ITEM: |
INFORMATIONAL
ITEM/STAFF REPORT |
||||
|
|||||
21. |
MONTHLY WATER SUPPLY AND |
||||
|
|||||
Meeting Date: |
January 22, 2024 |
Budgeted: |
N/A |
||
|
|||||
From: |
David J. Stoldt, |
Program/ |
N/A |
||
|
General Manager |
Line
Item No.: |
|||
|
|
|
|||
Prepared By: |
Jonathan Lear |
Cost Estimate: |
N/A |
||
|
|||||
General Counsel Review: N/A |
|||||
Committee Recommendation: N/A |
|||||
CEQA
Compliance: Exempt from environmental
review per SWRCB Order Nos. 95-10 and 2016-0016, and the Seaside Basin Groundwater
Basin adjudication decision, as amended and Section 15268 of the California
Environmental Quality Act (CEQA) Guidelines, as a ministerial project; Exempt
from Section 15307, Actions by Regulatory Agencies for Protection of Natural
Resources. |
|||||
Exhibit 21-A shows the water
supply status for the Monterey Peninsula Water Resources System (MPWRS) as of January 1, 2024. This system includes the surface water
resources in the
Water Supply Status: Rainfall
through December 2023 totaled 3.29 inches and brings
the cumulative rainfall total for WY 2024 to 5.01 inches, which is 74%
of the long-term average through December. Estimated unimpaired runoff through December totaled 576 acre-feet (AF)
and brings the cumulative runoff total for WY 2024 to 1,555 AF, which is 23% of the long-term average through December. Usable storage for the MRWPRS was 29,970 acre-feet, which is 104% of average through December, and equates to 90% percent of system capacity.
Production Compliance: Under State Water Resources Control Board (SWRCB) Cease and Desist Order No. 2016-0016 (CDO), California American Water (Cal-Am) is allowed to produce no more than 3,376 AF of water from the Carmel River in WY 2024. Through December, using the CDO accounting method, Cal-Am has produced 636 AF from the Carmel River (excluding 0 AF of Table 13 and 18 AF of Mal Paso.) In addition, under the Seaside Basin Decision, Cal-Am is allowed to produce 1,474 AF of water from the Coastal Subareas and 0 AF from the Laguna Seca Subarea of the Seaside Basin in WY 2024. Through December, Cal-Am has produced 556 AF from the Seaside Groundwater Basin. Through December, 0 AF of Carmel River Basin groundwater have been diverted for Seaside Basin injection; 0 AF have been recovered for customer use, 0 AF have been diverted under Table 13 water rights, and 952 AF of Pure Water Monterey recovered. Cal-Am has produced 2,199 AF for customer use from all sources through December. Exhibit 21-B shows production by source. Some of the values in this report may be revised in the future as Cal-Am finalizes their production values and monitoring data.
EXHIBITS
21-A Water Supply Status: January
1, 2024
21-B Monthly Cal-Am production by source: WY 2024
U:\staff\Boardpacket\2024\01222024\Informational
Items\21\Item-21.docx