelhead as the facility is
shut down and the fish are returned to the river.
Due to the work required to excavate and
replace the drain and to replace the liner, existing infrastructure along the
channel needs to be removed and replaced (air and water lines); however, the
PVC air and water lines have been constantly exposed to UV and the elements for
26 years and have started cracking in places and have required repairs. These
lines are also close to end of life in this facility and would likely need to
be replaced in the near future.
Bid advertisements were placed three times
with the Monterey County Weekly; the project was placed on ebidboard.com (a comprehensive
cross-agency database of California public works construction projects and
documents); and staff reached out via email to several contractors. Six contractors attended the site walk
through and three bids for the project were received on October 28, as shown in
Exhibit 4-A. Bids were responsive to all requirements in
the Notice Inviting Bids. The low bidder,
Tyman Construction, was $642,998 and has
5 years of experience in contracting, including projects with local private
entities, the Cities of Santa Cruz and Monterey, the Pacific Gas & Electric Company, and
Napa County Public Works. The Engineering Manager at Napa County characterized
Tyman Construction as being able to carry out quality work under extreme time
pressures and working extended hours to meet deadlines. When asked about
experience installing a liner similar to the EPDM required liner for the
Facility, Tyman Construction responded that the company has installed pond
liners in the past (the methods for installing liners, whether made of PVC or
EPDM, are similar).
The work involves removal of about and
replacement of 700 feet of an underground six-inch drain line, removal and
disposal of the existing 800-foot long Hypalon liner, removal and
reinstallation of a cobble layer in the riffle sections, installation of a
concrete bottom with a new EPDM liner, and approximately 2,400 feet of air,
fresh water, and saltwater lines. The work site has limited as-built
information; is in a remote area; access is subject to rockfall and debris
slides; and conditions under the rearing channel are not well characterized. For
these reasons, staff is asking for a 15% contingency for unforeseen conditions
and for additional engineering consulting work.
CEQA:
The
California Environmental Quality Act Section 15301 exempts maintenance of
existing facilities, including those under section (i).
“ Maintenance of fish screens, fish
ladders, wildlife habitat areas, artificial wildlife waterway devices, stream
flows, springs and waterholes, and stream channels (clearing of debris) to
protect fish and wildlife resources; ”
IMPACTS ON STAFF AND RESOURCES: Funds for this work are budgeted under Sleepy
Hollow Operations Budget Program line item 2-3-1-L Design/Construct Rearing
Channel and Quarantine Tank Improvements.
The FY 2022-23 budget adopted on June 20, 2022, included $750,000 for completing
the installation of quarantine tanks, planning and engineering, and rearing
channel work. If this item is approved, the total authorized funds for the program
line item would be $784,500, an increase of $34,500 over the budgeted amount. A
mid-year budget adjustment would be made to account for the budget increase.
The work would be performed under the
direction of the Project Engineer.
EXHIBIT
4-A Bid Summary and Forms
U:\staff\Boardpacket\2022\20221114\Consent
Calendar\04\Item-4.docx