ITEM:

INFORMATIONAL ITEM/STAFF REPORT

 

15.

STATUS REPORT ON MEASURE J/RULE 19.8 PHASE III SPENDING

 

Meeting Date:

April 17, 2023

Budgeted: 

N/A

 

From:

David J. Stoldt,

Program/

N/A

 

General Manager

Line Item No.:

 

Prepared By:

Suresh Prasad

Cost Estimate:

N/A

 

General Counsel Review:  N/A

Committee Recommendation:  N/A

CEQA Compliance:  This action does not constitute a project as defined by the California Environmental Quality Act Guidelines Section 15378.

 

SUMMARY: Attached for review as Exhibit 15-A, monthly status report on Measure J/Rule 19.8 Phase II spending for the period February 2023.  This status report is provided for information only, no action is required.  

 

EXHIBIT

15-A    Status on Measure J/Rule 19.8 Phase II Spending

 

 

 

 

U:\staff\Boardpacket\2023\20230417\Informational Items\15\Item-15.docx