ADMINISTRATIVE COMMITTEE

 

2.

Consider Expenditure of Budgeted Funds to AUTHORIZE Contract with DENISE DUFFY AND ASSOCIATES TO PREPARE CEQA DOCUMENTS FOR WATER PROJECT 2

 

Meeting Date:

December 5, 2011

Budgeted: 

Yes

 

From:

David J. Stoldt,

Program/

1-2-1-B

 

General Manager

Line Item No.:

3c. ($26,500)

3d. ($40,000)

 

Prepared By:

Joe Oliver

Cost Estimate:

 

 

reimbursable (Cal-Am)

Update on 12/5/11

 

General Counsel Review:  N/A

Committee Recommendation:  The Administrative Committee reviewed this item on December 5, 2011 and recommended ___________________.

CEQA Compliance:  N/A for contract; supports CEQA compliance for WP2.

 

SUMMARY:  The Monterey Peninsula Water Management District (MPWMD or District) and California American Water (Cal-Am) are jointly pursuing Phase 2 of the Aquifer Storage and Recovery (ASR) program, known as “Water Project 2” (WP2) at the Seaside Middle School (SMS) site.  SMS Well #1 was drilled in 2010 under a California Environmental Quality Act (CEQA) exemption for a test project.  Full CEQA compliance is needed for SMS Well #1 to be deemed a permanent water supply project, along with construction of a new SMS Well #2, planned for summer 2012.  These two wells, along with appurtenant facilities, will comprise Water Project 2.

 

Due to easement conditions imposed by the Monterey Peninsula Unified School District, certain well construction activities may only occur when school is not in session (June through early August 2012).  To meet this timeline, assistance by consultants is needed now to prepare CEQA compliance documents in early 2012.  Based on the site-specific project components, the CEQA documents will either be an Addendum or a Supplement to the ASR Phase 1 Environmental Impact Report completed in 2006.

 

Exhibit 2-A provides an overview of the WP2 project description, which was provided to Denise Duffy and Associates (DDA) in late November 2011.  Due to printing deadlines for the December 5, 2011 Administrative Committee (AdCom) meeting, a proposal from DDA is not attached and an update on the schedule and cost estimate will be provided at that meeting.  DDA was selected as a sole-source consultant due to time limitations and the firm’s prior work and familiarity at the Water Project 1 site. 

 

RECOMMENDATION:   District staff recommends authorization to retain DDA to prepare CEQA compliance documents for WP2.  The cost estimate for this planned work will be discussed at the December 5, 2011 AdCom meeting.  If approved by the Board on December 12, 2011, staff will prepare a contract with DDA immediately.  The requested funding authorization will include a contingency amount which would only be utilized based on written request and authorization by the District.

 

IMPACT ON STAFF/RESOURCES:  Planning, design, construction and operation of the WP2 facilities are ongoing significant District commitments, as reflected in the MPWMD FY 2011-12 budget under Program 1-2-1-B.   Line Item 3c identifies $26,500 for CEQA environmental review support and Line Item 3d includes $40,000 regulatory agency permitting, which are the two line item sources directly applicable to this work (account 4-7860.06).  At this writing (11/30/2011), it is unknown how much will be assigned to which of these line items to cover the DDA scope of work.  Alternately, budgeted funds could be assigned from the project contingency and a mid-year budget adjustment could be made in early 2012 if needed.  District staff will continue to coordinate with Cal-Am on all work elements applicable for direct reimbursement.

 

EXHIBITS

2-A      Summary of preliminary project specifications for Water Project 2

 

 

 

 

 

U:\staff\word\committees\Admin\2011\20111205\02\item2.docx