ADIMINSTRATIVE COMMITTEE |
||||
|
||||
1. |
AUTHORIZE
Expenditure of Budgeted Funds FOR site restoration at |
|||
|
||||
Meeting Date: |
December 6, 2010 |
Budgeted: |
Yes |
|
|
||||
From: |
Darby Fuerst, |
Program/ |
1-2-1 |
|
|
General Manager |
Line Item No.: |
B. 1. a. |
|
|
||||
Prepared By: |
|
Cost Estimate: |
$3,245 ( |
|
|
||||
General Counsel Review: N/A |
||||
Committee Recommendation: The Administrative Committee reviewed this
item on December 6, 2010 and recommended _______________. |
||||
CEQA Compliance: N/A |
||||
SUMMARY: The
Monterey Peninsula Water Management District (MPWMD or District) Board will
consider approval of budgeted funds to complete site restoration of the
temporary discharge area that was utilized during development and production
testing of the Seaside Middle School ASR Test well during 2010. The work will include removal and disposal of
temporary piping used during the testing, removal of gabion rock used for
erosion protection, and minor grading to restore the site to its pre-existing
condition. This work will be undertaken
for an estimated amount of $2,950. With
a 10% contingency, the total not-to-exceed cost will be $3,245.
RECOMMENDATION:
District staff recommends authorization of budgeted funds not-to-exceed
$3,245 to complete restoration of the temporary discharge area at the Seaside
Middle School ASR Test well site. If
approved, staff will proceed with securing contractor assistance to complete
this task.
BACKGROUND: The
Seaside Middle School ASR Test well was constructed in Summer 2010; development
and production testing of the well were completed in October 2010. During well development and production
testing, discharge water was directed to a temporary disposal area in the
southwestern portion of the school parcel.
Now that this work has been completed, the temporary disposal site needs
to be restored to its pre-existing condition.
MPWMD received the cost estimate for this work from the contractor
(Monterey Peninsula Engineering) that performed the initial installation in
Summer 2010. Through recent discussion
with Monterey Peninsula Unified School District staff, it was determined that
this location will not be utilized as a future temporary discharge disposal
area, in favor of a more isolated alternate location in the northwestern
portion of the school parcel. As such, any
future use of a temporary discharge disposal area (such as with the drilling of
a second ASR well at the site) will require installation of a separate
temporary pipeline and erosion control at the alternate discharge location on
the school parcel.
None
U:\staff\word\committees\Admin\2010\20101206\01\item1.doc