ADMINISTRATIVE
COMMITTEE |
||||
|
||||
3. |
CONSIDER
EXPENDITURE OF FUNDS TO RETAIN CONSULTANT TO PREPARE SUBSEQUENT EIR ON
APPLICATION BY |
|||
|
||||
Meeting
Date: |
April 14, 2009
|
Budgeted: |
No |
|
|
||||
From: |
|
Program: |
WDS Permitting |
|
|
General
Manager |
Line Item No.: |
N/A |
|
|
||||
Prepared
By: |
Henrietta Stern |
Cost
Estimate: |
$180,869 |
|
|
||||
General Counsel Approval:
N/A |
||||
Committee
Recommendation: The Administrative
Committee reviewed this item on April 14, 2009 and recommended ____________________. |
||||
CEQA Compliance: N/A |
||||
SUMMARY: The
Board will consider authorizing staff to retain David J. Powers and Associates
(DJP) for a not-to-exceed amount of $180,869 to prepare a Subsequent
Environmental Impact Report (SEIR) on the water-related impacts of California
American Water (CAW) production of up to 90 acre-feet per year (AFY) to serve
the proposed Monterey Bay Shores Ecoresort (MBSE) in
1. Denied Application #20080915MBS without prejudice;
2. Directed staff to prepare Findings of Denial for consideration on March 26, 2009; and
3. Determined that if the applicant wishes to proceed with the application, MPWMD shall prepare a SEIR focused on water issues prior to consideration.
Regarding Item #2, the Board adopted the Findings of Denial at its March 26, 2009 meeting. The primary issues identified in the Findings include: (a) inadequate documentation of the environmental effects of exercising SNG’s water rights through service by CAW, (b) need to evaluate alternative means of supplying the MBSE parcel from Seaside Basin sources, and (c) the desire for the public to have an opportunity to comment on a recent environmental document for the project.
Regarding Item #3 above, at this writing on April 7, 2009, co-applicant SNG has verbally confirmed that it wishes to move forward on the application and is prepared to fund the preparation of an SEIR. However, the co-applicants have not seen the scope, cost and schedule provided in Exhibit 3-A. Written confirmation from both co-applicants will be required prior to execution of a contract with DJP.
As shown in Exhibit 3-A, the key
components of the scope are to prepare a Draft and Final SEIR in compliance
with the California Environmental Quality Act (CEQA). This includes circulation of a Notice of
Preparation, technical report preparation and review, Draft SEIR preparation,
meetings and public hearings, and response to public comments. A major work
task is evaluation of hydrologic impacts, to be performed by Todd
Engineers. Other impact assessments
relate to: aquatic resources on the
The estimated cost would be $180,869. This includes a base amount of $164,426 plus a 10% contingency of $16,443 given that unforeseen factors could affect the effort needed to address pertinent SEIR issues. The total estimated timeline is 43 weeks from when the consultant receives details of water supply timing and volume from CAW (i.e., water supply description).
RECOMMENDATION: District staff recommends that the Board should:
DJP is recommended as a
sole-source contractor in order to maximize efficiency and minimize delay. The firm prepared the December 2008 Addendum
to the original 1998 EIR on the project, and thus is familiar with the project
and setting. DJP would subcontract with
Todd Engineers for hydrology tasks, as Todd has ongoing experience in the
At its April 14, 2009 meeting, the Administrative Committee recommended that the Board ___________.
BACKGROUND AND DISCUSSION: Public hearings on the CAW/MBSE application were held on November 17, 2008; and on January 29, February 26, and March 26, 2009. Extensive background information is provided in the materials prepared for previous meetings.
The November 17, 2008 materials are available on the District website at:
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2008/20081117/1117agenda.htm (Item 11).
The January 29, 2009 staff report and presentation materials are available on the website at:
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2009/20090129/0129agenda.htm (Item 18).
The February 26, 2009 staff report and presentation materials are available on the website at:
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2009/20090226/0226agenda.htm (Item 15).
The March 26, 2009 staff report and presentation materials are available on the website at:
http://www.mpwmd.dst.ca.us/asd/board/boardpacket/2009/20090326/0326agenda.htm (Item 14).
The Addendum to the Final
Environmental Impact Report,
The
On February 26, 2009, the District Board, as Responsible Agency under the California Environmental Quality Act (CEQA), exercised its independent judgment, and determined that an SEIR is necessary to make an informed decision, consistent with the criteria in CEQA Guidelines Section 15162. The criteria are described in the March 26, 2009 agenda package.
The Findings of Denial adopted on March 26, 2009 explain the
specific rationale for why an SEIR is needed.
Part of the reason for this determination was new information submitted by
CAW at the February 26, 2009 public hearing that raised questions about CAW’s
ability to serve MBSE from
IMPACT TO DISTRICT STAFF/RESOURCES: This expenditure is not included in the FY 2008-2009 budget, but is 100% reimbursable by the co-applicants (CAW and SNG). A rough estimate of costs will also be added for the FY 2009-2010 budget for work anticipated after July 1, 2009, and will be designated as 100% reimbursable. District staff time will be needed to manage the consultant contract and provide guidance and information. Affected personnel most likely will include the Project Manager and Water Resources Division Manager.
EXHIBIT
3-A DWP Scope of Work and Cost Estimate dated April 6, 2009
U:\staff\word\committees\Admin\2009\20090414\03\item3.doc