ITEM: |
ADMINISTRATIVE COMMITTEE |
||||
|
|||||
2. |
Consider BUDGETED expenditurE FOR PUMP MAINTENANCE at sleepy
hollow steelhead rearing facility |
||||
|
|||||
Meeting Date: |
September 12, 2011 |
Budgeted: |
Yes |
||
|
|||||
From: |
David J. Stoldt General Manager |
Program/ Line
Item No.: |
Aquatic
Resources/ Fisheries 2-3-1-I |
||
|
|
|
|
||
Prepared By: |
Cory Hamilton |
Cost
Estimate: |
$6,408.57 |
||
|
|||||
General Counsel Review: N/A |
|||||
Committee Recommendation: The Administrative Committee reviewed on September
12, 2011 and recommended . |
|||||
CEQA Compliance: N/A |
|||||
SUMMARY: In late July, staff started preparation of the
Sleepy Hollow Steelhead Rearing Facility (SHSRF) for the upcoming 2011 Rescue
Season. During this time, intake pumps are turned on and tested. Intake Pump #2 failed. The moisture control unit in the motor
control was flickering on and off. This
meant that either moisture has entered the pump seal or that there is simply
moisture in the electrical line. JM
Electric was called in to diagnose whether the pump indeed failed and needed to
be removed or if an electrical component had failed. The diagnosis determined there was moisture
in the electrical lines. JM Electric
replaced wires and waterproofed all connections. Intake Pump #2 continued to fail after
replacement of wires. This meant that there was still moisture in the wire
going down to the pump. Staff pulled Intake
Pump #2 and replaced it with the back-up pump.
JM Electric then wired and waterproofed all connections on replacement
pump. This work was deemed necessary in order to have SHSRF online before fish
rescues started, therefore, this was an emergency situation and work was authorized
before fish could be brought into the facility.
RECOMMENDATION:
Staff recommends that the
Board approve this expenditure. These funds are within the allocation
identified for this purpose in the Fiscal Year 2011-2012 Budget, under line
item 2-3-1 I, “Intake/cold well repair & maintenance” for $19,500.
2-A JM Electric Invoice for intake
pump repairs