ITEM: |
INFORMATIONAL ITEM/STAFF REPORT |
||||
|
|||||
19. |
MONTHLY WATER SUPPLY AND CALIFORNIA AMERICAN WATER
PRODUCTION REPORT |
||||
|
|||||
Meeting Date: |
April 15, 2024 |
Budgeted: |
N/A |
||
|
|||||
From: |
David J. Stoldt, |
Program/ |
N/A |
||
|
General Manager |
Line Item No.: |
|||
|
|
|
|||
Prepared By: |
Jonathan Lear |
Cost Estimate: |
N/A |
||
|
|||||
General Counsel
Review: N/A |
|||||
Committee
Recommendation: N/A |
|||||
CEQA
Compliance: Exempt from environmental
review per SWRCB Order Nos. 95-10 and 2016-0016, and the Seaside Basin
Groundwater Basin adjudication decision, as amended and Section 15268 of the
California Environmental Quality Act (CEQA) Guidelines, as a ministerial
project; Exempt from Section 15307, Actions by Regulatory Agencies for
Protection of Natural Resources. |
|||||
Exhibit 19-A shows the water
supply status for the Monterey Peninsula Water Resources System (MPWRS) as of April 1, 2024. This system includes the surface water
resources in the
WATER SUPPLY STATUS:
Rainfall through March 2024
totaled 4.94 inches and
brings the cumulative rainfall total for WY 2024 to 20.88 inches, which is 111%
of the long-term average through March. Estimated unimpaired runoff through March totaled 12,350 acre-feet (AF)
and brings the cumulative runoff total for WY 2024 to 38,575 AF, which is 72% of the long-term average through March.
Usable storage for the MRWPRS was 29,850
acre-feet, which is 94% of
average through March, and equates
to 90% percent of system capacity.
PRODUCTION COMPLIANCE: Under State Water Resources Control Board (SWRCB) Cease and Desist Order No. 2016-0016 (CDO), California American Water (Cal-Am) is allowed to produce no more than 3,376 AF of water from the Carmel River in WY 2024. Through March, using the CDO accounting method, Cal-Am has produced 1,109 AF from the Carmel River (excluding 218 AF of Table 13 and 35 AF of Mal Paso.) In addition, under the Seaside Basin Decision, Cal-Am is allowed to produce 1,474 AF of water from the Coastal Subareas and 0 AF from the Laguna Seca Subarea of the Seaside Basin in WY 2024. Through March, Cal-Am has produced 671 AF from the Seaside Groundwater Basin. Through March, 798 AF of Carmel River Basin groundwater have been diverted for Seaside Basin injection; 0 AF have been recovered for customer use, 117 AF have been diverted under Table 13 water rights, and 1,926 AF of Pure Water Monterey recovered. Cal-Am has produced 3,995 AF for customer use from all sources through March. Exhibit 19-B shows production by source. Some of the values in this report may be revised in the future as Cal-Am finalizes their production values and monitoring data.
EXHIBITS
19-A Water Supply Status: April
1, 2024
19-B Monthly Cal-Am production by source: WY 2024
U:\staff\Boardpacket\2024\04152024\Informational
Items\19\Item-19.docx