ADMINISTRATIVE
COMMITTEE |
||||
|
||||
6. |
CONSIDER EXPENDITURE OF FUNDS TO PREPARE REVISED VERSION OF JUNE 26,
2006 REPORT BY BOOKMAN-EDMONSTON/GEI CONSULTANTS, “SEAWATER DESALINATION
PROJECTS EVALUATION” INCLUDING SEAWATER CONVERSION VESSEL ALTERNATIVE |
|||
|
||||
Meeting Date: |
February 12,
2007
|
Budgeted: |
Yes, provided
2006-07 Mid-Year Budget Adjustment is approved |
|
|
||||
From: |
David A.
Berger, |
Program/ |
Contingency |
|
|
General
Manager |
Line Item No.: |
Acct. 8900 |
|
|
||||
Prepared
By: |
Andrew
Bell |
Cost Estimate: |
$30,000 |
|
|
|
|
|
|
|
||||
General Counsel Approval:
N/A |
||||
Committee
Recommendation: The Administrative Committee reviewed
this item on February 12, 2007 and recommended ________________________. |
||||
CEQA Compliance: N/A |
||||
SUMMARY: The Board will consider amending an existing
contract with Bookman-Edmonston/GEI Consultants (B-E/GEI) for additional
services to revise their June 26, 2006 report evaluating three seawater
desalination project alternatives. The not-to-exceed
cost in the contract with B-E/GEI would be increased by $27,200 from $55,000 to
$82,700. The report revisions would be
in response to questions and comments on the report by the Board and public at
the June 29, 2006 Workshop and subsequent comments submitted by project
sponsors California American Water (Cal-Am) and Pajaro/Sunny Mesa Community
Services District. In addition, at the
October 16, 2006 meeting, the Board asked staff to include the scope and costs
of adding an analysis of a seawater conversion vessel project, the offshore
seawater desalination concept proposed by the Water Standard Company and
PBS&J, to the B-E/GEI report update.
The scope and costs for the additional work are presented in Exhibit 6-A. A
summary of comments by the Board, the public, and project proponents, including
copies of written comments received after the workshop, was provided to the
Board in a memorandum from the District Engineer dated September 12, 2006 (Exhibit 6-B).
RECOMMENDATION: Staff recommends that the Board authorize the General Manager to amend the existing contract with B-E/GEI to revise the June 26, 2006 report titled “Seawater Desalination Projects Evaluation” in accordance with the scope of work presented in Exhibit 6-A at a cost not to exceed $30,000, which includes a $2,800 contingency amount.
BACKGROUND AND DISCUSSION: In 2004 and 2005, all information for the MPWMD comparative matrix of water supply alternatives was submitted by the project sponsors with no independent analysis by MPWMD to assess the completeness or accuracy of the information. At its February 23, 2006 meeting, the District Board authorized a contract with B-E/GEI to perform an independent review of the three desalination projects then included in the matrix. The projects are as follows:
1. Coastal Water Project, sponsored by Cal-Am.
2. North Monterey County Desalination Project, sponsored by the Pajaro/Sunny Mesa Community Services District.
3. 7.5 million-gallon-per-day project in
At the June 29, 2006 Board Special Workshop, B-E/GEI presented their June 26, 2006 report titled “Seawater Desalination Projects Evaluation.” Copies of the full report are available at the District office, and presentation materials are provided at the following website location:
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2006/20060629/0629agenda.htm.
At
the June 2006 workshop, B-E/GEI representatives responded to a number of
questions and comments by the Board and public. At the end of the workshop, the Board asked
for the cost for additional work by B-E/GEI to revise the final report by
including responses to comments and questions during the workshop.
At its July 17, 2006 meeting, the Board was advised that $15,000 would
be needed to respond to comments and revise the report. At that meeting, the Board determined that
additional funds should not be expended to revise the report at that time, and
to defer action on amending the B-E/GEI contract until after the September
25, 2006 Board Strategic Planning Workshop. District staff was directed to solicit written comments from Cal-Am and
Pajaro/Sunny Mesa Community Services representatives and to prepare a summary
of oral and written comments. A summary
of comments by the Board, the public, and project proponents, including copies
of written comments received was provided to the Board under separate cover in
a memorandum from the District Engineer dated September 12, 2006. These materials have been provided to B-E/GEI.
At the October 16, 2006 Board meeting, the Board decided to defer
action on amending the B-E/GEI contract until a scope and cost for adding the
seawater conversion vessel concept could be developed. A representative of the project sponsors,
Skip Griffin of PBS&J, an engineering consulting firm, met with B-E/GEI
representatives and provided representative information on the seawater
conversion vessel project. B-E/GEI
reviewed the information provided by Mr. Griffin and determined that a total of
$27,200 would be required to update the June 2006 report to address comments
and questions posed in June 2006 and to add the seawater conversion vessel
project. The scope of work and a
breakdown of costs for these tasks is provided in Exhibit 6-A.
Staff believes it is important to revise and update the report so that
it provides as complete an evaluation as possible of information currently
available for the District and the public.
Comments and questions regarding the report, particularly by Cal-Am and
Pajaro/Sunny Mesa representatives, have resulted in the report being viewed as
inaccurate and incomplete. In addition,
the Board expressed a desire to include the seawater conversion vessel concept
as an additional seawater desalination project in the report. By spending an additional $27,200, the
District will protect the $53,700 investment already made in reviewing and
evaluating the original three projects.
An updated report will also be useful to members of the public and the Community
Advisory Committee in being able to better understand these major water supply
project proposals.
IMPACT TO STAFF/RESOURCES: On February 23, 2006 the Board authorized an expenditure of up to $60,000, including a contingency of $5,000, to contract with B-E/GEI to prepare a comparison of desalination costs and timelines. A contract for an amount not-to-exceed $55,000 was executed with B-E/GEI, and approximately $53,700 was expended to complete the original report. Based on the information provided in Exhibit 6-A, the estimated cost of the additional work to revise the report is $27,200. No funds to revise the report were included in the Fiscal Year 2006-2007 Budget adopted at the June 22, 2006 Board meeting. However, in the proposed Mid-Year 2006-2007 Budget Adjustment (Item 15 in this packet), $30,000 is added for completion of this report. The difference between the estimated cost ($27,200) and the proposed amendment ($30,000) is $2,800, a contingency of approximately 10%, in order to address unanticipated necessary work on the part of the consultant. District Engineer Andrew Bell is the staff person responsible for administering the contract.
EXHIBITS
6-A Work Effort Estimate and Cost Estimate, Bookman-Edmonston/GEI Consultants
6-B September 12, 2006 memorandum from District Engineer Andrew M. Bell to Board of Directors, “Summary of Comments on June 26, 2006 report by Bookman-Edmonston/GEI Consultants, ‘Seawater Desalination Projects Evaluation’”
U:\staff\word\committees\Admin\2007\20070212\06\item6.doc