ADMINISTRATIVE
COMMITTEE |
|||
|
|||
1. |
CONSIDER EXPENDITURE
OF FUNDS TO OBTAIN A CURRENT ESTIMATE OF THE STORAGE CAPACITY OF LOS PADRES
RESERVOIR AND AUTHORIZE THE GENERAL MANAGER TO ENTER INTO CONSULTANT
AGREEMENTS FOR OBTAINING DATA |
||
|
|||
Meeting
Date: |
October
14, 2008 |
Budgeted: Partial |
|
|
|||
From: |
Darby
Fuerst |
Program/ |
|
|
General
Manager |
Line
Item No.: Project 2-2-3 |
|
|
|||
Prepared
By: |
Larry
Hampson |
Cost
Estimate: $35,000 |
|
|
|||
General
Counsel Approval: N/A |
|||
Committee
Recommendation: The Administrative
Committee considered this item on October 14, 2008 and recommended __________________. |
|||
CEQA
Compliance: N/A |
|||
SUMMARY: Staff proposes to obtain and analyze data
concerning the present storage capacity of Los Padres Reservoir, which is
located on the Carmel River approximately 25 miles upstream of the Pacific
Ocean (see Los Padres Reservoir vicinity map, Exhibit 1-A). This proposed project will provide an
estimate of current storage capacity in Los Padres Reservoir and a baseline to quantify
increased sedimentation expected from the Basin Complex Fire.
The original capacity of the reservoir has been
reduced from 3,030 acre-feet (AF) in 1948 to an estimated 1,200 AF at present. After the Basin Complex Fire burned the
watershed above the reservoir in July 2008, the U.S. Forest Service Burned Area
Response Team (BAER) estimated that up to 372 AF of sediment could wash into
the reservoir in the winter of 2008-09 and up to 600 AF of sediment could wash
into the reservoir in the next five to ten years.
Data from reservoir soundings and the topography
of exposed sediments adjacent to the reservoir would be used to update the
present elevation-capacity table. The
reservoir sounding would be conducted by
RECOMMENDATION: District staff recommends that the Board
authorize the General Manager to enter into agreements with the Foundation of
California State University at Monterey Bay to conduct the work
described in Exhibit 1-B at an estimated
cost of $16,500, and with either HJW GeoSpatial, Inc. or California State
University San Jose to conduct the work described in Exhibit 1-C at an estimated
cost of $18,500. The total not-to-exceed cost under both agreements is $35,000.
BACKGROUND: The
most recent survey of Los Padres Reservoir capacity was in 1998, when California
American Water (CAW) estimated that the reservoir held 1,569 AF of water at the
spillway elevation of 1,040 feet above mean sea level (referenced to the 1929
National Geodetic Vertical Datum, or NGVD).
In their recent application to the Public Utilities Commission for a
rate increase, CAW estimates that the reservoir capacity has decreased to 1,200
AF due to sedimentation. Thus, with an initial
reservoir capacity estimated at 3,030 AF in 1948, the long-term average annual
loss of storage capacity is estimated to be approximately 30 AF/year. As a result of the Basin Complex Fire in July
2008, the US Forest Service estimated that up to 372 AF of sediment could wash
into the reservoir in the winter of 2008-09 and up to 600 AF could wash in
during the next five to 10 years. This
represents more than an order of magnitude greater than the long-term
sedimentation rate and, should this event occur, would severely limit the
capability of CAW to release water from storage during the dry season to
maintain aquatic habitat in the Carmel River downstream of Los Padres Dam. An accurate determination of the rate of
sedimentation at this reservoir is necessary in order to effectively implement
a long-term policy for managing the reservoir and river downstream of Los
Padres Dam.
Loss of storage capacity is associated with
intense rainfall events on the steep slopes in the upper
Reservoir sounding and topographic data from
exposed sediments would be used to update the present elevation-capacity table
that is based on a 1998 sounding by CAW.
The cost of the analysis is estimated to be up to $35,000. No funds for this work were included in the
Fiscal Year 2008-09 budget because the fire occurred after the budget was
adopted. Staff proposes to fund the work
with a combination of funds from other budgeted items, contingency fund and a
contribution of 50% of the project cost from CAW.
A reservoir sounding would be conducted by CSUMB
using boat-mounted LiDar (Light Detection and Ranging) equipment that is tied
into a base station using GPS (Global Positioning System). Terrestrial data along the exposed sediments
would be gathered by [HJW GeoSpatial, Inc. using traditional aerial
photogrammetry with GPS survey control or California State University San Jose
using land-based LiDar equipment with GPS survey control]. All data are expected to be accurate to
within 0.5 feet of the true location.
EXHIBITS
1-A Los
Padres Reservoir Vicinity Map
1-B Foundation
of CSUMB Proposal: Los Padres Reservoir
Bathymetry – Fall 2008
1-C HJW GeoSpatial, Inc.
Proposal: Los Padres Mapping
U:\staff\word\committees\Admin\2008\20081014\01\item1.doc