EXHIBIT 3-A

                                                                             

MONTEREY PENINSULA WATER MANAGEMENT DISTRICT

 

                                                              MEMORANDUM

 

 

DATE:            January 25, 2010

 

TO:                 Darby Fuerst, General Manager

 

FROM:           Andrew M. Bell, District Engineer

 

SUBJECT:     Summary of MPWMD Investigations of Desalination Projects to Serve the Monterey Peninsula Area

 

 

SUMMARY

Starting in 1990, MPWMD has investigated a number of desalination projects, with intake facility sites ranging from the Moss Landing Harbor to the north to Carmel River Beach to the south.  This memorandum summarizes the sites that have been considered, and the studies conducted and documents prepared to evaluate options for serving the Monterey Peninsula area from desalination projects.

 

DISCUSSION

In 1990, due to slow progress of the New Los Padres Dam and Reservoir Project, the District undertook a review of non-dam alternatives.  Based on review of 97 water supply options, seawater desalination was determined to be the most promising alternative.  The first study of desalination potential was conducted by Boyle Engineering.  Boyle’s initial report, issued July 17, 1991 and titled “MPWMD Desalination Feasibility Study,” reviewed seven sites from Moss Landing on the north to Carmel River.  See Attachment 1 for a list and locations of these sites.  The resulting recommendations of this study were to conduct more detailed evaluations of two sites, the Monterey Regional Water Pollution Control Agency (MRWPCA) site and the Moss Landing site.

 

Geotechnical studies of seawater or “saline groundwater” intake wells at three locations were conducted by District consultant Staal, Gardner & Dunne.  These three locations are the Marina County Water District (now Marina Coast Water District) Wastewater Treatment Facility in Marina (February 1991 report), the Monterey Sand Company site in Marina (February 1992 report), and Sand City (February 1992 report).

 

Although the MRWPCA and Moss Landing sites were recommended by Boyle, these further investigations resulted in selecting Sand City as an additional promising alternative.  The desired capacity of what was termed a “near-term project,” which represented a project that could be completed while the dam and reservoir project proceeded, was determined to be a 3 million-gallon-per-day (MGD) plant operated seasonally to produce 2,000 acre-feet per year (AFY).   In March 1992, District consultant James M. Montgomery Consulting Engineers issued a report titled “MPWMD Desalination Preliminary Design, Final Report.”  This report provides preliminary design and estimates of capital costs for a 3 MGD project at these three sites.

 

The Sand City site was ultimately selected as being the most promising, and a Draft EIR was issued on a 3 MGD project producing 2,000 AFY in April 1992 (Draft EIR, Near-Term Desalination Project, by EIP Associates).  A more extensive geotechnical feasibility study was then conducted on intake facilities at the Sand City site, and the report on this study by Staal Gardner & Dunne was issued in September 1992.  The Final EIR on the Sand City project was issued in December 1992.  The District issued a call for bids for final design, construction, and operation of the project pending final approval of the project and its funding by a vote of Peninsula residents.  Unfortunately the vote, held in June 1993, failed.

 

In 2002, the Board directed staff to investigate the feasibility of a desalination project located within the District boundary that could produce up to 8,400 AFY.  The District retained engineering consulting firm Camp Dresser & McKee and environmental consulting firm Jones & Stokes Associates (JSA) to conduct project studies.  Conclusion of the engineering studies for a 7.5 MGD project producing 8,400 AFY are presented in the March 2003 CDM report titled “Monterey Peninsula Water Supply Project Alternatives, Final Phase 1 Technical Memorandum.”  A report titled “Board Review Draft EIR” prepared for the project by JSA was issued in December 2003.  This document reviewed a project with intake facilities located in Sand City just north of the Monterey Beach Hotel, and three alternative plant sites.  The locations of these facilities are shown in Attachment 2.  The Board elected not to proceed with this project.

 

In January 2008, the Board directed staff to re-initiate the evaluation of a desalination project in Sand City and former Fort Ord.  In the meantime, the City of Sand City had gained approval of its brackish water desalination project with intake facilities located in the area where intake facilities were proposed for the 8,400 AFY project.  The updated evaluation of a project in this area, presented in an August 2008 report by JSA and CDM titled “MPWMD 95-10 Project Constraints Analysis,” concluded that the Sand City area was no longer available, but that there is the possibility of a project with intake facilities located in the southern portion of former Fort Ord.  A subsequent study of the feasibility of a project in this area was conducted by Martin B. Feeney, Consulting Hydrogeologist.  Findings of Mr. Feeney’s studies are in his November 2009 report titled “MPWMD 95-10 Desalination Project Hydrostratigraphic Investigation” and were provided to the Board for the December 14, 2009 meeting.  The report concluded, based on review of logs of existing wells and results of a number of soil borings drilled in what is now the Fort Ord Dunes State Park, that a project with intake facilities constructed in this area would be infeasible due to the absence of a continuous low-permeability layer that would prevent the project from impacting the Seaside Groundwater Basin.  Mr. Feeney recommended that the District “terminate further investigation of this project at this juncture.”

 

CONCLUSION

Since the early 1990s, the District has investigated a large number of desalination projects and sites in locations ranging from Moss Landing on the north to Carmel River Beach on the south.  No project site that would be both technically and economically feasible appears to exist within the MPWMD boundary.  Desalination projects currently under review that could serve the District as part of California American Water’s (CAW) Coastal Water Project would have intake facilities located north of the District boundary, just north of Reservation Road (Regional Project and North Marina Project) and at Moss Landing (the site initially proposed by CAW as part of the Coastal Water Project).

 

 

Attachment 1     page II-6 and Figure 1 – Desalination Sites Considered, from Boyle Engineering July 17, 1997 report, MPWMD Desalination Feasibility Study

Attachment 2     Figure ES-1 – Location of HDD Wells and Collection Pipelines, from Jones & Stokes, December 2003 report, Board Review Draft, MPWMD Water Supply Project, Draft EIR

 

 

 

 

U:\staff\word\committees\AdHoc\WaterSupplyPlan\2010\20100202\03\item3_exh3a.doc