ADMINISTRATIVE
COMMITTEE |
||||
|
||||
2. |
CONSIDER EXPENDITURE OF
BUDGETED FUNDS TO CONTRACT FOR CONSTRUCTION OF INITIAL APPURTENANT FACILITIES
FOR PHASE 1 ASR PROJECT |
|||
|
||||
Meeting
Date: |
October 4, 2007 |
Budgeted: |
Yes |
|
|
||||
From: |
David A.
Berger, |
Program/ |
Water Supply Projects |
|
|
General
Manager |
Line Item
No.: |
1-2-1 A. Account No. 4-04-7860.04 |
|
|
||||
Prepared
By: |
|
Cost
Estimate: |
$352,000 |
|
|
|
|
|
|
General Counsel Approval: N/A |
||||
Committee Recommendation: The Administrative Committee considered this item on October 4, 2007 and recommended _____________. |
||||
CEQA Compliance: N/A |
||||
SUMMARY: As part of the Phase 1 Aquifer Storage and
Recovery (ASR) Project, Monterey Peninsula Water Management District (District)
consultants and staff have been preparing project plans for construction of
permanent ASR facilities at the District’s Phase 1 ASR site off of
Project plans have been prepared by the District’s consultant, Pueblo Water Resources, Inc. (PWR), and an engineering estimate (i.e., Engineer’s Opinion) for the proposed work is included in the attached letter (Exhibit 2-A). As shown, the total estimate for this segment of work at the Phase 1 site is $320,000.
RECOMMENDATION: To expedite installation of these required facilities in time for conducting injection operations at both wells this upcoming season, District staff recommends that the Board authorize the General Manager to solicit bids and award a contract for the work to the lowest responsive and responsible bidder, as described in Exhibit 2-A. If the lowest responsive bid exceeds the $320,000 engineering estimate by more than 10% (i.e., $320,000 + 10% = $352,000), then award of the bid will be withheld and the project plans may be modified and resolicited. Upon acceptance of a successful bid, the District will include a 10% budget contingency for use in the event that undiscovered conditions or unanticipated work is encountered during construction, as recommended in the PWR letter (Exhibit 2-A). The Administrative Committee considered this matter at its October 4, 2007 meeting and recommended __________.
BACKGROUND: The District has been pursuing the Phase 1 ASR
Project since 2004. During that time, the
District undertook an extensive effort in engineering and planning studies for
the project, culminating in the Board’s adoption of a certified Environmental
Impact Report / Environmental Assessment on August 21, 2006. Subsequently, the U.S. Army granted a
Right-of-Entry to the District for the Phase 1 ASR site expansion on September
19, 2006, and the City of
2-A September 26, 2007 letter from PWR
U:\staff\word\committees\Admin\2007\20071004\02\item2.doc