ADMINISTRATIVE
COMMITTEE |
||||
|
||||
1. |
AUTHORIZE
EXPENDITURE OF REIMBURSABLE FUNDS OBTAINED FROM THE CALIFORNIA DEPARTMENT OF
FISH AND GAME TO CONTRACT WITH LIST ENGINEERING TO COMPLETE FINAL DESIGN AND
DENISE DUFFY & ASSOCIATES TO COMPLETE ENVIRONMENTAL REVIEW AND PERMITTING
FOR THE SLEEPY HOLLOW STEELHEAD REARING FACILITY (SHSRF) SEDIMENT CONTROL AND
INTAKE RETROFIT |
|||
|
||||
Meeting
Date: |
September
12, 2011 |
Budgeted: |
Yes |
|
|
||||
From: |
Dave
Stoldt, General
Manager |
Program/ |
Sleepy
Hollow Facility Operations |
|
|
|
Line
Item No.: |
2.3.1
- F. & G. |
|
|
||||
Prepared
By: |
Kevan
Urquhart |
Cost
Estimate: |
$276,000 |
|
|
||||
General
Counsel Review: N/A |
||||
Committee
Recommendation: The Administrative
Committee reviewed this item on September 12, 2011 and recommended
_______________. |
||||
CEQA
Compliance: N/A |
||||
SUMMARY: The Board will consider authorizing staff to accept
an impending grant from the California Department of Fish and Game (CDFG), and
use these funds for sole source contracts with List Engineering (LE) and Denise
Duffy & Associates (DDA) to accomplish the next phase of engineering
design, environmental compliance and permitting for the Sleepy Hollow Steelhead
Rearing Facility (SHSRF) Sediment Control and Intake Retrofit Project, in
expectation of proceeding to the final construction phase in 2012. The intake retrofit is necessary to expand
the operating season for the SHSRF, as required by the National Marine
Fisheries Service (NMFS) for our pending Federal Endangered Species Act (ESA),
Section 10 Permit, and to ensure the SHSRF can continue to operate under
increased sediment loads after the Removal and Re-Route of San Clemente Dam is
accomplished in 2013-2016.
RECOMMENDATION: District staff recommends that the Board
authorize the General Manager to enter into a grant agreement with the California
Department of Fish and Game to design, conduct environmental compliance review,
and secure permits for the SHSRF Sediment Control and Intake Retrofit project
at a cost not-to-exceed $276,000, and authorize these funds to be used for sole
source contracts with List Engineering for final project design, and Denise
Duffy & Associates for environmental compliance review and permitting.
BACKGROUND: This grant is
being funded by California American Water (Cal-Am)/NMFS ESA Section 9
Settlement Funds held by CDFG. The sole
source contracts to be issued to List Engineering and Denise Duffy and
Associates are 100% reimbursable.
The District
completed the “Interim Retrofit Project” in 2003, which was designed to improve
the intakes at the SHSRF and harden them against increasing sediment loads
derived from the changing hydrology and operations of San Clemente Dam (SCD). This project was
acknowledged to be a stop-gap measure, as the full project
envisioned at the time was too expensive for the District to pursue on its own,
and the outcome of SCD removal or reinforcement was uncertain at the time. The Board directed staff to find State and
Federal partners or other grant funds to aid in the proper completion of the
Intake Retrofit. The original plan for
the Intake Retrofit was produced at District expense by List Engineering on February
14, 2003, and an update to: (a) address current environmental and operational
conditions and (b) focus the final conceptual design, was funded by the
District and completed by List Engineering on May 11, 2010. CDFG has set aside the necessary grant funds
to pay for the construction of the SHSRF Sediment Control and Intake Retrofit
Project, but requires that it be done in two steps. First, the District must
apply for design, environmental review and permitting support. Once those products are delivered and
reviewed by CDFG and NMFS, they can be sure of the final construction costs,
and will grant the funds for the final construction phase.
District staff are trying to expedite funding approval of the first
phase of design, environmental compliance review and permitting, through review
and approval by the Board, so that contracts can be let to the contractors as
soon as CDFG grants the funds. The project
must be underway, and preferably completed by the summer of 2012, or the SCD
Removal/Re-Route Project may take precedent and sideline completion of this project
until 2016 or later. CDFG cannot
guarantee to continue to hold the currently reserved funds for this project
past 2012. Delays in implementing the
project may result in a loss of grant funds.
The timelines for the final design, environmental review and permitting
phase require that they begin as soon as possible to be able to initiate actual
construction work in 2012. For this
reason District staff are bundling both the Grant
receipt and subcontractor expenditures in one Staff Note, and are selecting
experienced local contractors for the first phase. The next and final construction phase will be
subject to the competitive bidding process.
The DRAFT
subcontractor proposals shown in Exhibits 1-A,
1-B, and 1-C
are still subject to revision, after they are reviewed by CDFG, and their
combined value, plus a 20% contingency for any potential near-term revisions is
included in this not-to-exceeded request for $276,000 in 100% reimbursable
spending authority.
The District’s
2011-2012 Budget for Sleepy Hollow Facility Operations includes a Planning and
Design Line Item 2.3.1 - F. for $190,000 and an initial phase of construction
Line Item 2.3.1 – G. for $280,000. Thus,
in combination, spending authority exists for this request in the current
budget.
IMPACT ON STAFF/RESOURCES: The staff person responsible for
administration of the contracts and supervision of the work is Kevan Urquhart,
the District’s Fisheries Supervisor. He
will be advised on project management by District Engineer, Larry Hampson, and
Environmental Project Manager, Henrietta Stern.
EXHIBITS
1-A DRAFT Sleepy Hollow Steelhead Rearing
Facility Renovation Design Proposal from List Engineering
1-B DRAFT Sleepy Hollow Steelhead Rearing
Facility Renovation Design Proposal Budget from List Engineering
1-C DRAFT Proposal For Environmental
Services For The Sleepy Hollow Steelhead Rearing Facility Project from Denise
Duffy & Associates
U:\staff\word\committees\Admin\2011\20110912\01\item1.docx