EXHIBIT 4-A

 

 

 

S C O P E   O F   W O R K   A N D   B U D G E T

 

July 1, 2007 through June 30, 2008

 

 

TASK 1 CVSIM UPDATE/ASSISTANCE ($3,000)    Program 1-1-1

 

TASK 2 CVSIM QUALITY CONTROL ($3,000)             Program 1-1-2

 

 

 

 

             F E E   S C H E D U L E

 

Fees for services for basic contract and options will be calculated on a time and materials basis in accordance with the labor rate shown:

                                        

                                         Principal               $ 110.00 per hour

 

Direct cost (i.e., travel, meals, lodging, telephone, printing, graphic materials) are subject to a 10% administrative charge.   Travel time charges for one way travel only (i.e. at 50 percent of regular fees).

 

 

 

      W O R K   S C H E D U L E

 

 

 

Allocation of effort to individual tasks will be on an "as needed" basis, and in accordance with the specific requests for assistance by Contract Manager.  Work completion date for TASK 1 and TASK 2, is June 30, 2008.

 

 

 

 

U:\staff\word\committees\Admin\2007\20071108\04\item4_exh4a.doc