ADMINISTRATIVE COMMITTEE |
||||
|
||||
1. |
Consider
Expenditure of Budgeted Funds to PURCHASE ELECTRICAL EQUIPMENT AT PHASE 1
AQUIFER STORAGE AND RECOVERY SITE |
|||
|
||||
Meeting Date: |
October 12, 2010 |
Budgeted: |
Yes |
|
|
||||
From: |
|
Program/ |
1-2-1 |
|
|
General Manager |
Line Item No.: |
A. 1 a |
|
|
||||
Prepared By: |
|
Cost Estimate: |
$177,650 |
|
|
||||
General Counsel Review: N/A |
||||
Committee Recommendation: The Administrative Committee reviewed this
item on October 12, 2010 and recommended _____________. |
||||
CEQA Compliance: N/A |
||||
SUMMARY: The
Monterey Peninsula Water Management District (MPWMD or District) has been
developing facilities for full-scale operation of the Phase 1 Aquifer Storage
and Recovery (ASR) Project in cooperation with California American Water
(Cal-Am). The Phase 1 ASR site, also
known as the Santa Margarita ASR site, is located near
Component
Description Estimated
Cost
1.
meter
and main switchboard $ 54,500
2.
variable
frequency drive with transfer switch $ 91,000
3.
motor
control center gear $ 16,000
Total $161,500
Separate bids have been requested for
each component as manufacturers may not be able to supply all three
components. The estimated cost for the
three components above is $161,500. With
a 10% contingency ($16,150), the total estimate is $177,650.
RECOMMENDATION:
District staff recommends authorization to award contracts for bids for
the permanent electrical control equipment listed above for use in the Santa
Margarita Phase 1 ASR facility building, for a not-to-exceed total estimated
cost of $177,650. The requested funding
authorization includes a 10% contingency amount over the estimated cost, in the
event that actual costs differ from the component estimates. If approved, staff will proceed with
processing contract awards for qualified bids to the successful electrical
equipment manufacturers.
BACKGROUND: The
Santa Margarita Phase 1 ASR site is designed as a dual-well injection and
recovery facility. The facility building
that is currently under construction will house all the necessary chemical and
electrical control equipment needed for recovery of injected water from the
onsite ASR wells. The MPWMD and Cal-Am
have coordinated on the design of this building in order to accommodate the
additional equipment needs for ASR expansion to other sites within the
The electrical equipment components described
in this item are planned to be purchased and installed as soon as possible so
that the ASR wells will be able to utilize this permanent equipment during the
upcoming WY 2011 injection season. The
installation of this equipment will be done by separate contractor bid award. The timing for purchase and installation of
this equipment is critical as it is a necessary prerequisite before Pacific Gas
& Electric (PG&E) will authorize installation of the new upgraded
electrical transformer to be located at the new facility building. The PG&E work is currently scheduled to
take place in January 2011, but this schedule may have to change as it is
staff’s current understanding that some of the electrical equipment may not be
manufactured in time to meet this schedule.
This schedule will be confirmed once all bids are awarded and the
equipment installation can be coordinated with PG&E’s transformer
installation schedule.
None
U:\staff\word\committees\Admin\2010\20101012\01\item1.doc